August **** - February 2021
2003
2010
2017
2017
2018
2014
2008
2016
Mlungisi Petros Buthelezi
*** ********** **** ********* ****.
076-***-**** admbly@r.postjobfree.com
Objective
I seek challenging opportunities where I can fully use my skills for the success of the organization. Experience
AVENG GRINAKER LTA
CONCRETE FOREMAN
I joined the above company from as a general worked but through my perfomance and potential ended up as Concrete Foreman. From 2006 up to 2010 I worked 3 projects as a general worker, shutter hand grade 3, shutterhanf grade 2 up to Section leader(Supervisor).Than from 2010 up to 2018 I got promoted to be a Junior foreman up to Concrete foreman and I worked 7 projects. I always make sure that I reach my targets as per my Site engineers planned and I committed my self in to the job as a foreman. MIKE BUYSKES CONSTRUCTION.
Finishing Foreman
I alsa joined the above company as a foreman but I was full time on finishing. I only worked 2 Projects with them and my contract was unfortunately expired because of company economy. Education
Pince Bhokwe high School
Senior Certificate
Grade 12
Impact College
BAC & BAA(First Aid)
Certificate
CONCRETE INSTITUTE
INTRODUCTION TO CONCRETE
Certificate
CONCRETE INSTITUTE
CONCRETE PRACTICE
Certificate
INSTITUTE FOR WORKING AT HEIGHT.
FALL ARREST TECHNICIANS
Certificate
AVENG GRINAKER LTA TRAINING CENTER.
NATIONAL CERTIFICATE: CONSTRUCTION (level 2)
Certificate
GRINAKER LTA CIVIL TRAINING CENTER.
GENERAL EDUCATION AND TRAINING IN CONSIDERATION.
Certificate
PERI FORMWORK AND SCAFFOLDING TRAINING CENTER.
FORMWORK TRAINING (PERI SYSTEM)
Certificate
Projects
Shutter hand gr 3(Avenge)
Form work support, Shuttering, using power tools.
Contract value: R50 Million
Duration: 1year.
Shutter hand gr2 (Aveng)
Form work, Shuttering, using power tools and setting out. Project: Silver star Casino
Contract value:R648,9 Million
Duration:18 Months.
Supervisor (Avenge)
Team leader, reading engineering drawing, setting out and using dumpy level. Project: Samrand Computer Center.
Contract value:R717 Million
Duration: 1 year.
Junior Foreman (Aveng)
Team leader, setting out, reading engineering drawings, using dumpy level and theodolite,training guys and DSTI etc.
Project: Soccer City Stadium
Contract value:R3,3 Billions
Duration :6 Months
Junior Foreman (Aveng)
Team leader, reading engineering drawings, setting out, DSTI, Using dumpy level and theodolite, organising concrete and etc.
Project: MTN Switch data center
Contract value:R50,5Million
Duration: 7Months
Junior foreman (Avenge)
Reading engineering drawing, team leader, setting out, using dumpy level and theodolite, DSTI, training guys etc
Project: Telesure Head Quarters
Contract value:R800 Million
Duration: 1 year
Junior Foreman (Avenge)
Reading engineering drawings, Setting out, Team leader, Sub contractors managing, DSTI, using dumpy level and theodolite, etc
Project: DEPARTMENT OF ENVIRONMENT AFFAIRS
Contract value:R744Million
Duration: 6Months.
Junior Foreman (Aveng)
Team leader, reading engineering drawings, Setting out, using dumpy level and theodolite, DSTI, Concrete organising and team managing.
Project: Coda world
Contract value: R175Million
Duration:14Months
Junior Foreman (Aveng)
Team managing, training guys, reading engineering and architect drawings, Setting out, Using dumpy level and theodolite, DSTI, Concrete ordering, Sub contractors managing. Project: Mall of the South
Contract Value:R942 Million
Duration: 16 Months
Concrete foreman (Aveng)
Team managing, reading engineering and architect drawings, setting out, Staircases, Sub Contractors managing, Safety file, Life line installation, Concrete ordering, DSTI, Using dumpy level and theodolite, Power tools Check list,Risk Assessment, PPE Check list for my team. Project: Village walk(The Marc shopping center)
Contract value: R1,7Billion
Duration: 2Years 3months
Finishing foreman (MBC)
Oversees the whole project, Site logistics managing, Planning with Superiors, Approving Hours for the guys, Quality, Approving units from block A up toblock C, Sub contractors managing(Painters, Tillers,Plumbers, Form work, Filling and Partition and cleaners. Project: VUJADE
Contract value: R80 Million
Duration: 6Months
Finishing Foreman (MBC)
Team managing, Sub contractors managing (Painters, plumbers, Tillers, Bulcon installers, Air- conditioning, cilling and partition, Shopfitters, brickwork and plaster, quality, fire protection),Concrete structure (Shoprite and Cash build), external works (Fences and all gates for the mall, ccv cameras bases and etc)
Project: MALL OF TEMBISA
Contract value: R800 Million
Duration: 1 year.
Language
Zulu English Sesotho Pedi Xhosa
Zulu: Read, speak and write English: Read, speak and write Xhosa:Read, speak and write Pedi:Speak Sesotho:Speak.
Interests
Church, reading news papers, soccer
Activities
Watching sport over a weekend, Church on Sunday
Personal Details
Date of Birth : 19/12/1983
Marital Status : Single
Nationality : South African
Reference
Dumisani Maluleka - "Aveng"
Project Manager
Neo Masimeni - "Aveng"
Contracts Manager
Sibinoso Phakathi - "Mike buyskes construction"