Summary:

Electrical Engineer with 10 years of experience in Project Estimation & Execution, Testing, Operation and Maintenance &MEP works up to 33KV Networks in Oman, UAE and India. Upgrade my Skills in Industrial automation engineer.

Strength Highlights:

• Project management

• Strong decision maker

• Complex problem solver

• Hard working person

• Effective Team Member

• Service-focused

• Result Oriented

Education:

• Master's Certification Program in Electric

Vehicle Design & Development, Skill-Lync. - (2022-Present)

• BE in Electrical Engineering, K S

Rangasamy College of Technology - (8.45 CGPA) (2012)

• HSC St. Mary’s Higher Secondary School. - (86.5%) (2008)

• SSC St. James Higher Secondary School. - (90%) (2006) Certifications:

• GRID CONNECTED PV SYSTEM DESIGN

AND INSTALLATION on 24.08.2020 to

03.09.2020 in `GSES India Sustainable energy

Pvt Ltd.

• Completed Post Gratutae Diploma in

INDUSTRIAl AUTOMATION (PGDIA) in

SMEC Labs.(PLC and SCADA)

• Oman Driving License valid up to 22.04.2025

• Competent Electrical person in Majan Mazoon

& MEDC available(expiry) subject to renewal.

Job Related Software:

• Auto Cad-Electrical(2d)

• MS Office (word,excel, PowerPoint etc..)

• PLC AND SCADA

WORK EXPERIENCE IN OMAN:

Company: DELTASTAR POWER PROJECTS SERVICES ENG LLC, OMAN. Position: Project Engineer

Period : June 2015 to August 2021

Project Details:

• Upgrade Shuwayha Primary SS from 1x6MVA to 2x6MVA and associateelectrical works (Al Burami Governorate)

• Upgrade zroup pss from 1x6 MVA to 2x6MVA in buraimi governorate for royal oman police (stf complex burami)

• Upgrading Al Haimly Primary Substation From 1x6 MVA To 2x6 MVA At Rustaq In South Al Batinah Governorate

• Upgrade Protection system in Majan network

• Enchancing Indoor Primary stations

• Replacement of Protection Relays in Intercontinental (P109),Sarooj Shati Al Qurum(P110), ROP (P111), Lulai (P095) And MSQ(GP06) Substations at MEDC Network.

• Varrious Reinforcement work in 11KV & 33KV network. Installation of transformer, RMU, Feeder Pillar Auto recloser, Breaker, Current Transformer, Voltage Transformer etc… Job Involved:

Tender related work support to Estimation Engineer:

• Check the tender annoncement in Majan,Mazoon,MEDC on daily basis.

• Arrange the necessary documents to purchase the tender.

• Attend the site vist and analyse the pros & Cons of the working site.

• Review the BOQ and send the major material equiry to concern supplier or Manufature.

• Follow up the supplier to get the appropriate price to quote the tender.

• Prepare the estimation excel for material price,labour price,adminstration price,mobilization price, accomadation price etc.. before prepare original BOQ.

• Prepare the necessary documents and envelop to submit the tender to customer. Excecution Related work at Site:

• Installed 100KVA to 10MVA transformer & related activities.

• Installed HT & LT Cable routing, jointing & termination and testing of cables.

• Installed RMUs,OLU and HFU in package substation and outdoor distribution substaion.

• Installed Over head line(wooden pole & Concrete pole) and conductor stringing up to 33KV network.

• Ensuring good Safety & Quality practice in Installation.

• Installation of 33kV and 11kV Pole mounted Auto Reclousre made by Tavrida,Schneider.

• Installation of 33KV Voltage transformer.

• Installation of voltmeter and transducer & cabling works

• Control Relay Panels Installations and Capactior bank.

• Installation of 33KV outdoor circuit breaker and indoor circuit breaker.

• Site survey as per approved drawing and marking the site

• Prepare the project schedule and follow up the client to get approval.

• Coordination with civil team to complete the civil activities.

• Prepare the electrical material list and follow up with supplier to deliver the material on time at site.

• Site execution as per approved structure drawings

• Manage the manpower and material list

• Attend the weekly and monthly meeting with client also submit the report. Company : DELTASTAR POWER PROJECTS LLC, OMAN.

Position : Operation Maintenance

Period : 2013 to 2015

• Attend any of 33KV, 11KV and 0.415 KV interruptions (Emergency Work) during 24 Hours and Holidays according to the Operation & Maintenance Engineer instructions.

• Replace and add Oil for Transformers, RMU, OLU, and HFU as per the plan

• Installation and testing of earth system.

• Dismantling and Re Straightening of 33KV,11 KV and 0.415 KV Lines.

• Preparation of the various records and reports on daily, weekly, and monthly basis.

• Replace damage / failure 630mm2 cables.

WORK EXPERIENCE FROM UAE:

Company : DELTASTAR POWER PROJECTS SERVICES LLC, ABU DHABI Position : Project Site Engineer

Period : June 2018 to November 2018 (5 months)

Project 1 :Emergency Works to Supply & installation of the earth system stolenfrom 22 Primary Substations at Both Eastern Region and Central Region. Client : Abu Dhabi Distribution Company Location Eastern & Central Region Abu Dhabi- UAE Job Involved:

• Marking and Fixing Arrangement.

• Compliance with this method statement.

• Taking all safety measures as per risk assessment plan.

• Coordination with related functions and agencies

• Provide/ arrange necessary PPE

• Recommend safe work methods to carry out the works safely

• Ensure that all works are carried out in safe manner.

• Installation of Copper Clad Steel Conductor (CCS) upto 400 sqmm.

• Removing old earthing cable with maintaining the proper electrical safety rules by means oftemporary and portable earthing.

• Installation of new Copper Bus Bar in 33 & 11kV SWG panel (Siemens & Schneider)withmaintaining the proper electrical safety rules by means of temporary and portable earthing.

• Preparing for Testing of Contact Resistance, Earth resistance, Step & Touch Potential.

• Man Power & Material Management.

• Client, Subcontractor, Technician & labor management.

• Comprehensive problem solving abilities.

Project: 2

REPLACEMENT AND UPGRADE OF PROTECTION EQUIPMENT FOR 100 MVA TRANSFORMERT251,TO PROVID

NEW OC PROTECTION RELAY FOR BUSCOUPLER BAY D03 AT AAPS. Client : Abu Dhabi Transmission & Dispatch

Company. Location: Al Ain Power station(MIRFA)

• Installation of REF CT in 33KV Incomer feeder & Add new OC & REF relay fixed in33KV CRP panel

• Replaced old Protection panel in transformer protection panel.

• Installed new protection panel in transformer T-251

• Split the cables and wiring connection from new transformer protection panel toBuscoupler bay D03

• Compliance with this method statement &taking all safety measures as per risk assessment plan.

• Man Power & Material Management. Client, Subcontractor, Technician & labor management. WORK EXPERIENCE FROM INDIA:

Company : DELTASTAR POWER PROJECTS PVT LTD INDIA.

Position : SITE ENGINEER

Period : 11.07.2012 to 11.07.2013

Project : Solar project work in various locationsJob Involved

• Design, Installation & Commissioning of Solar ON GRID & OFF GRID Power Plants.

• Design, Installation & Commissioning of Solar Water Heater, Water Pump & StreetLights.

• LT solar power plant installation (440V) and Earthing activities of full plant.

• Inverters, AJB & Batteries Installation and Maintenance.

• Maintaining all IS & MNRE Standards.

• Providing technical & Commercial Support to Sales team.

• Projects Planning & Scheduling.

DETAILS OF TEST CONDUCTED:

• Contact Resistance test using Micro Ohm meter for bus bar, Circuit Breaker and Earthing.

• Earth grid resistance measurement test.

• Step and touch potential test.

• Dis-connector and Earth switch closing / opening time

• 33kV and 11kV cable High Voltage Testing.

• CT, VT ratio test and Insulation Resistance test

• Breaker Insulation Resistance Test.

I hereby declare the above information are true to the best of my knowledge and belief Sincerely, A.SEBASTIAR.