Muhammad Shahzad
Planning Engineer
Summary:
Profile: Male, 31, Married
Nationality: Pakistani
Current Location: Qatar-Kentz
Company: KENTZ (Engineering & Construction).
Preferred Location: Saudi Arabia, Kuwait, Qatar, UAE
Language: English (Fluent), Urdu (Native), Arabic (Basic)
National ID: 37104-1007866-7
Passport: LV410866
Contact: +92-345-*******
E-mail: **********@*****.***
Salary Expectations: Negotiable
Career Objectives:
Quest to work in highly functional environment that enables me to have rich functionality with applied technology in challenging position, where my knowledge and experience can be shared for my career and as well as for company growth.
Professional Qualification:
Diploma of Associate Engineer in Electrical Technology (2002)
From: Sind Board of Technical Education.
Matriculation (HSSC) (1998)
From: Board of Intermediate and Secondary Education Rawalpindi.
Additional Qualification:
PRIMAVERA CERTIFICATION (2009)
Project Management Module –Advance Sours
From: Saudi Arabia
PRIMAVERA CERTIFICATION (2007)
Project Management Module –Basic Sours
From: Saudi Arabia
Diploma of Computer Sciences (Basic) (2003)
From: Advance Computer College Kohat Pakistan
Professional Profile:
Highly organized, dedicated, diligent with position attitude, can handle multiple assignments under high pressure meetings & tight deadlines.
Good written, oral English communication skills. Thrive on working in challenging environment.
Job History:
Company: Textile industry works Kohat. Pakistan
Duration: From Dec, 2003 to Feb, 2005
Position: Trainee Engineer Electrical
Company: Golden Engineering works Sialkot. Pakistan
Duration: From Mar, 2005 to Nov, 2006
Position: Junior Planner
Company: M/s Arabian Bemco Contracting Co. Ltd Saudi Arabia
Duration: From December 10, 2006 to Mar 09, 2008
Position: Project Controller
Project: Riyadh Power Plant – 9 (5980 MV) Riyadh Saudi Arabia
52X60 MW nos. of Gas Turbines and 4 no. of Steam Turbines)
Company: M/s Arabian Bemco Contracting Co. Ltd Saudi Arabia
Duration: From Mar 09, 2008 to Sep-05, 2010
Position: Planning Engineer
Project: Qurayyah Combined Cycle Power Plant – II (3800 MW) Dammam Saudi Arabia
Company: KETZ (Engineering & Construction).
Duration: From Sep-21, 2010 to Till Date
Position: Planning Engineer
Project: Central Processing Facility Block S2 Field Development Project
Job Responsibilities:
Develop / elaborate EPC schedule in Primavera P3e for a facility in light of design drawings / specifications / minutes of relevant meetings etc.
Collect actual progress data and update EPC schedule in Primavera P6.1.
Obtain weekly status of all Detail Schedules. Update status for Master Schedule update with slippages and opportunities defined.
Work with Engineering to verify activities in weekly consultant’s reports. Verify engineering deliverables status/progress and identify slippage and/or opportunities. Track engineering deliverables in Master Schedule and update accordingly.
Review changes to contractor's schedules, enter the details in the Master Schedule when approved and report any abnormality or area of concern.
Produce management reports on the project time status and resources for the weekly reports.
Updating and analysis of ongoing schedule comparative to baseline. Activity includes but not limited to; verification of Critical path and impact to target milestones (contractual, project key milestones, turnkeys, construction turn-over milestones, etc.) and recommending possible mitigating actions.
Coordinate construction activities & look-ahead schedules with field discipline engineers and adjust schedule logic, if required.
Develop and maintain material / tracking list (all disciplines) for scope of work. Raise concern for slippage of materials / equipment from target delivery dates.
Carry out priority work established by the Project Controls Manager, maintain open communication channels and ensure cooperation and coordination with disciplines in the project services group and other project personnel.
Constant coordination with internal departments, partner companies and lower-tier Contractors for progress monitoring and control.
Support project team to achieve internal targets by regularly informing criticality and forecasted dates of completion of essential key-dates (either by detail analysis of resources or forecast by sub-contractor) as well as providing proposal to mitigate/expedite critical activities.
PROJECTS INVOLVED & ACHIEVEMENTS:
Develop / elaborate EPC schedule in Primavera P6 for a facility in light of design drawings / specifications / minutes of relevant meetings etc.
Collect actual progress data and update EPC schedule in Primavera P3e.
Develop and maintain progress curves (discipline and overall) for scope of work.
Keep field engineer updated on budgeted quantities / man-hours and productivity rates.
Coordinate construction activities & look-ahead schedules with field discipline engineers and adjust schedule logic, if required.
Develop and maintain engineering deliverable list (all disciplines) for scope of work. Raise concern for slippage of deliverables from target delivery dates.
Coordinate with material planning engineer for up-to-date material / equipment deliveries.
Develop and maintain material / tracking list (all disciplines) for scope of work. Raise concern for slippage of materials / equipment from target delivery dates.
Check quantity to perform and quantity to be performed.
Submit daily activity report of scope of work on prescribed form.
Muhammad Shahzad Khan