Work Package #* East - Section * East & Engineering - (MSJV 92.3% / 90.6% Target - As of July 8, 2023
oHot topics:
Weather for the week 8 - 28 deg, dry all week with little moisture.
Several bird nests along the ROW are impacting production and same with the FDR’s of 4/5’s shutting down crews early and spending time on spark watch.
oConstruction Update:
AUT Scanning of Golden Weld KP 595+300 was successful after repair. Only 2 golden welds remained.
Welding crew completed 2 test welds on the pressure testing heads for TS-03B at KP 610+919 and blind flange at KP 612+700. Also, Water filling completed for TS-03B (1,956m).
Crews completed coating for all welds and any repairs in the backfilling locations.
Backfill 100% of step slopes 57 (KP 611), 60 (KP 612+100 to KP 612+250) and concentrating at KP595+400.
Re-Instated WC KP586 completed.
Placing boulders at WC-1824 which is the last remining crossing in section.
Machine Cleanup countinued 1,360m at KP596 to KP598 / KP605/ KP608 / KP610 & Final Cleanup progressed 1,122m at KP587 to 610 (completing certain section sign-offs within that KP range.).
oActions for the Week:
Update CGL Level 1 & 3 schedules and summery March Chart for July mid-month.