Experience Summary
1: operation manager : lead the Operations staff and manage all aspects of operations of a power plant to ensure safe, environmentally compliant and efficient operations of the plant. Nubaria III (2020 to now)
1: Lead operation engineer: Plan, develop, coordinate, manage and direct Supervises of all operation work (Lead 4 shift in charge engineer) in Nubaria I&II CCGT Power station (Nov 2013 to 2020)
1: Lead Commissioning engineer: follow-up the design, submittals, Installation, Sit acceptance tests, Commissioning and Start up engineer for Sabiya CCGT combined cycle Gas Turbine Power Project as consultant in Kuwait ministry of electricity and water MEW 2010-2012
2: Senior (shift in charge) operation control room engineer in 1500 MW combined cycle power station.
3: Commissioning, steam blow out, start up, and operation Engineer for HRSG boiler. 4: Pre commissioning and commissioning senior engineer and start up engineer for 8 GE gas turbine frame 9E .
5: CCGT Power plant, Gas turbine, DCS, HRSG & Steam turbine operation engineer 6: Last Two Years Training courses: ( PMP and Negotiation, Effective Communications,, Effective Leadership and motivation, RCA, Effective Team Building, Change Management, strategic planning, process analysis, GOVERNANCE, Iso 9001, Risk Assessment) **************@*****.*** +20-109-***-**** Egypt
COMPANY NAME : Nubaria III power station 750 MW (Middle Delta Electricity Production company, Egypt) Date JOB POSITION JOB DISCRIBTION
Lead the Operations staff and manages all aspects of operations of a power plant to ensure safe, environmentally compliant and efficient operations of the plant.
Monitor plant and unit performance, conduct root cause analysis, and lead investigations to develop and implement corrective actions
Set maintenance priorities and schedules maintenance for the plant in conjunction with the Maintenance Manager
Developed, implemented and revised operational policies and procedures which improved plant performance and ensured consistent operations between crews.
Fulfill the responsibilities of the Plant Manager position in their absence.
Achieved for the company savings of approximately 6 grams/kw by rearranging the priority of load rising on the units in coordination with the Dispatch center.
The plant consist of 2 modules, each one has 2 GE gas Turbine, 1 Alstom STEAM TURBINE and 1 STF HRSG
2020
to update
Operation Manager
Nubaria III Combined
Cycle Power Plant
750MW)
COMPANY NAME : Nubaria 1&2 power station 1500 MW (Middle Delta Electricity Production company, Egypt) Date JOB POSITION JOB DISCRIBTION
Nov 2012
to update
Lead Operation
engineer
Nubaria Combined Cycle
Power Plant 1500MW)
Responsible for all functions relating to facility operation . Direct plant operation staff to complete operations and tasks within environmental and regulatory compliance
requirements, with a focus on safety, quality, and achievement of the facility’s goals availability and reliability.
The plant consist of 2 modules, each one has 2 Siemens gas Turbine, 2 Alstom HRSG and 1 Mitsubishi Steam Turbine **************@*****.*** +20-109-***-**** Egypt
COMPANY NAME : KHARAFI NATIONAL & MEW, KUWAIT
Date JOB POSITION JOB DISCRIBTION
Senior Mechanical Commissioning Engineer in the ministry of electricity and water in Kuwait : follow the construction and commissioning steps and start up procedure . for Sabiya CCGT (which consists of 3 Modules, each one consists of 2 GE gas Turbine, 2 HRSG Hyundai and 1 GE Steam Turbine. Coordination with contractors and consultant for the site constructions, erection commissioning testing.
on all the mechanical constructions
drawings, submittals and documents related to new Gas Turbine power plant.
Coordinate the day to day commissioning activities related to mechanical plant equipments.
Attend site mechanical commissioning meeting
Maintain a detailed log book covering the day to day note of all mechanical activities in the plant
Attend testing and inspection activities related to mechanical plant equipments
Coordinate and witness mechanical precommissioning / commissioning activities at the site.
Follow up mechanical test on completion of the plant.
Responsible to attend all turbines Tests
(cold.warm,hot start,minimum stable load, emission test,acoustic test, load rejection, half condenser,etc
,estimating efficiency of gas turbine in thermal
performance test.
Day to day follow the plant performance during Reliability period
Develop a punch list, identifying defects and negotiate a solution with the EPC contractor without ambiguity and unnecessary delays.
Negotiating with the EPC Contractor on behalf of the owner to ensure root causes of system defects are
understood and resolved to acceptable standards.
From
2010
To April2011
AND
From Sep.2011
to Oct.2012
Owner
Commissioni &
start up engineer
(Sabiya CCGT 2000
MW)
Ministry of Electricity and
Water in Kuwait MEW
(Manpower supply from
Kharafi national)
2 Years
brief : Responsible of all Commissioning activity in CCGT as owner engineer **************@*****.*** +20-109-***-**** Egypt
Company name: KHARAFI NATIONAL, EGYPT
Date JOB POSITION JOB DISCRIBTION
Commissioning and start up Senior mechanical
commissioning engineer in el shabab power station project in Egypt responsible for all pre commissioning, flushing and commissioning process for 8 GE gas turbine frame 9E And start up & operation engineer during first fire and all turbine and generator tests, and operate the unit during reliability Period.
April 2011
to
sep 2011
Commissioning engineer
5 months
brief: Responsible of pre commissioning, commissioning and start up engineer company name : NUBARIA POWER STATION, EGYPT( Middle Delta Electricity Production Company) Date JOB POSITION JOB DISCRIBTION
From 2008
to 2010
Shift in charge
operation control room
engineer
in
Nubaria power
station1500 MW
Lead the engineers and technical groups to operate 4 Combustion Turbine Generator (Siemens), with 2 combined Steam Turbine Generator (Mitsubishi) and 4 HRSG
(Alstom)boiler and all related equipments.
follow the dispatch load request.
perform periodical test.
shut down and start up the unit.
operate the unit in disturbed situation.
collect and analyze periodical data.
follow and deal with alarms in control room
perform necessary measures before equipment start up.
follow operation specification.
analyze equipment efficiency.
check availability of stand by equipment.
lead in the shift personnel and equipments.
detected defect.
record and write all necessary information logbook Total 2 years
brief: shift in charge CCR in 1500 MW CCGT
**************@*****.*** +20-109-***-**** Egypt
company name : NUBARIA POWER STATION, EGYPT
Date JOB POSITION JOB DISCRIBTION
2004 to 2006
Gas turbine operation
engineer
Commission, start up and operation for four Siemens V94.3A Gas turbine 250 MW responsibility as gas turbine operator shift engineer.
Supervision to installing and construction steps to gas turbine.
attending first fire to gas turbine with Siemens commissioning engineers.
standing up as operator shift engineer during commission and generator protection tests.
Start up and shut down the unit in safe mode
Responsible to estimating efficiency of gas turbine during performance test.
working as operator shift engineer during reliability period. Total 2 years
brief: Gas Turbine Operation Engineer
company name : NUBARIA POWER STATION, EGYPT
Date JOB POSITION JOB DISCRIBTION
2006 to 2008 HRSG
Commissioning and
Start up Engineer
After taking a training in France in operation the HRSG (Jan 2006) Alstom
I was a leader of the team whom is concerned of doing Steam blow out, trevi test review, site acceptance engineer after that I work as operation engineer
commissioning and first start up of the HRSG
boiler (HP/IP/LP drum 125/25/5 bar) and Steam Turbine and operate the combine cycle in reliability period and performance test
achieved safe and reliable commissioning and start up of all BOP
Total 18 months
brief: combined power plant startup and operation engineer company name : DAMANHOR POWER STATION, EGYPT
Date JOB POSITION JOB DISCRIBTION
2002- 2004 operation engineer
operation engineer for small CCGT 158 MW 4x4x1
4 GAS Turbine
4 NEM, HRSG
1 Steam Turbine
Source: all reference paper available at request