Post Job Free
Sign in

Engineer Manager

Location:
United States
Posted:
September 15, 2012

Contact this candidate

Resume:

Curriculum Vitae

Eng. WAEL SALEM

+201*********

*******@*****.*** *.*******@*****.***

Profile:

** ***** ** ********** ** Constuction and Comissioning for Transformers, MCC, S.G., DCs, PLC, instruments and control

systems. Gained experience by working in international projects - constructing and putting to operation- power stations,

LNG, Oil & Gas projects, and water treatments plants. Has the knowledge of international standards and codes such as

IEEE, IEC, and NEC...etc.Flexible and highly capable person, Patient, disciplined, and proven team player. Able to

communicate at all levels, energetic and enthusiastic, highly committed and self motivated, results and profits oriented,

well organized and have a good time management skills and proven operational decision making and problem solving

skills, This includes performing design, management and overall coordination of complex electrical engineering projects,

including providing technical guidance and/or supervision to contract, consulting, and/or City staff to monitor project

progress and conformance with established plans and specifications; develops plans, specification, cost estimates and

contracts for major projects.

Experiences:

Abo Qir Thermal Power Plant Unites 6 & 7

2 x 650 MW Gas/Oil Fired Unites

Electrical, I&C Construction Manager of CP-117 Feb. 2012 - Till now

Sidi Krir Power Station 750 MW Combined Cycle

Electrical, I&C Maintaenance Manager Sep. 2010 - Dec.2011

Sidi Krir Power Station 750 MW Combined Cycle

for and on behalf TTC / TPSC consortium

Dec. 2009 - Aug. 2010

Instruments and Control S.Engineer (then hired as)

Electrical, I&C Commissioning Manager of CP-117 & CP-118

2 Gas Turbine & 1 Steam Turbine

- The contracts CP117 & CP118 responsibilities include the commissioning of switchgears,main and auxiliary tranf.,

load centres and MCCs, DCS & PLC Loop test I/O module, all cables and electrical system for pumping station, trash

Rack, cooled wire checking, hot and function tests for all systems.

- Prepare commissioning procedures, DCS function check, operating and field trouble shooting DCS function on BOP

system, time schedules and reports and interface with client for approvals and handing over of electrical sys.

- To define the individual procedures for calibration and testing of the plant instruments.

- Ensure instruments(Pressure, Temp.,liquide level, control valves,..etc.)are calibrated/tested to specification procedures.

- Prepare and activate design and document handling procedure.

- Communicate with clients and follow up project meetings.

- Create time schedules and work plans and strategies.

- Follow-up design team activities.

TUNA field Development Project

Petrobel (Balayiem Petrolum Company)

Mediterranean

KAHROMIKA deputation

Instruments Engineer (Part Time) Sep. 2009 - Nov. 2009

Petrobel has started gas production from Tuna field in the Temsah concession off Eghypts' Mediterranean coast .

Tuna has been developed by a new four leg platform in arround 80 m (262 ft) of water with three production wells and 14

- Prepare instruments calibration and installation procedures, function check, operating and field trouble shooting.

- To define the individual procedures for calibration and testing of the plant instruments.

- Ensure instruments(Pressure, Temp.,liquide level, control valves,..etc.)are calibrated/tested to specification procedures.

- Prepare and activate design and document handling procedure.

- Communicate with clients and follow up project requirments.

- Create time schedules and work plans and strategies.

- Follow-up design team activities.

EL-Atf Power Station 750 MW Combined Cycl

KAHROMIKA

Misr Co. mechanical and Electrical Projects

Under Instruction of TOSHIBA

plant systems & service corporation

for and on behalf TTC / TPSC consortium

Construction Manager of Electrical work CP-117 Sep. 2008 - Nov. 2009

2 Gas Turbine & 1 Steam Turbine

- Install 3 Main Transformer & 2 Auxilliary Transformer - Install 2 Generator Circuites Breaker GCB -

- Isolated Phase Bus Duct IPB for CTG#1 & 2 and for STG -

- Load center unit substation, Medium voltage switchgear, 400V Motor Control Center (MCC) -

- Electrical monitoring control system (EMCS), Distribution Control System & Electrical Equip. Room Cabinet and Panel

Raceways, Conduites and Cables for CTG#1 & 2, Transformer Area, STG Turbine building, HRSG 1&2 Aera, Control

Building, Circulating Water Pump House Electrical Building, Pipe Rack & Yard area & Miscellaneous facilities .

- Install & Check Fire Alarm System for all station for CP-118.

- Grounding System.

- Transformer Protective Relaying System.

- Follow up the Q.C. for the hole contract.

- Install All Instruments at all area (CTG#1, 2, STG, CWP, CCWP etc.).

Shoubra El-Khiema Power Station Project

Environmental measures and efficiency improvement

Siemens AG

Construction Manager Nov. 2006 - Aug. 2008

Steam boiler control (4X315 MW - Steam Generation) Siemens AG

- Working of SF6 220 KV C.B and vacuum 6.3 KV C.B.

- W orking and testing of transformers (410, 50, 32, 1.3) MVA.

- Working of 6.3 KV, 400 V, DC motors, MCC, Load centers, and AC & DC motors control circuit.

- Working of excitation sys. & A.V.R and generators (overhaul maintenance).

- W orking of gas turbine control.

- Install Working in Boiler Water Pumps Control System (Gas & Steam).

- Install & Check Fire Alarm System & Fire Fighting System for all 4 Unites.

- Install & Check Sound System for all Power Stations.

- Maintenance of battery charger and inverter.

- Fiber Optics Systems.

- Doing the total progress of the project.

Abu Dhabi National Construction ADNC ( UAE)

Senior Projects Engineer Dec. 2005 - Nov. 2006

ADWEA Taweelah B2 Power Plant with Bechtel.

ALJABER Energy Service Construction Co. - AJES

Instruments & Elec. Site Engineer Mar. 2004 - Nov. 2005

Swiss Company for Construction

Main Boards & Control System

Instruments Engineer Feb. 2001 - Dec. 2002

Activities

- Preparation of specifications and contracts, Generating detailed design, Reviewing contractors technical design

submittals against contract requirements, codes and requirements for the interfaces with others.

- Coordinating different contractors scopes of work within the same project.

- Monitor and measure the stable measurement of electric power station.

- The supervision during the installation of DCs, MCCs, SWGR, the instruments at site.

- following up the project schedule.

- The calibration for all project instruments and eguipments as required according to the project specification and the codes

- The preparation of all documentation for all scope of the contract.

- The test activity for alll scope of work.

- W orking in Boiler Water Pumps Control System (Gas & Steam).

- W orking in DCS & PLC Loop test I/O module.

- Raw Water System (WR) & Waste Water System (XW).

Study and Estimate the technical specification of Cairo North Power Station for the following contracts:

- 250 MW Steam Turbine Generator combined cycle for (modules I & II).

- 220 KV – 3150 A Bus Bar, Gas installed switchgear.

- Large Power Transformers rated 314 MVA and 24 MVA 4 * 2000 A – MV switchgear, 4*1333 KVA load center

and 4 * 2000 A – LV switchgear.

- Balance of plant (Transformer protection relays and electric I&C installation).

- Electric (>250 HP) drives & pumps.

Education:

Jun. 2000 – Jan 2001: - Obtain Diploma from New York University in 2000 in Web Designing.

- Obtain Diploma in Internet Marketing - MSI Institute in New York - USA.

Sep.1993 – June 1998: - Bsc. of Electric Power Engineer, Cairo University, Faculty of Engineering.

W ith Excellent Project Grade.

Information Technology Skills:

* Computer skills e.g. Microsoft Office (Win Word, Excel, Outlook and Project Management).

* Hardware & Net Working skills e.g. (System Upgrading, PC Assembling, Trouble Shooting, PC Maintenance and Networking) .

* Internet Programming (HTML+ Advanced, JavaScript).

* Interior Designing with 2D AutoCAD.

* Graphic Designing with Adobe photo shop, Dream Waver and Flash.

Training Courses, Workshops and Certificates:

* Occupational Safety and Health Adminstration -

- Osha General Industry Safety and Health ID. No.:- 30-900******

- Osha Construction Safety and Health ID. No.:- 30-600******

* Safety Training Course at Mitsubishi Haevy Industry -

* Training course on T3000 of Siemens Dcs systems

* Assistant Electric Engineer at American Company ( NYC - USA )

- Follow up of Design and execute electric circuits in buildings

- Responsible for installation with a team

* Assistant Engineer at MARUBENI Corporation- Japanese Co. ( W est Cairo Power Station – Egypt )

- Engineering of steam generator and Turbines

- Monitoring and measuring stable measurement

Personal Profile

Marital Status: Married.

Military status Completed.

Languages: Arabic (Native), English ( Fluent speaking, writing and reading ).

Driving License: Valid Driving License.

DOB: Sep., 15th, 1975.

Activities: Gain many culture and activities through traveling to many countries (USA, Russia,

England, Azerbaijan, China, Syria, Jordan, Lebanon, Tunisia and Morocco).

References:

References and recommendations are available upon request



Contact this candidate