Amr M. Magdy El-Serafy.
UAE: Fujairah.
Mob.UAE +971-**-**-**-***)
Mob.Egypt +2-010-***-**-**)
E-mail: ***********@*****.***, ***********@*****.***, ***********@*******.***,
I- ACADEMIC STUDIES :
* Professional Diploma in
”Contractual & Legal Aspects in Construction Industry”-
at the A.U.C. (The American University In Cairo), May 2005.
* High Study Diploma in
” Construction Management”- Faculty of Engineering-
Cairo University, June 1998.
* B.Sc. Civil Engineering -Construction Department -
Ain Shams University, June 1992. Project: Reinforced Concrete.
* High School Diploma Collège De La Salle - El Daher, June 1987.
II- SKILLS :
Professional and practical use of Project Management Software:
-Primavera Project Planner (P3 Ver.3.1).
-Primavera Project Planner Enterprise for Construction (P3e/c Ver.6.1).
-MS Project.
-Expedition.
-Microsoft Office Package.
-AUTOCAD2006.
III- LANGUAGES :
ARABIC : MOTHER TONGUE.
FRENCH : EXCELLENT.
ENGLISH : EXCELLENT.
SPANISH : GOOD.
IV- EXTRA COURSES :
1. Professional Courses:
2010 –PMP Preparation Course in Project Management- CHICAGO Management Training Institute, Dubai, UAE.
2008 –Project Management Applications Tools & Techniques using Primavera Project Planner Enterprise for Construction (P3e/c Ver.6.1). CMCS Management Training Institute, Dubai, UAE.
1997 -Microcomputer Applications In Project Management
(Using Primavera Program under Windows)- Faculty of Engineering-Cairo University, Egypt.
-Microcomputer Applications In Project Management
(Using Primavera Program under DOS) at AUC.
The American University In Cairo, Egypt.
1991 -Cad & Staad Programs, Faculty of Engineering- Ain Shams University, Cairo, Egypt.
2. Languages Courses:
1987 “Alliance Francaise”,The International Language & French Civilization School Paris (Ecole Internationale De Langue Et Civilization Francaise Paris).
1985 Diploma In English Writing & Conversation “Interlink School”, Bournemouth, England.
1984-1985 Attended several courses in English conversation at The “B.B.C” The British Book Center, Alexandria.
V- PREVIOUS EXPERIENCES:
Since 01/08/2009- till now
ELWAN GROUP (ICG NFRASTRUCTURE CAPITAL GROUP FZC) - UAE
FUJAIRAH OFFICE
- Execution of the Waste Water Treatment System Expansion I for the City of Fujairah and its Environs.
Projects:
- Expansion I of the Wastewater Treatment System for the City of Fujairah and its Environs (WWTS) which shall cover:
o WWTP: Addition of two trains with capacity of 16,000 m3/d and its associated structures.
o WWCN: Addition of 30 km of pipeline to connect 60,000 of people to the system.
Project Manager for ELWAN GROUP (ICG FZC).
1.1 The Project Manager, as head of the Expansion-I Implementation Unit (EIU) shall co-ordinate and report to Chief Technical Officer (CTO) on EIU’s responsibilities and duties as follows:
a) overall administration of Expansion I Works and shall develop systems for communications of coordination between design, construction and supervision of Expansion I teams;
b) communicate and liaise with OE, Consortium and other parties for Expansion-I activities for:
i. WWCN
ii. WWTP
iii. EDN
iv. AHC
c) represent the Owner in all Technical issues, written and verbal correspondence, issuing notices, instructions, orders, certificates, information and all other communications with Consultant, Consortium and other parties, as well as taking decisions as and when necessary on technical matters related to the Expansion-I Works;
d) approve and counter approvals of technical submittals of the Consortium after OE’s review and verification;
e) clear Variation Orders and Interim Payment Applications of Consortium & OE in coordination with CTO; and
f) administer all supervision tasks, monitoring progress of all day to day activities of Works and giving guidance and co-ordination required for Consultant & Consortium.
Since 01/08/2008- 31/07/2009
MASHAREA PROJECT MANAGEMENT - UAE
HEAD OFFICE
- MASHAREA Project Management (MPM) is an International Project Management Firm based in Egypt with branches in UAE, KSA and eventually in Oman and Qatar.
Projects:
- Projects varies from Horizontal Projects like The SEASONS to Vertical Projects like The ONYX, The BOULEVARD Towers, The JUMEIRAJH VILLAGE SOUTH Tower, DOWN TOWN JABAL ALY Tower, DUBAI WATER FRONT Tower, JABAL ALY CRESCENT Tower .
Projects Control Systems Manager for UAE Branch.
Supervise all the UAE Branch Projects;
Supervise and lead a team of Planners;
Attend Meetings with the Clients, Contractors and Management;
Coordinate information with other Departments;
Held Technical Scheduling Meetings with Projects Contractors Planners;
Prepare of the UAE Branch All Projects Master Programme of Works;
Supervise and Review the preparation of the Clients Master Programme;
Review, Analyze and Evaluate Time Impact Analysis Claims;
Prepare Projects Internal Indicators;
Prepare & Submit Monthly Progress Reports for the UAE Branch Projects;
Evaluate, review and approve projects time schedule & periodical progress reports submitted by Contractors;
Supervise and Review all projects resources and submittals, and advice Contractors in case of any deviation of the target with the corrective action required; and
Supervise the issuance of Cost Control Reports.
Since 01/06/2007- 31/07/2008
OGER ABUDHABI- UAE
Project name : THE NEW CAMPUS OF THE UAE- UNIVERSITY, AL-AIN.
Project Objective : Construction of the New Campus of the UAE University in Al-Ain.
Project Description:
- Stage 1 consists of the 25 buildings including (Female Residence, Service Compound, Girls Faculties of Engineering, Humanities and Social Science, General Studies, Business and Economics and Shared labs and Mosque).
- Stage 2 consists of the Administrative building of the University, the Great Hall and the library, with state of the art design and finishes.
- Stage 3 consists of 10 buildings including (the Male Village, Dining, Sports, Mosque, Service Compound, Male Faculties of Engineering, Humanities and Social Science, General Studies, Business and Economics).
Project Controls Manager.
Supervise and lead a team of Planners;
Attend Meetings with the Client, Subcontractors and Management;
Coordinate with Several Project’s Departments to get the correct information at the right time;
Held Technical Scheduling Meetings with Project Subcontractors Planners;
Prepare Client's Master Programme for the project;
Prepare & Submit Cause & Effect Time Impact Claims;
Prepare Projections on Project Finish Date according to the Project Performance Index;
Prepare Project's Internal Indicators;
Prepare & Submit Monthly Progress Reports for the Project;
Evaluate, review and approve projects time schedule & periodical progress reports submitted by Subcontractors;
Revise all project resources and submittals, and advise subcontractors in case of any deviation of the target with the corrective action required; and
Supervise the issuance of Cost Control Reports.
Since 01/03/2006- 31/05/2007
PROJACS INTERNATIONAL- Qatar
Project name : THE PEARL- Qatar.
Project Objective : Development of the PEARL Island.
Project Description:
- The project consists of 4 individual towers 20 to 36 floors over podiums.
- The project is a part of a master development created by United Development Company located in Doha. The development is situated on a man-made island of reclaimed land offshore the Arabian Peninsula state of Qatar.
Project Controls Manager.
Prepare & Submit Cause & Effect Time Impact Claims.
Prepare Projections on Project Finish Date according to the Project Performance Index.
Prepare Project's Internal Indicators.
Preparing & Submitting Monthly Progress Reports for the Project.
Preparation of Client's Master Programme for the project.
Evaluate, review and approve projects time schedule & periodical progress reports submitted by Subcontractors.
Revise all project resources and submittals, and advise subcontractors in case of any deviation of the target with the corrective action required.
Since 01/08/2005- 28/02/2006
FLUOR International Limited- PMCM
Project name : The New Campus of the American University in Cairo, New Cairo City.
Project Objective : Development of the American University.
Project Description:
- 300 million USD Project.
- Built area 180,000 m2 set on 260 Acre (1,055,000 m2) of Land.
- Full Time student enrollment of 5,500.
- The project consists of :
(President Housing, AUC Park & Square, Humanities & Social Sciences School, Sciences& Engineering School, Business, Economics & Communications School, Core Academic Center, Library, Campus Center, Student Housing, Indoor Sports Facilities, Desert Development Center, Physical Plant, Faculty Housing, Central Spine, Utility Plant, Administration Building, Site& Infrastructure).
Planning & Scheduling Manager.
Prepare Project's Internal Indicators.
Preparing & Submitting Monthly Progress Reports for the Project.
Preparation of Client's Internal Programme for the project.
Evaluate, review and approve projects time schedule & periodical progress reports submitted by Contractors.
Revise all project resources and submittals, and advise Contractors in case of any deviation of the target with the corrective action required.
Evaluate Contractors Time Claims.
Prepare & Submit Cause & Effect Time Impact Claims.
Since 01/10/2004- 31/07/2005
Murray & Roberts International
Project name : San Stefano Grand Plaza Complex.
Project Objective : Improve Alexandrian Community.
Project Description:
- 80 million USD Project.
- High Rise Building (30 floors) two towers linked by steel structure bridge.
- Superstar Hotel.
- International Standard Commercial Mall.
- Residential Flats.
Planning & Scheduling Manager.
Lead a team of (4) Planners.
Prepare & Submit Cause & Effect Time Impact Claims.
Supervise Preparing & Submitting Monthly Progress Reports for the Project.
Supervise Preparation of Short Term Programmes for the project.
Evaluate, review and approve projects time schedule & periodical progress reports submitted by Subcontractors.
Revise all project resources and submittals, and advise subcontractors in case of any deviation of the target with the corrective action needed.
Since 01/10/2003- 30/09/2004
Engineering Consultants Group S.A. (E.C.G.)
Project name : Smart Village.
Project Objective : Enhance& Develop IT Community.
Project Description:
- Ministry of Communication Administrative Buildings.
- Smart Village Administrative Buildings.
- Infra Structure of the Smart Village.
Project Controls Manager.
Evaluate, review and approve projects time schedule & periodical progress reports submitted by Subcontractors.
Revise all projects resources and submittals, and advise subcontractors in case of any deviation of the target with the corrective action needed.
Prepare & Submit Monthly Progress Reports for the Projects.
Since 01/10/2002-30/09/2003
ELAttal Group Brothers.
Project name : Malaysian Student Hostel, Abbasiah-Cairo.
Project Objective : Structural Repair, Rehabilitation& Renovation of Malaysian Student Hostel.
Project Description:
- Repair of (4) Buildings with total of (23) Floors.
- Repair of more than (300) columns, (2,000 m2) slabs.
- Rehabilitate the buildings by redefining the spaces to upgrade the existing buildings to maximize utilization.
- Create new Scope of using the buildings as "Cultural Center" for the Malaysian community, including: (Embassy Educational Division center, Theatre, Computer Lab., Health Center, Clinic, Laundry).
Project Controls Manager.
Contribute, review & issue of Project Budget, Time Plans and Cost Control Reports.
Supervise the implementation of the civil works.
Review the Project Implementation Plans & Progress of the ongoing projects and provide inputs to improve overall project management by identifying any constraints or problems in advance, and report back to the Top Management - with recommendations for corrective actions- to resolve problems.
Organize appropriate management training for the project staff and implementing "clinic workshops" on specific matters concerning the project performance.
Participate in the supervision and contribute to the preparation and updating of project related documents.
Since 01/10/2001- 30/09/2002
KOLALY ENGINEERING.
Project name: Ministry of Communications& IT
Smart Village, Cairo.
Project Objective : Construction of a new Building for the Ministry of Communications & IT Technologies within the new environment at the Smart Village in Egypt.
Project Description:
- Construction of (4) stories building for the ministry over 5,000 m2 of land.
- The façades of the building consist of Structural Glazing having the shape of an Inverted Incomplete Cone beside a Pyramid.
- The building included all Electromechanical Facilities such as (Air condition, Lifts, Closed Circuit TV, Access Control, Fire Alarm, Fire Protection …etc).
Project Management Officer.
Contribute, review & issue of Project Budget, Time Plans and Cost Control Reports.
Supervise the implementation of the civil works.
Issuing Periodical Progress Reports.
Contributing in Regular Meetings with the Project Manager, Owner Representative and Consultants to review Project Progress& monitoring project's Procurement, submittals status as well as discussing and resolving any problems concerning the project.
Since 19/12/1998-30/09/2001
Bin Ladin International Egypt.
Project name : El-Rehab project- New Cairo City.
Project Objective : Constructing of a new City outside the Capital to encourage citizens to live and establish a new community.
Project included:
- Construction of 270 buildings (5 stories) in sectors B2 & B4.
- Construction of 336 villas.
- Construction of the following utility buildings with its Infrastructure:
(Hospital – Mosque – Shopping center – Language schools – Club).
Senior Planning & Cost Control Engineer.
Imposed master target plan according to hand over dates, including all phases of construction (turnkey project).
Reviewed project planning and schedule documents on progress. (Following-up site activities)
Coordinating engineering or construction problems with superintendents.
Prepared projections and schedules for different site Resources
( Manpower – Material delivery schedule – Subcontractors distribution – equipment plans )
Data evaluation and analysis and project management reports preparation.
Preparing Monthly Cost Reports.
Preparing Monthly Owner’s Invoices.
Since 1/10/1995 – 15/12/1998
Katameya Real Estate Investment and Dev. Company.
Project name : Katameya Heights - New Cairo City.
Project Objective : Constructing of an International Golf Resort with Residential villas.
Project included:
- 27 holes golf course.
- Country club, 280 residential villas & 6 artificial ponds, over 350 feddans of land.
Technical Office Assistant Manager.
- Construction management and time scheduling
- Progress of works reports.
- Organizing and Developing Information Systems for the project.
- Quantity surveying, shop-drawings, cost estimation contribution.
- Supervising the Civil and Construction works & Quality control.
Since 31/1/1994 - 9/9/1995
Soletanche Bachy Egypte
S.B.E.(Sub-Contractor Of Compenon Bernard
S.G.E. J-V Of Civil Works).
Project name: Greater Cairo Underground Metro Line No2.
Site Engineer
- Execution and Supervision of all the activities and equipments on site including the mixing plant unit of jet grouting of all the stations on the line.
N.B:(special pump 400 bars pressure).
Since 18/10/1993 - 31/12/1993
Petroleum Projects& Technical Consultations Co. (Petrojet).
Project name : GAPCO oil fields.
Marine Survey Engineer.
Since 10/2/1993 - 30/9/1993
El-Saed General Contracting Constructions Company.
Project name : El-Salam Housing Project.
-The Project Consisted Of Constructing 20 Buildings At El-Salam City.
Site Engineer.
Since 15/8/1992 - 31/1/1993
Misr Sanitary Engineering Company (Missan).
Project name : Waste Water Projects Luxor & Hurgada..
Design Engineer.
-The Sanitary Projects of Hurgada & Luxor Cities.
Designer of Concrete Structures (Houses, transformers, shelters, trenches...etc).
VI- PERSONAL DATA :
Name : Amr Mohamed Magdy El-Serafy.
Date of Birth : 3rd of July, 1969.
Nationality : Egyptian.
Religion : Moslem.
Marital Status : Married.
Military Status : Exempted.
Address : 106, El-Fath City,App No 42 ,
4th Floor, Nasr City, Cairo,Egypt .
Cellular : + (971-***-****** (UAE)
: + (201-***-***** (Egypt)
Telephones : + 202-***-**** (Egypt)
+ 202-***-**** (Egypt)
+ 202-***-**** (Egypt)
E-Mail : ***********@*****.*** (Personnel)
: ***********@*****.*** (Personnel)
: ***********@*******.*** (Personnel)