Richard E. Golden
Pinole Ca ***64
*********@*****.***
JOB TARGET: IC&E Tech
CAPABILITIES:
•New Construction, Start-up & Maintenance of Electrical Equipment, Automated Instrumentation & Control
•Applications in Electrical Power Generation, Gas Turbine LM 6000, GE 7F, LM 2500 Gas Turbine Water & Waste Treatment
•Installation & Calibration of Flow, Pressure, Level, and Temperature Transmitters, Recorders, Controllers, Control Valves, CEMS Analyzers, Equipment, pH, ORP
•Installation and Start-up of ABB DCS., PLC./S.C.A.D.A., U.P.S. Power Distribution Systems, Motor Control Centers, Pumps, Motors, Blowers, Compressors, Steam Generators, Turbines, scr sys
•Steam Systems, Lithium Bromide Chillers, Cooling Towers, Boilers,RO Units
•Prepared Instrumentation/Electrical Procedures, Inspection Reports, Calibration & Electrical Test Reports
•Maintained Quality Control on instrumentation /electrical specifications and schematics
ACCOMPLISHMENTS:
•Successfully converted several major plant processes control using ABB DCS, Allen Bradley PLC-5 Control System RS Logix Software Woodward Micronet Citect SCADA ( Windows NT) ABB Symphony and Harmony to Conductor Composer Woodward Can Network Control System Converted PEB from GE Mark V to Micronet can bus Control system for GT
•Implemented Reliability Improvement Systems for maintaining instrumentation and calibration record keeping with Fluke 744 Process Calibrator & DCP Track Software,GP Mate Maximo MP2,Maintained IT phone system
•Sr. Inst. Tech. for LASAN, DWP Y2K testing of PLC, SCADA, DCS systems of all types.
•Updated software & hardware for ABB DCS control systems & networks.
•Sr.Start-Up Tech.on new installation of Rosemount Delta V DCS Field Buss Control System @ CE GeoTherm.Power Plant (Brawley Ca.)
•Lead Tech for Delta V System for Units 1&2 front yard & CEMS system Upgrade
•Member Instrument Society of America (ISA).
•EXPERIENCE:
11/2013 to 12/2023 IC&E Tech
Pic Group Inc 25 MW LM 2500 DLE HRSG, 3 100.000pph Aux Steam Boilers
11/2012 8/13 Instrument & Control Tech. Burbank Water Power 250 MW GE 7F Gas Turbine, 50MW LM 6000 and ZLD Plant
7/2008-12/2010 Sr.IC&E, GE Energy, Carson Cogen. LM 6000 Gas Turbine. Maintained all Process Control DCS PLC’S, SCADA Instrumentation,CEMS systems for a 50 MW Power Plant with/a HRSG Combined Cycle
7/2001-7/2008 Sr. IC&E Tech DynegyCorporation
South Bay Power Plant 750 MW Set Up and Calibrated all Process Control instrumentation Maintained all Control Systems DCS PLCS and CEMS
2/2000-7/2000 Sr. Instrumentation Tech (CEM Engineering, Mission Viejo, CA)
Assigned to AES Power Generating Station, Long Beach CA
1/1999-1/2000 Sr. Instrument Tech (Tekton Resources, Salem, NH)
Responsible for Y2K PLC & DCS Assessment and Testing
1994-1998 Sr. Instrument Technician (Praxair Reliability Center, Ontario, CA)
1992-1994 Sr. I&C Start-Up Tech (Sun Technical Services, Mission Viejo, CA.)
1986-1992 Journeyman Inst/Electronic Tech (McDonnell Douglas, Torrance, CA)
EDUCATION:
•Automated Instrumentation & Motor Controls (Long Beach City College, Long Beach, CA)
•Honeywell Control Instrument, P.L.C. Motor Control Training (Douglas Training Center, Torrance, CA) Rockwell Automation PLC 5, ABB University DCS Controls,GE Energy Woodward Atlas Micronet LM 6000 Controls