EDUCATION
Degree of Bachelor of Technology –Electrical and Electronics.1989 Kerala India.
PROFESSION
Electrical Engineer
NATIONALITY
Indian
AUTHORITIES
Qatar – Water & Electricity(Kahramaa)
Qatar –Drainage Affairs(Ashghal)
LANGUAGES
English
Malayalam
Hindi
Tamil
SUMMARY
Mr. Suresh Kumar is a fully qualified Electrical and Electronics engineer with over 28 years of vast experience in supervision of the field of 11KV Substations,11KV Switchgears & RTUs, High ways street lights, Malls, High rise Buildings, Solar system, Refurbishment and upgrading work for Sewerage pumping stations, water & sewage treatment plant, Potable water pumping stations, Firewater pumping station, Tanker Filling Station, Waste transfer stations, control system and SCADA with technical and practical working knowledge. Familiar with Erection, Installation, Testing& commissioning, operation, maintenance, and process in water & sewage treatment work.
PROFESSIONAL EXPERIENCE
PRESENT EMPLOYER:
Organization: Dorsch International consultant,Qatar.
Project: Design and Build Cotract for Al wukair Sewage PR-PS
Temporary Pumping Station & Associated Works. C845/A.
Electrical Engineer.
Client: Ashghal
Period: October 2023 – till date.
Duties/Responsibilities:
Review and approval of Design drawings/documents, Shop drawings as per project and authority requirements.
Review and approval of Site Acceptance Test Reports (SAT) for 11KV switchgear & RTU Panels etc.
Installation inspection of 11KV Substations, 11KV Switchgears & RTU panels.
Testing & commissioning and handing over to the client all documents.
Supervising contract activities & ensuring compliance with standards & specifications.
Egis International Consultant, Qatar
Qatar Economic Zone-03 (Um Alhoul),
Client: MANATEQ, Economic Zone, Qatar
Electrical Engineer,August 2020 – May 2023 .
Projects Involved during this tenure (Packages):
CP-02- Construction of Roads and Infrastructure at Um Al Houl (Packages 3.1 A & 3.1 B)
CP-03- Construction of Roads and Infrastructure Package 3.3
CP-10- Construction and Erection of Syncrolift and Travel Lift.CP-11- Construction of Electrical Substations
CP-19- Design and Build of Light Industrial and Logistics Units,
CP-22- Construction of Common Utilities for Arterial Roads (North of North Access Roads), Design & Construction of Reservoirs including Pumping Stations and their connections to CP 02 and CP 03 (CP 22 Utility Connectivity) at QEZ-3.
CP-24: Sewage Treatment Plant (STP).TSE, Firewater, and Portable water pumping stations.
Duties/Responsibilities.
Review and approval of Design drawings/documents, Shop drawings as per project and authority requirements.
Review and approval of Electrical Material Submittals, Method of Statement (MOS), and PQ Documents.
Review and approval of Factory Acceptance Test (FAT) & Site Acceptance Test Reports (SAT) for 11KV switchgear & RTU Panels etc
Witnessing Factory Acceptance Tests for MV & LV cables, MCC panels, LV panels, VFD panels, Distribution Boards, Generator sets, etc.
Site Supervision and Inspection of Electrical related works such as Distribution Substation, Complete Infrastructure network for EHV/HV/MV/LV cables, Road crossing Duct banks, etc., MV, LV & FO cable installation, Traffic Signal, Street light, QNBN-TEL & UGN, SSD, QAF networks, etc.
Study and implement various contractual documents, such as Specifications, the scope of work, BOQ, drawing package, and execution of work in line with local and international standards.
Verifying the contractor's Interim Process Application (IPA) as per the installation status and approvals.
Project Coordination meetings with Clients, Contractors, HSE, QA/QC, and Stakeholders.
Concerns on the Design implementation on the site are being discussed with the core engineers for proper execution at the site.
KEO INTERNATIONAL – CONSULTANT, DOHA
Construction of emergency tanker filling station. Stand by pump houses and improvement of internal piping at selected stations, Kahramaa, Qatar, GTC-524 - 330 mil QR.
Electrical Engineer, 2015- April 2020
Mr. Suresh Kumar’s role involves the Management of all Electrical sub-contractors, Design consultants & supervision Consultants. Dealing with client representatives & Engineering team of end-users. Execute the project according to the contract and Company policy within the contract period.
Supervising contract activities & ensuring compliance with standards & specifications.
Monitoring the quality & progress of construction activities.
Review electrical design drawings & specifications issued by the consultant. Review shop drawings, material submittals, attending FAT (Generator, Panels), etc., submitted by sub-contractors. Coordinate with all MEP services with other trades Ensuring that approval of materials & documentation is obtained/maintained in an accurate & timely manner.
Discuss and settle all the issues related to the electrical &ICA works with clients, Subcontractors, supplies claims & variations. Preparing detailed material take-off for the tender submission by reading the specification and drawing.
Assisting and coordinating with the design department by giving updating the BOQ for getting the current market price for the materials for tender submission. Installation, testing, and commissioning of all equipment on time.
Duties /Responsibilities
Review for Electrical Related Materials (Pumps, MCC Panels, Generators, SMDBs, DBs, UPS, MOV panels, Street lights, etc) technical evaluation submittals & finalization as per Specification.
Review electrically related method statements & finalization as per contract requirements.
Discussed & finalizes Electrical related NCR with the construction team.
Monitoring and supervising Electrical and ICA activities.
Client interaction, understanding requirements and ensuring timely project Deliverables and meeting construction forecast within the assigned time.
Monitor the status of inspection and follow-up on actions of resubmission, ensuring all required actions are completed prior to re-submission.
Attending the factory acceptance (FAT) and other commissioning actives
Cable sizing calculation of power cables.
Preparation of single line diagram for HV/LV system.
PARSONS INTERNATIONAL, DOHA, QATAR.
Refurbishment and upgrading work for various pumping stations- with associated pipeline in Pumping station-17, W1, and 40. Civil Project 729/2 - 200 mil QR.
Electrical Engineer, 2011-2015
The project is the construction of refurbishment and upgrading works with associated pipelines (Wash out the chamber, Isolation chamber, flow meter chamber, flow control valve chamber, Distribution chamber, Air valve chamber, and pumping station).
Construction of new screen chamber building, and wet well along with all civil, mechanical, Electrical, and Fire alarm system.
Carried out inspection of Installation and testing & commissioning of 11/ 415V substation, Generator up to 2000KVA, different capacity Sewerage pumps (400,375 & 55KW), MV Panels, MCC panels, UPS system, Irrigation system, Sump pumps, transfer pumps. CCTV system, laying of underground cables, Cable tray work, Earthing system, Feeder pillars, HVAC system, etc. Carried out inspection of the installation, testing, and commissioning of the following types of equipment. actuators, overhead crane, all plumping network, Fire alarm, FM-200 system, sliding gates, flow meter, motorized control valves, sump pumps, roller shutter, OCU, all level sensors, and SCADA system, etc.
Duties / Responsibilities
Review for Electrical Related Materials (Pump, MCC, PF correction panels, SMDBs, Generators, Feeder pillar, UPS, Control Panels,etc.) Technical evaluation submittals & finalization as per Specification.
Review electrically related method statements & finalization as per contract requirements.
Discussed & finalizes all related NCR with the construction team.
Monitoring and supervising Electrical and ICA activities.
Client interaction, understanding requirements and ensuring timely project Deliverables and meeting construction forecast within the assigned time.
Review Electrical related shop drawings modified as per site conditions and comments.
Preparing daily progress reports and reporting to RE.
Monitor storage area and take necessary action to prevent damage.
Perform materials receiving inspection/test to verify compliance with the requirement of specification and /or approved submittal. Report non-compliance via the use of receiving inspection reports.
Monitor the status of inspection and follow-up on actions of resubmission, ensuring all required actions are completed prior to re-submission.
Carried out all electrical insulation tests.Cable sizing calculation of power cables.
Preparation of single line diagram for HV/LV system.
Attending factory acceptance (FAT) and other commissioning activities.
Testing & commissioning and handing over to the client all documents.
Pinnacle Construction LLC, Qatar
Construction of Waste Transfer Stations
Senior Electrical Engineer, 2008-2011
The project is the construction of a new Waste Transfer Station (3 Numbers) MEP works. Operation of waste skips treatment works from screening to primary, and secondary, treatment.
Duties / Responsibilities
Installation of Compactors, Overhead cranes, MV panels, MCC panels, Diesel Generator sets, Weighting Bridges, sump pumps, Truck washing systems, Fire alarm systems, Booster pumps, etc.
Dealing with client representatives & Engineering team of end users.
Review Electrical shop drawings and material submittals.
Review Electrical design drawings & specifications issued by a consultant.
Discuss and settle all issues related to the Electro-mechanical works with clients, sub-contractors & suppliers.
Supervising contract activities & ensuring compliance with standards & specifications.
Overseeing project schedules & budgets within allocated cost & time parameters.
Verify electrical sub-contractors & supplier’s claims & variations.
Kharafi National, Kuwait.
Electrical Engineer 1998-2007
During this time as Electrical Engineer, at Subiya Wastewater treatment and reclamation plant, the Water injection plant, The scientific center, Marina Mall, Kuwait liberation tower, Kuwait.
Duties / Responsibilities
Installation, testing, and commissioning of 11/.443kv substation, generator up to 1600 KVA, sewage pumps, booster pumps and control panels, sump pumps, Extract fans, bleed fans, overhead crane, valves supply, screening press, MV panels, bus ducts, MDBs, MCCs, Feeder pillars, various rating motors, starters, earthing systems, earth pit with insulation test, instruments/monitors like flow, temperature transducer, pressure, etc.
Laying of MV underground cables, cables & pilot cable terminations, cable joints, control, and instrumentation.
Conducting fire alarm system, CCTV system, fixing accessories related to light, power, and other services.
Fixing & fabrication of cable trays, cable testing, meggering, and commissioning of panels after installation.
S K Electrics & Infrastructures, India.
Electrical Engineer 1989-1998.
During this time as Jr. Electrical Engineer, Cochin Refineries Ltd. The fertilizer and Chemicals Ltd. Water treatment plant, India.
Installation, testing, and commissioning of generator up to 1200 KVA, MV panels, bus ducts, MDBs, MCCs, Feeder pillars, various rating motors, starters, earthing systems, earth pit with insulation test, instruments/monitors like flow, temperature transducer, pressure, etc.
Installation of Industrial lighting and electrification works.
Testing & Commissioning of LT substation, cable laying, DG set, and DBs
Transmission line installation and commissioning up to 110KV.
Preparing bill of quantities, pricing, cable calculations and load schedules.