Post Job Free
Sign in

Civil Engineer Engineering

Location:
Lusaka, Zambia
Posted:
June 17, 2025

Contact this candidate

Resume:

*

BUPE KABWEBWE

BEng Civil Engineering ****

BUPE KABWEBWE CV

Name Bupe Kabwebwe Mwasaga BK-CV19

Profession: Civil Engineer

Date of Birth: 08/06/1994

Contact Details: +260-***-***-***/ +260 955

409 987/ +260-***-***-***

***********@*****.***

Religion: Christian

Education:

Bachelor of Engineering (BEng-Civil), University of Zambia, 2019

School Certificate, St Mary’s Secondary School, 2011 Undergraduate Research Paper:

Residual Strength of Concrete with Glass and Waste Tire Rubber.

Grade: A

Employment

Period

Record Relevant to

the Job Employing

organization and your

title/position.

Contact

information for

references

:

Country/

Project

Summary of activities performed

relevant to the Assignment

2

BUPE KABWEBWE

BEng Civil Engineering 2019

May 2024-

February

2025

Employing

Organization:

Shachitari

Contractors ltd.

Title/Position:

Site Engineer

Contact

Information for

References

Name: Eng Syafiki

Mwakisulu

Position: Supervisor

Tel no: +260 970 622

916

Zambia.

Completion of

Msanzala

Bridge in

Lusangazi

District Eastern

Province

A. My Responsibilities are to;

Contract management

Interpretation of design drawings

Material and Plant planning

Project scheduling

Project supervision

Site management

IPC preparation.

Project Control.

Within this context, I am also

fulfilling the following tasks;

B. Tasks

Supervision

Mass earthworks

All concrete works

All structural steel and installation

of bearings

Embarkment and scour

protection

Administration

Human resource management

Conflict Resolution

Availability of materials as and

when needed

Site motivation

Project control to ensure we

minimize delays in project

delivery

Ensuring routine servicing of

machines.

Finances and Accounting

Management of site petty cash

and balancing of records by the

end of the month.

Preparation of monthly wages,

overtimes and bonuses

Presentation of monthly material

forecast with reference to project

schedule.

Material stock taking

3

BUPE KABWEBWE

BEng Civil Engineering 2019

December

2022-

December

2023

Employing

Organization:

Shachitari

Contractors ltd.

Title/Position:

Site Engineer

Contact

Information for

References

Name: Mr Nkonde

Kalunga

Position: MWDS

Contact Details:

097*******

Zambia.

Construction of

Kapekesa Earth

Dam and

Associated

Infrastructure.

Eastern

Province

A. My Responsibilities were to;

Contract management

Material and Plant planning

Project scheduling

Project supervision

Site management

IPC preparation.

Project Control.

Within this context, I am also

fulfilling the following tasks;

B. Tasks

Supervision

Mass earthworks

All concrete works

Administration

Human resource management

Conflict Resolution

Availability of materials as and

when needed

Site motivation

Project control to ensure we

minimize delays in project

delivery

Ensuring routine servicing of

machines.

Finances and Accounting

Management of site petty cash

and balancing of records by the

end of the month.

Preparation of monthly wages,

overtimes and bonuses

Presentation of monthly material

forecast with reference to project

schedule.

Material stock taking

4

BUPE KABWEBWE

BEng Civil Engineering 2019

June 2021-

August

2023

Employing

Organization:

Shachitari

Contractors ltd.

Title/Position:

Site Engineer

Contact

Information for

References

Name: Mr Sekani

Longwe

Position:

Resident Engineer

Email address:

sekani1930@gmail.c

om

097*******

Zambia.

Emergency

Construction of

the Lundazi and

Msuzi Bridges,

Lundazi

Eastern

Province

A. My Responsibilities were to;

Material and Plant planning

Project scheduling

Project supervision

Site management

IPC preparation.

Project control

Within this context, I also fulfilled

the following tasks;

B. Tasks

Supervision

Supervision of all concrete and

steel work

Mass earthworks supervision

Confirmation of layer work levels

Steel girder setting out and

installation

Bond dek installation

Cement stabilization of bases

Double seal application as

wearing course on road section

of bridges

Administration was responsible

managing the plant ensuring

Human resource management

Conflict Resolution

Availability of materials as and

when needed

Site motivation

Project control to ensure we

minimize delays on project

delivery

Ensuring routine servicing of

machines.

Finances and Accounting

Management of site petty cash

and balancing of records by the

end of the month.

Preparation of monthly wages,

overtimes and bonuses

Presentation of monthly material

forecast with reference to project

schedule.

Material stock taking

5

BUPE KABWEBWE

BEng Civil Engineering 2019

June 2020

-

June 2021

Employing

Organization:

Shachitari

Contractors ltd.

Title/Position:

Site Engineer

Zambia.

Construction of

90km Feeder

Road RD223

Serenje T2-

Chisomo Road

in Serenje

District of

Central Province

A. My Responsibilities were to;

Material and Plant planning

Project scheduling

Ground levelling with an

automatic level

Project supervision of ring and

box culverts from excavations to

gravel wearing course level.

Site management

IPC preparation.

Within this context, I also fulfilled

the following tasks;

B. Tasks

Supervision

Supervision of all concrete and

steel work

Confirmation of layer work levels

Ensured that excavations were

done to required depth

Ensured backfilling and road bed

formation were done according to

specifications.

Ensuring proper drainage of

entire section is functional

Ensuring pavement layer; gravel

is suitable for pavement

construction and constructed to

required compaction.

Administration was responsible

managing the plant ensuring

Human resource management

Conflict Resolution

Availability of materials as and

when needed

Site motivation

Ensuring routine servicing of

machines.

Finances and Accounting

Management of site petty cash

and balancing of records by the

end of the month.

Preparation of monthly wages,

overtimes and bonuses

Presentation of monthly material

forecast with reference to project

schedule.

Material stock taking

6

BUPE KABWEBWE

BEng Civil Engineering 2019

October 14

2017 -

December

2017

Employing

Organization:

Shachitari

Contractors ltd.

Title/Position:

Assistant Site

Engineer

(attachments)

Zambia.

Construction of

culverts on

Mwambezi,

Konkhuda,

Ncheza,

Sankhata and

Sambangoma

streams;

Nyimba Eastern

province.

A. My Responsibilities were to;

Design of culverts in CAD

Ground levelling with an

automatic level

Project supervision of ring and

box culverts from excavations to

road bed formation.

Site management

Locate a borrow pit for backfilling

purposes

Within this context, I also fulfilled

the following tasks;

B. Tasks

Supervision

Ensured that excavations were

done to required depth

Setting out of the site for the

culverts was done correctly

Ensured that the concrete cast

was to the specified grade

Ensured that the steel bending

and fixing was according to

specifications

Ensured that the formwork was

levelled and properly oiled in

readiness for casting

Ensured backfilling and road bed

formation were done according to

specifications.

Administration was responsible

managing the plant ensuring

Availability of fuel to ensure

progress of works

Availability of materials as and

when needed

Site motivation

Stock taking of materials used.

Finances and Accounting

Management of site petty cash and

balancing of records by the end of

attachment period.

Oct 2016-

Jan 2017

Employing

Organization:

Zambia Airports

Corporation

Limited

Title/Position: Site

Zambia.

Construction of

new KKIA

terminal

building,

Lusaka.

A. Tasks

Supervision

Ensured that excavations were

done to required depth for

terminal building and hotel.

Levelling was done correctly

7

BUPE KABWEBWE

BEng Civil Engineering 2019

Supervisor (Intern)

Ensured that the steel bending

and fixing was according to

specifications

Ensured that the formwork was

levelled and properly oiled in

readiness for casting

Ensured that the concrete cast

was to the specified grade

Inspection

Inspection of steel fixing at the

Hotel and Terminal building

Inspection of the flexible

pavement on the runway

Other Tasks

Design of guard house

Design of boomgate

2015-2016 Employing

Organization:

Ministry of

Works and

Supply

Lufwanyama

District

Title/Position:

Attachments

Contact

Information for

References

Name: Mr Pride

Mubanga

Position:

District supervisor

Email address:

pridemubanga@gma

il.com

Zambia.

Construction

of Mini

Hospital,

Office block

and Maternity

Ward.

A. Tasks

Supervision (Office block,

Primary School, Mini Hospital,

Maternity ward construction)

Ensured that excavations were

done to required depth

Levelling was done correctly

Backfilling with laterite done

correctly

Ensured that the concrete cast

was to the specified grade

Ensured that the steel bending

and fixing was according to

specifications

Ensured that the formwork was

levelled and properly oiled in

readiness for casting

8

BUPE KABWEBWE

BEng Civil Engineering 2019

Other Qualifications

Good working knowledge in Excel spread sheets Microsoft word, power point and Microsoft Project

Good working knowledge in AutoCAD, Revit.

Preparations of Bill of Quantities

Operation of an Automatic level.

Language skills (English, Nyanja)

Team player, good project manager, workforce system creation and management

support facilitator.

Effective project control

Good conduct in a work environment and contribution to organisation development. Team player.

Contact Information for References

Name: Mr Charles Ntinda

Position: Project Manager

Tel no: +260-***-***-***

Name: Eng Syafiki Mwakisulu

Position: Civil Engineer (Structural)

Tel no: +260-***-***-***

Name: Eng Sekani Longwe

Position: Resident Engineer (Bicon)

Tel no: +260-***-***-***

Name: Dr Charles Kahanji

Position: Project Supervisor (Undergraduate research paper) Tel no: +260-***-***-***

Below are attached documents

9

BUPE KABWEBWE

BEng Civil Engineering 2019

10

BUPE KABWEBWE

BEng Civil Engineering 2019

11

BUPE KABWEBWE

BEng Civil Engineering 2019

12

BUPE KABWEBWE

BEng Civil Engineering 2019

13

BUPE KABWEBWE

BEng Civil Engineering 2019

Expert’s contact information: Email: ***********@*****.***; Cell: +260-***-***-***;

+260-***-***-***

Certification:

I, the undersigned, certify that to the best of my knowledge and belief, the CV correctly describes myself, my qualifications and my experience, and I am available to undertake the assignment in case of award. I understand that any misstatement or misrepresentation described herein may lead to my disqualification or dismissal by the Client and/or sanctions by the Bank.

Signed: Date: 13/04/2025

Authorized Signature of Staff Member

Full Names of Consultant: Bupe Kabwebwe



Contact this candidate