Resume:

FGKr Project/Manager/Electrical Engineer Resume Issuance date: September, 2025

* ** *

Fred G. Kraese Cellphone: 1-650-***-****

P.O. Box No.0505

South San Francisco, Ca. 94083-0505

U.S. Citizen E-Mail: ********@*******.***

Education and BSEE from New York University * IEEE Member Affiliations North American College of Law – Passed the Baby Bar Skills Provided engineering, management and, contract expertise for both public and private entities. Many projects executed in a highly regulated environment these projects were delivered within budget and schedule. I have extensive Project design, budgeting, scheduling and, field support experience during construction, PCO/RFI’s & startup. Met with Owner and outside authorities as the need arose. Unanticipated field conditions have been experienced but with only minor deviation from the estimate and schedule. Years of experience have provided a thorough knowledge federal & state standards and, facility maintenance. Software knowledge: MS Office & P6, Estimating.

Stanford Linear Accel. Ctr. Nov. 2009 – March 2025 Project Management, Electrical Engineering & Contracts Scope Replaced three (3) power substations equipment & building, replaced cooling tower cells, improved efficiency with the installation of VFD’s in place of Across-the-Line Starters, improved various processes, increased domestic water capacity, added process instrumentation, IT equipment

(Servers, WAN/LAN/VoIP & server room environmental equipment), access gates for site security and, improved surrounding pedestrian/motorized access, interior/exterior lighting & landscaping. DOE Funding $12 million

Duties Led a team to develop the specifications for material, outside technical services, construction & safety protocol, commissioning and, estimates & schedules for the upgrading of an existing Substation.

Schedule/Cost Completed in 20 months as scheduled. $9.7 million total cost, 3% over the estimate. Cost Overrun

Scope Demolish an existing 100,000 SFT building for installation of a multistory 300,000 SFT building. Budget $8.5 million

Duties Part of a team to develop the specifications for the safe demolition. Coordinated with Subcontractors and outside technical consultants. Estimates & schedules, for the replacement and/or increase of the existing utilities capacity to meet the needs of the new building including pedestrian & ADA walkway, parking, lighting and, landscaping. Schedule/Cost Plans, specifications and, drawings turned over to the General Contractor on schedule. Demolition accomplished within schedule. The overall project was within estimated cost. Contracts Development of technical & contractual specifications for goods and services. Chevron Richmond Refinery 1983 – April 2009

Project Management, Electrical Engineering & Contracts Scope 230kV – Low Voltage; Design, Installation and, Maintenance 99mW Co-Generation Plant; Design, Installation and, Maintenance Heat Exchangers; Installation and, Maintenance

115-12.47kV Substations;

Distillation Columns; Installation and, Maintenance Building & Temporary Trailers; Design, Installation and, Maintenance Exhaust Scrubbers; Installation and, Maintenance

Contracts; development of technical & contractual specifications for goods and services Chevron Bakerfield Oil Fields

Assistant Project Management & Electrical Engineering Scope 115kV – Low Voltage; Design, Installation and, Maintenance Oil Field Pump Stations; Design, Installation and, Maintenance Oil Field Distribution Stations; Design, Installation and, Maintenance Casson Gas Processing Stations; Design, Installation and, Maintenance



Contact this candidate