A professional, self-motivated, well-qualified and computer literate Project Executive, with a proven and demonstrable track record and comprehensive experience of the development, regeneration, investment and construction industries. A persuasive communicator, with excellent interpersonal skills, I am commercially aware and have first-rate technical, leadership and management skills. Able to select, direct and motivate teams to achieve and maintain all goals, and I am now looking to continue my career in a demanding position within an established and progressive company.

Comprehensive experience in the construction and operation of Grain Processing Facilities and Power Generation Facilities. Majority of experience lies in the combined cycle, simple cycle, fossil fuel and nuclear facilities.

Experienced in residential, commercial and industrial electrical wiring, repair and maintenance, as well as analog, pneumatic and direct digital controls. Installation/calibration of pressure transmitters, differential pressure transmitters, flow meters, orifice plates, pressure, temperature, and flow control valves.

________________________________________

EXPERIENCE

I have held the following positions on many large-scale mechanical construction projects, including but not limited to: fossil fuel generation stations, co-generation stations, combined cycle generation stations, nuclear generation stations, grain processing plants, chemical plants, gas liquefaction, herbicide plants, pharmaceutical plants, food product plants, equipment manufacturing and other industries.

Project Manager/Mechanical Superintendent: Manage subcontractors, create and update production schedules, meet with customers, Architects/Engineers and review changes, manage multi-crafts personnel and issue and manage change orders.

Project Controls/Scheduler: Fluent with Microsoft Project and Primavera P3 & P6 scheduling software, Primavera Contract Manager as well as SAP.

QA/QC Manager: Fluent with ASME Sec I, IX, 31.1, 31.3, BPE & VIII Div 1 & NBIC codes of construction. Create, assign and update welding procedures, field inspection and verification, travelers, set parameters for thermal heat treatment and machinists, prepare and complete 3 year reviews and welder qualification tests. Create and manage weld maps, heat maps and slope maps etc.

Mechanical Estimator: Assemble T&M, T&M not to exceed, lump sum, cost plus bids on mechanical and structural projects. Fluent with Quick Pen and Wendes mechanical estimating software as well as manual estimating methods.

Field Engineer: Field layout and verification of mechanical systems. Create and submit isometric drawings to engineering and shop fabrication. Create detailed construction drawings from equipment drawings and P & IDs. Fluent with Auto-CAD and COADE software.

Instrumentation Foreman: Installation, calibration & start-up of pneumatic and direct digital controls.

Fabrication Shop Foreman: UA fabrication shop foreman specializing in industrial piping, structural steel, tanks & pressure vessels. Responsibilities include ordering and tracking materials and consumables, equipment purchasing, reviewing and breaking apart drawings for fabrication.

Certified Welder: SMAW, GTAW, MIG, Orbital TIG & Orbital MIG Certification’s

Certified HVACR / CFC Technician: UA certification of CFC qualification. Install new and repair existing commercial and industrial HVAC&R equipment.

Certified Valve Technician: UA certification of valve maintenance training & rebuilding. Rebuild various valves in place to nuclear specifications.

________________________________________

CERTIFICATIONS

Primavera Certifications: Certified in P3, P6 and Contract Manager.

Certified Valve Technician: UA certification of valve maintenance training & rebuilding.

Certified HVACR / CFC Technician: UA certification of CFC qualification. Installation, repair and maintenance of commercial/industrial HVAC&R equipment.

Certified Welder: X-ray quality manual welding ability utilizing the Shielded Metal Arc, Gas Tungsten Arc and Metal Inert Gas processes on various ferrous and non-ferrous materials.

Certified Sales & Service Training: AERCO Boiler Company on Industrial/Commercial non-condensing boiler installation, repair and servicing.

Certified ASME Section VIII, Div. 1 Pressure Vessel Code of Construction: How to interpret and apply this code of construction. Course held by Hartford Steam Boiler Inspection and Insurance Company.

Certified ASME Section IX, Welding Qualifications: How to create ASME Sec. IX welding procedures. Course held by Hartford Steam Boiler Inspection and Insurance Company.

Certified NBIC, Repair and Alterations to Boilers and Pressure Vessels: Interpretation and application of the State of Illinois repair and alteration code. Course held by Hartford Steam Boiler Inspection and Insurance Company.

________________________________________

EMPLOYMENT SUMMARY

Shambaugh & Son, LP Present

Bechtel Frederick, MD 2011-2012

Enerfab, Inc., Cincinnati, OH 2003-2011

Various Contract Positions 2000-2003

General Power Construction Company, East Peoria, IL 1982-2000

________________________________________

EDUCATION

United Association Apprenticeship Peoria, Illinois Graduated 1993

5-year apprenticeship focusing on HVAC&R certified welding, drafting, blueprint reading, installation, repair and maintenance of Industrial/Commercial mechanical systems.

Illinois Central College East Peoria, Illinois Attended 1986 – 1988

Various courses included college algebra, CAD and computer programming, business software applications.

Morton High School Morton, Illinois Graduated 1986

WORK HISTORY

04/20/2012 thru Present

Contractor: Shambaugh & Son, LP

Project Name / Location: Farbest Foods, Inc. Vincennes, IN

Estimated Project Value: $80M

Duties: Project Manager on Design Build Poultry Processing Facility. Senior P6 Scheduler / Planner

01/01/2012 thru 04/01/2012

Contractor: Bechtel

Project: TVA – Bellefonte Unit 1 Sr. Planner/P6 Scheduler.

Estimated Project Value: $4.9B

Duties: Sr. Planner/Scheduler for the Engineering Walk Down efforts to support the 10% Engineering. Assemble estimates for 180 (BOP) systems.

05/01/2011 thru 12/01/2011

Contractor: Bechtel

Project: Florida Power & Light, Point Beach Nuclear Power Station U1 & 2 Extended Power Uprate.

Estimated Project Value: $700M

Duties: Sr. Nuclear Planner / Scheduler within the Project Controls Group. Online scheduling, planning/budgeting activities with the plant operating scheduling with strict adherence to the “T” minus work weeks while planning U1R33 outage (MFIV replacement, main generator breaker added, condenser modifications, feed water heater change out, iso phase bus duct cooling upgrade etc.). Outage duties included maintaining outage schedule, assembling “what if” scenarios and producing month end reports, burn down curves and tracking unit matrix.

02/01/2011 thru 05/01/2010

Contractor: Enerfab, Inc.

Project: Duke- Cayuga Station Spring Outage.

Ameren-Duck Creek Station Spring Outage Planner/P6 Scheduler.

Estimated Project Value: 2M

Duties: Project Manager / Mechanical Planner / P6 Scheduler.

01/01/2011 thru 02/01/2011

Contractor: Enerfab, Inc.

Project: Various Estimates

Assembling firm estimates AEP, Consumers Energy & Duke

Estimated Project Value: 8M

Duties: Mechanical Estimator, Planner / P6 Scheduler.

08/01/2010 thru 12/01/2010

Contractor: Enerfab, Inc.

Project: Kureha/CH2MHILL – Belle, WV

Estimated Project Value: $15M

Design/Build Bio-Degradable Plastics Plant

Duties: Mechanical Estimator / Project Manager / Planner / P6 Scheduler.

04/01/2010 thru 12/01/2010

Contractor: Enerfab, Inc.

Project: Kansas City Power & Light

Estimated Project Value: $8M

Unit 1 Hot Reheat Replacement

Duties: Mechanical Estimator / Project Manager / Planner / P6 Scheduler.

02/01/2010 thru 12/01/2010

Contractor: Enerfab, Inc.

Project: Minnkota Power Cooperative, Inc. – Center, ND

Estimated Project Value: $3M FGD Mechanical Installation

Duties: Mechanical Estimator / Project Manager / Planner / P6 Scheduler.

1/1/2010 thru 08/01/2010

Contractor: Enerfab, Inc.

Project: Citrosuco – Wilmington, DE

Estimated Project Value: $3M Bulk Storage Citrus Plant addition

Duties: Mechanical Estimator / Project Manager / Planner / P6 Scheduler.

09/01/2009 thru 12/01/2009

Contractor: Enerfab, Inc.

Project: ADM Bio-Degradable Glycol Plant. High Pressure Piping Installation.

Estimated Project Value: $1M

Duties: Mechanical Estimator / Project Manager / Planner / P6 Scheduler.

01/01/2008 thru 01/01/2009

Contractor: Enerfab, Inc.

Project: AECI Thomas Hill U-1 SCR SCR Mechanical Installation

Estimated Project Value: $3M

Duties: Mechanical Estimator / Project Manager / Planner / P6 Scheduler.

03/01/2007 thru 09/01/2009

Contractor: Enerfab, Inc.

Project: ADM Bio-Degradable Polymer Plant –Design Build.

Estimated Project Value: Estimated $22M

Duties: Mechanical & Engineering Project Manager / MS Project Scheduler.

2006 thru 03/01/2007

Contractor: Enerfab, Inc.

Project: AEP Mitchell Station Unit #1 & 2 Clean Air Upgrades Outage

Estimated Project Value: $10M

Duties: Mechanical Project Manager / Planner / P3 Scheduler.

2006

Contractor: Enerfab, Inc.

Project: Eli-Lilly T-4 Piping Upgrades

Estimated Project Value: $210,000.00

Duties: Mechanical Project Estimator / Planner/ MS Project Scheduler.

2006

Contractor: Enerfab, Inc.

Project: Eli-Lilly Boiler(s) Installation

Estimated Project Value: $7M

Duties: Mechanical Project Estimator / Planner / MS Project Scheduler.

2006

Contractor: Enerfab, Inc.

Project: AEP Mitchell Station Unit #1 & 2 Boiler Feed water Reroute

Estimated Project Value: $2M

Duties: Mechanical Project Estimator / Planner / P3 Scheduler.

2006

Contractor: Enerfab, Inc.

Project: AEP Mitchell Station Unit #1 & 2 NH3 System for SCR Project

Estimated Project Value: $3.4M

Duties: Mechanical Project Estimator / Planner / P3 Scheduler.

2006

Contractor: Enerfab, Inc.

Project: Mitsubishi Heavy Industries, LTD.

LNG Bulk Storage Facility

Estimated Project Value: $20M

Duties: Mechanical Project Estimator / Planner / MS Project Scheduler

2005

Contractor: Enerfab, Inc.

Project: Eli-Lilly Bump Tank #14 Installation

Estimated Project Value: $400,000

Duties: Mechanical Project Estimator / Planner / MS Project Scheduler

2005

Contractor: Enerfab, Inc.

Project: Southern Gardens Hurricane Recovery Project

Estimated Project Value: 2M

Duties: Mechanical Project Estimator / Planner / MS Project Scheduler

2005

Contractor: Enerfab, Inc.

Project: Eli-Lilly Fermenter Vessel #30 Cooling coil installation.

Estimated Project Value: $700,000

Duties: Mechanical Project Estimator / Planner / MS Project Scheduler

2005

Contractor: Enerfab, Inc.

Project: Reliant Energy Keystone Station FGD

Estimated Project Value: 32M

Duties: Mechanical Project Estimator / Planner / P3 Scheduler

2005

Contractor: Enerfab, Inc.

Project: Eli-Lilly Fermenter Vessel #29 Cooling coil installation.

Estimated Project Value: $700,000

Duties: Mechanical Project Estimator Planner / MS Project Scheduler

2005

Contractor: Enerfab, Inc.

Project: Ameren Sioux Station FGD Addition

Estimated Project Value: 23M

Duties: Mechanical Project Estimator / Planner / P3 Scheduler

2005

Contractor: Enerfab, Inc.

Project: KCP&L SCR Addition

Estimated Project Value: $85M

Duties: Mechanical Project Estimator.

2005

Contractor: Enerfab, Inc.

Project: DuPont Loudon, TN

Estimated Project Value: 275,000.00

Duties: Project Estimator, Piping Superintendent.

2005

Contractor: Enerfab, Inc.

Project: PepsiCo/Gatorade Line 5. Phoenix AZ

Estimated Project Value: $8.5M

Duties: Project Estimator, Piping Design, Mechanical Bid Package Assembly.

2004-2005

Contractor: Enerfab, Inc.

Project: AEP/Babcock Power SCR&FGD upgrades to Conesville, Kyger Creek & Big Sandy

Estimated Project Value: $200M

Duties: Project Estimator, Piping Superintendent.

2004-2005

Contractor: Enerfab, Inc.

Project: Cinergy/PSI Cayuga Station. Cold Re-heat reroute.

Estimated Project Value: $700,000

Duties: Project Estimator, Piping Superintendent / Planner / P3 Scheduler

2004-2005

Contractor: Enerfab, Inc.

Project: Eli-Lilly/Tippecanoe Laboratories. Antibiotic Cold Storage Renovation Building T-39.

Estimated Project Value: 2.5M

Duties: Project Estimator, Piping Superintendent. Estimated project, upon receipt of an order I supervised construction to completion managing 200,000 in change orders / Planner / MS Project Scheduler

2003-2004

Contractor: Enerfab, Inc.

Project: Eli-Lilly/Tippecanoe Laboratories Fermentor Tank T-26 Chilled Water Coil Replacement.

Estimated Project Value: 500,000

Duties: Project Estimator, Project Superintendent. Estimated project and supervised multi-craft labor to completion / Planner / MS Project Scheduler

2003

Contractor: Enerfab, Inc.

Project: Ameren/Cilco Duck Creek Station SCR addition

Estimated Project Value: 1,500,000

Duties: Certified Combination Welder GTAW/SMAW/Foreman Steamfitter

2003

Contractor: E.L. Pruitt Company

Project: City Water Light and Power/ SCR addition to Units 31,32 & 33

Estimated Project Value: 4,200,000

Duties: Certified Combination Welder GTAW/SMAW

2002

Contractor: Murphy

Project: Citgo Lemont Refinery, Cat cracker Shutdown.

Estimated Project Value: Unknown

Duties: Certified Combination Welder GTAW/SMAW/Machinist. Responsible for the removal and re-installation of the 18” XXS P-22 downcommers.

2002

Contractor: Stone & Webster

Project: Exelon Dresden Unit 3 D3R17 Power Uprate Modification.

Estimated Project Value: Unknown

Duties: Valve Tech. Re-built misc. valves in place to Nuclear standards during power uprate shutdown.

2002

Contractor: Nooter Construction Company

Project: Nelson Energy Project

Estimated Project Value: 400M

Duties: Certified Combination Welder GTAW/SMAW/Field Engineer, Combination welder on the Boiler and Non-Boiler external piping. Field Engineering included field verification of dimensioning, layout and sketching of various power piping systems.

2002

Contractor: Stone & Webster

Project: Exelon Clinton Nuclear Power Station Unit 1 C1R08 Power Uprate Modification. Maintenance and Modifications

Estimated Project Value: Unknown

Duties: Valve Tech/Certified Combination Welder GTAW/SMAW. Re-built misc. valves in place to Nuclear standards during power uprate shutdown. After shutdown, modifications included a Hydrogen Injection system into the feed water and a chemical upgrade project at the screen house.

2001-2002

Contractor: ENTEC Services, Inc.

Project: Various

Estimated Project Value: N/A

Duties: Mechanical Estimator/Service Technician, miscellaneous HVAC&R service work on various commercial buildings. DDC and pneumatic control installation and calibration. Mechanical Estimator on HVAC&R projects both retrofits and new installations.

2001

Contractor: Stone & Webster

Project: Exelon Braidwood Nuclear Power Station Unit 1 A1R09 re-fuel outage.

Estimated Project Value: Unknown

Duties: Valve Tech

2001

Contractor: William A. Pope Company

Project: Cilco/AES Medina Valley Cogeneration. 45MW Combined-cycle cogeneration. 7200 tons of refrigeration from Ammonia absorption and centrifugal chillers.

Estimated Project Value: $62M

Duties: General Foreman. Second Shift Management on a 62 million dollar combined cycle cogeneration facility. In this position, my responsibilities were to lead and manage over 50 Journey status craftspeople, coordinate and sequence the installation of equipment, piping and piping system components, purchase and track materials and consumables and to support Plant, Equipment and Commissioning personnel to insure a smooth startup of all interfacing processes.

2000

Contractor: Stone & Webster

Project: Cordova Energy Center/ 500MW Combined-cycle generating station.

Estimated Project Value: $250M

Duties: Field Engineer/Certified Combination Welder GTAW/SMAW. Created weld maps and as-builts for boiler and non-boiler external piping.

1999-2000

Contractor: General Power Construction Company

Project: CILCO E.D.Edwards Station/ Sulfur Injection Upgrade

Estimated Project Value: $300,000

Duties: General Foreman. Installed and interfaced new Sulfur Injection System into the dry-precipitators while units remained on-line.