Shane G. Green
Cell: 469-***-**** e-mail: ************@*****.***
Construction Project Management: Reliable construction professional offering more than 5 years of success managing commercial construction projects. Career history of directing multi-million dollar projects and maximizing profits through skillful contract negotiation, sub-contractor coordination and material procurement. Dedicated to ensuring the highest level of construction quality maintaining full adherence to all deadlines and specifications. Superior safety ethics and client relations.
Quality Control Sub Contractor Coordination OSHA Safety and Compliance
Planning and Scheduling Materials Management
Professional Experience
McCarthy Building Companies 2007-Present
Assistant Superintendent: Responsible for subcontractor coordination. Provide liaison between field engineering, estimating, and subcontractors to ensure compliance of construction with drawings and specifications. Assist in planning work schedule, determining manpower levels, material quantities, equipment, requirements are maintained, including field engineering and construction activities. Monitor work performance and productivity of crafts to ensure project rules, procedures, and safety requirements are maintained. Advise senior level supervision and project management of potential problems, work interferences, schedule difficulties assist in circumventing/resolving such problems as required.
• Blue Cross Blue Shield Headquarters, Richardson, TX: 15 and 7 story office tower; $180 million total project cost; 16 acre site improvement; 1,050,000 sq ft; 3600 car parking structure
• Dallas County Detention Center, Dallas, TX: 4 story tower housing 2300 inmates; $65 million total project cost; 335,000 sq ft; 50,000 cubic yards of concrete; 550,000 masonry units
Satterfield & Pontikes 2005-2007
Project Engineer: Responsible for processing all shop drawings, submittals and material procurement. Discover and resolve interface conflicts between the Company and subcontractors and conflicts between subcontractors. Assist in developing and updating schedule. Accumulate necessary data and prepare monthly pay estimates. Assist field supervision on interpretation of drawings and specifications and questions for and from the architect/engineer.
• Hector Garcia Middle School, Dallas, TX: 3 story educational facility; LEED Certified Project; $24 million total project cost; 175,000 sq ft; 13.4 acre site improvement
Education and Certifications
OSHA 30 HR Certification
SWPPP Certification
2001-2002 Community College of the Air Force
Certificates in Computer Networking and Communications
2003-2005 Weber State University
Courses focused on General Education and Construction Management