Results-driven degreed Mechanical Engineer with 30+ years of experience managing complex, multi-million dollar international projects, specializing in construction of airports and large-scale commercial facilities. Proven track record in design, construction and commissioning of the HVAC, plumbing, fire safety systems. Expertise in design, project management, construction supervision, and MEP systems coordination and Commissioning. Skilled in stakeholder management, design coordination, safety and quality. Skilled in stakeholder management, design coordination, safety and quality. Proven leader with a track record of developing high-performing teams and fostering collaborative work environments. Proficient in Microsoft Office Suite, project management software, and BIM tools for efficient project execution.
PROFESSIONAL EXPERIENCE (last ten years)
Project Manager- Delray Glass Co. Alexandria, Virginia July 2024 – October 2024
• Manage facade cladding, exterior and interior glass partition projects with budgets exceeding $10 million
• Conduct daily site walkthroughs, preparing detailed reports on construction progress, budgeting, billing, tracking of issues, and mitigation strategies
Mechanical Group Chief- Kardelen Joint Venture Istanbul, TURKIYE Dec2023 – May2024
• Led MEP systems installation for residential project encompassing 9 blocks and 1097 apartments
• Managed project budget of $50 million, delivering on-time and approved budget
• Implemented rigorous quality control procedures, ensuring 100% compliance with design and local regulations
• Developed and managed detailed logistics, phasing plans, and critical path schedules, ensuring on-time project delivery
• Led design coordination efforts between design team, owners, and stakeholders, ensuring alignment of project goals
• Implemented comprehensive quality control processes for MEP systems, compliance with design specifications and local regulations
Mechanical Manager - Yapi Yapi Istanbul, TURKIYE Aug2022 – May2023
• Oversaw mechanical works organization and coordination for multiple subcontractors
• Managed procurement, submittal review, testing and commissioning and approval of major mechanical equipment worth $15 million, including coordinating and tracking equipment deliveries to align with project timelines
• Led preconstruction activities, including design review, value engineering, and constructability analysis, optimizing project outcomes
Mechanical Group Chief- Cengiz Holding Rize, TURKIYE Jan2020 – July2022
• Led engineering teams during construction of Artvin International Airport project
• Managed startup, pretesting, and commissioning of mechanical and electrical systems, coordinating with third-party commissioning agents and managing all related documentation
• Coordinated with architects and engineering teams to implement design revisions and resolve MEP conflicts, improving system efficiency by 10% and reducing on-site issues
• Managed startup, pretesting, and commissioning of mechanical and electrical systems, coordinating with third-party agents and meticulously documenting all processes
MEP Manager - MAPA Construction and Trade Co. Inc. Accra, GHANA Jan2016 – Nov2018
• Managed MEP systems installation for Kotoka T3 International Airport
• Oversaw procurement, installation and commissioning of specialized systems including Baggage Handling System, Personal Boarding Bridges, and X-RAY & Security devices
• Developed and implemented Methods of Procedure (MOPs) for critical MEP work in live airport environments, minimizing disruptions to ongoing operations
Sr. Mechanical Design Engineer - Sembol Construction Astana, KAZAKHSTAN Jan2015 – Jan2016
• Served as Project Mechanical Design Manager for Astana Expo 2017, overseeing engineering firms Supervised production of construction drawings and design coordination for ongoing construction activities.
• Managed mechanical design for complex project including Five Star Hotel, Congress Center, and Service Building Ensured seamless integration of mechanical systems with architectural and structural systems Sr. Mechanical Design Manager, Partner GMD & MOSKAY Joint Venture Istanbul, TURKIYE Jan2015 – Dec2015
• Led mechanical design and coordination for the Istanbul Grand Airport project
• Produced construction drawings and coordinated mechanical design with architectural, civil, and other disciplines
• Managed design for Terminal Building (1,350,000m2), 2.5km long Piers, HVAC rooms, and Central Cooling & Heating Plant
• Implemented innovative design solutions to optimize energy efficiency and system performance
• Led preconstruction activities, including design review, value engineering, and constructability analysis, optimizing project outcomes
Mechanical Group Chief Engineer, Renaissance Construction St. Petersburg, RUSSIA Jan2014 – Jan2015
• Led mechanical design, construction and coordination for the Four Seasons Residential Complex MEP Site Supervisor, Mapa Construction Baku, AZERBAIJAN Jan2013 – Nov2014
• Led mechanical design and coordination for the Baku Haydar Aliyev Airport New Terminal Building
• Produced construction drawings and coordinated mechanical design with architectural, civil, and other disciplines EDUCATION
Bachelor of Science, Mechanical Engineering, 1992