EXPERIENCE SUMMARY

A highly experienced result oriented competent person holding Technical Diploma in Electrical & Electronics Engineering with over 20 years of illustrious service in Construction, commissioning and Maintenance of Electrical Equipment’s and systems in mainly Oil & Gas Exploration, Refinery Plants & Ship building plants, Telecom Industries.

EDUCATIONAL QUALIFICATION

Master’s Degree – Fire & Safety Management. Year 2017. Jaipur National University

Diploma – Electrical and Electronics Engineering. Year 1995 – Govt. Polytechnic Visakhapatnam.

TECHNICAL / PROFESSIONAL TRAINING

Diploma in Industrial safety

Occupational Safety & Health Administration (OSHA) from American Safety Council

Trained First Aider from Ministry of Health Kuwait.

Trained Competent Gas Tester from Wataniya Environmental Services Kuwait.

Member of Behavior Based Safety Organization JOINT OPERATION Wafra, KUWAIT

KUWAIT OIL COMPANY APPROVED PTW Holder (Permit Applicant)

QATAR SHELL PEARL GTL APPROVED PTW Holder

SOFTWARE TECHNICAL

Diploma in Computer Hardware & Networking.

Diploma in Computerized Financial Accounting Course

COMPETENCY IN PRE COMMISSIONING AND COMMISSIONG OF ELECTRICAL EQUIPMENTS

Participated in First Power and Loop checks of Auxiliary Power supply

Participated and Supervised Site Acceptance or System Acceptance tests on Electrical Equipment’s.

Interlock Verification of Electrical Systems

Participated and Supervised Various Electrical Testing for Cables Continuity Test, Insulation Resistance Test, High Voltage Impulse Test (Hi-Pot).

Participated and Supervised Various Electrical Testing for Switchgear Torque testing for bus bar Joint connection points, Contact Resistance Test, Insulation Resistance test, Hi-Pot Test for Bus bar, Circuit Breaker Insulation Resistance Test, HV Impulse Test, Contact Resistance Test, CB Close/open timing Test, Secondary Injection test for Protection relays, Primary Injection Test for CT Ratio/Polarity/IR/Saturation Test, VT Ratio/Polarity/IR Tests. Ammeter & Volt Meter Calibrations.

Participated and Supervised Electrical Testing of Heat Tracing Cables and Circuit installations and commissioning of Heat tracing Circuits and Panels.

Participated and Supervised Electrical Testing of LT/HT Motors IR & WR Checks. Phase Rotation Checks, Motor Bump Testing, No Load Testing, On Load test

Participated and Supervised Electrical Testing for Transformers like IR, WR, Transformer Ratio Test, High Voltage Impulse Test, Oil Dielectric Test (B.D.V) test.

Participated and Supervised HV/LV Motor Solo Run Test, No Load and On Load tests.

Pre-Commissioning and Commissioning of Switchgear, MCC, PCC, UPS panels, Transformers, Motors, Emergency Diesel Generator, MOV’s, Cathodic Protection Systems, Heat Tracing Systems, HVAC Systems & Lighting Facilities.

Participated and Supervised Electrical Testing & Commissioning of Cathodic Protection system

Participated and Supervised Electrical Testing & Commissioning of UPS and Battery Chargers system

Participated in commissioning of HVAC System

Preparation of Pre commissioning and commissioning test sheets.

CAREER SUMMARY

1.SRI VENKATESWARA MARINE SERVICES – ELECTRICAL SUPERVISOR – March 2022 to Till Date

2.MADINA GROUP OF COMPANY (SHELL PEARL GTL PLANT QATAR)-ELECTRICAL SUPERVISOR-Dec 2021 to Feb 2022

3.SRI VENKATESWARA MARINE SERVICES – ELECTRICAL SUPERVISOR – June 2019 to Dec 2021

4.AL KHORAYEF GROUP OF COMPANY (KUWAIT OIL COMPANY NEW GC-16 PROJECT,KUWAIT)-SENIOR ELECTRICAL TECHNICIAN-SEP 2013 TO APRIL 2019

5.IMCO ENGINEERING&CONSTRUCTION(JOINT OPERATION WAFRA OIL FIELDS KUWAIT)-SENIOR ELECTRICAL TECHNICIAN-Aug 2010 to June 2013

6.VIMCCO- ELECTRICAL ENGINEER-June 2009 to July 2010

7.ASTER INFRASTRUCTURE LTD.,KABUL AFGHANISTAN-ELECTRICAL ENGINEER-May 2008 to May 2009

8.BHARAT TECHNICAL SERVICES-SERVICE ENGINEER-June 2006 to April 2008

9.THE NATIONAL ELECTRICAL WORKS-ELECTRICAL SUPERVISOR-June 2005 to Feb 2006

10.ALMEER TECHNICAL SERVICES (KUWAIT OIL COMPANY WEST GC-17,GC-28,MWIP,KUWAIT)-ELECTRICAL TECHNICIAN-May 1999 to March 2004

11.RAMAKRISHNA RAO CO PVT. LTD.-ELECTRICAL TECHNICIAN-Aug 1996 to Feb 1999

DETAILED PROFILE

COMPANY NAME

SRI VENKATESWARA MARINE SERVICES

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Electrical Services and Modification Works

Owner: Kakinada Sea port, Coramendal fertilizers Bhagyanagar Gas, Ruchi Oils, Nekkati Sea Foods, and Santhoshi Edible oils.

Contractor: Sri Venkateswara Marine Services

Role: Electrical Supervisor

Duration: Since 5 months

Scope: Electrical Modification in Substations and Other Electrical Services

RESPONSIBILITIES HANDLED

Responsibilities include Supervision of Electrical modification works as per the client requirements, as a corrective actions on Switchgear system,MCC,PCC,UPS panels

Preparation and review of schedule

Review and Track Material Control Index (MCI)

Prepare Catch up plan/ Reschedule the delayed activities

Resource Planning and allocation( Man power, Materials )

Prepare Weekly and Monthly Progress reports to client

Attend Review Meetings with Client

Discuss and close out the input requirements

COMPANY NAME

MADINA GROUP OF COMPANY (QATAR SHELL PEARL GTL PLANT)

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Major Turnaround Project-3(MTA-3)

Owner: QATAR SHELL PEARL GTL, QATAR

Contractor: Madina group

Role: Electrical Supervisor

Duration: 2 Months

Scope: MTA-3 Major Shut down Electrical Activities

RESPONSIBILITIES HANDLED

Responsibilities include Supervision of MTA Activities, Handling a Team of 6 Technicians to Fulfill the Shutdown Electrical Activities.

Review and Track Material Control Index (MCI)

Prepare Catch up plan/ Reschedule the delayed activities

Resource Planning and allocation( Man power, Materials )

Prepare Daily Progress reports to Project Engineer

Discuss and close out the input requirements

COMPANY NAME

SRI VENKATESWARA MARINE SERVICES

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: GEF Unit-2 Commissioning, Grasim Chemical Plant Commissioning

Owner: Gemini Edible Oils and Fats Unit-2, Kakinada. Grasim Chemicals balabadrapuram,Kakinada

Contractor: Sri Venkateswara Marine Services

Role: Electrical Supervisor

Duration: 2 Years 6 months

Scope: Pre Commissioning and Commissioning Activities of Electrical Systems and Equipment’s

RESPONSIBILITIES HANDLED

Responsibilities include Supervision and participation of pre commissioning and commissioning activities on Electrical Equipment’s and systems

Handled a Team of 8 Technicians to fulfill targets

Preparation and review of schedule

Review and Track Material Control Index (MCI)

Prepare Catch up plan/ Reschedule the delayed activities

Resource Planning and allocation( Man power, Materials )

Prepare Weekly and Monthly Progress reports to client

Attend Review Meetings with Client

Discuss and close out the input requirements

COMPANY NAME

ALKHORAYEF GROUP OF COMPANY (KUWAIT OIL COMPANY NEW GC-16 PROJECT) KUWAIT

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Built and Operation Maintenance of New GC-16 (Construction, Commissioning and Maintenance)

Owner: KUWAIT OIL COMPANY (KOC)

Contractor: Ali Alghanim

Role: Senior Electrical Technician/Shift In charge

Duration: 5 Years 7 months

Scope: New GC -16 Construction, Commissioning and Maintenance

RESPONSIBILITIES HANDLED

Responsibilities include Supervision of Construction, Commissioning and Maintenance of 11KV,3.3KV & LT Switchgear system, Transformers, HT/LT Motors, MCC, PCC, UPS, Lighting panels

Worked as a Shift In charge with 8 nos. of Technician Crew to Support Operation Department on Electrical Trouble shootings and Maintenance Activities.

Preparation and review of schedule

Review and Track Material Control Index (MCI)

Prepare Catch up plan/ Reschedule the delayed activities

Resource Planning and allocation( Man power, Materials )

Prepare Weekly and Monthly Progress reports to client

Attend Review Meetings with Client and contractor

Discuss and close out the input requirements

Expert in reviewing of Construction drawings like P&ID, Electrical lay outs, General arrangements, Isometric diagrams, Cross-sectional diagrams, Bus wiring diagrams, Single line diagrams, Schematic diagrams etc.

Planning Electrical conduits, cable trench, duct banks and raceway layouts.

Erection, Installations of Switchgear, MCC, PCC, and UPS panels, Transformers, Motors & Lighting Facilities.

Good Experience in Installation of Heat Tracing Systems

Participated and Supervised Power and Control Cables Glanding, Terminations.

Supervision of Cable Joints and End Terminations.

Participated and Supervised Various Electrical Testing for Cables Continuity Test, Insulation Resistance Test, High Voltage Impulse Test (Hi-Pot).

Participated and Supervised Various Electrical Testing for Switchgear are Switchgear Earthing system, Torque testing for bus bar Joint connection points, Contact Resistance Test, Insulation Resistance test, Hi-Pot Test for Bus bar, Circuit Breaker Insulation Resistance Test, HV Impulse Test, Contact Resistance Test, CB Close/open timing Test, Secondary Injection test for Protection relays, Primary Injection Test for CT Ratio/Polarity/IR/Saturation Test, VT Ratio/Polarity/IR Tests. Ammeter & Volt Meter Calibrations.

Participated and Supervised Electrical Testing of Heat Tracing Cables and Circuit installations and commissioning of Heat tracing Circuits and Panels.

Participated and Supervised Electrical Testing of LT/HT Motors IR & WR Checks.

Participated and Supervised Electrical Testing for Transformers like IR, WR, Ratio, High Voltage Impulse Test, Vector Group& Polarity test, Turn ratio test Oil Dielectric Test.(BDV,DGA)

Participated and Supervised HV/LV Motor Solo Run Test, No Load and On Load tests.

Pre-Commissioning and Commissioning of Switchgear, MCC, PCC, UPS panels, Transformers, Motors, Emergency Diesel Generator, MOV’s, Cathodic Protection Systems, Heat Tracing Systems, HVAC Systems & Lighting Facilities.

Good Knowledge in commissioning of Photoelectric Systems (Solar Panel Systems)

Participated and Supervised Electrical Testing & Commissioning of Cathodic Protection system

Participated and Supervised Electrical Testing & Commissioning of UPS and Battery Chargers system

Participated in commissioning of HVAC System

Preparation of Pre commissioning and commissioning test sheets.

Participated and Supervised Predictive, Preventive and Break down Maintenance of All Electrical Equipment’s like Switchgear, Vacuum Circuit Breaker, Oil Circuit Breakers, Air Circuit Breakers, Motor Starters, Power Transformers, HV/LV Motors, UPS, Battery Charger System, Batteries, MOV’s, Cathodic Protection Systems, Heat Tracing Systems, HVAC Systems, Earthing system & Lighting facilities.

Expert in Troubleshooting of all Electrical Systems.

Competent in Plant Shut down Maintenances activities

COMPANY NAME

IMCO ENGINEERING AND CONSTRUCTION, Wafra, Kuwait

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Joint Operations Wafra Well Head Fields

Owner: Joint Operation Wafra

Contractor: IMCO

Role: Senior Electrical Technician

Duration: 2 Years 10 months

Scope: Electrical Maintenance activities at Well Head Sites

RESPONSIBILITIES HANDLED

Responsibilities include Supervision of Electrical Maintenance Activities as per client Schedules on Switchgear system,MCC,PCC,UPS panels

Prepare Daily Progress reports to client

Participated and Supervised Predictive, Preventive and Break down Maintenance of All Electrical Equipment’s like Switchgear, Vacuum Circuit Breaker, Oil Circuit Breakers, Air Circuit Breakers, Motor Starters, Power Transformers, HV/LV Motors, UPS, Battery Charger System, Batteries, MOV’s, Cathodic Protection Systems, Heat Tracing Systems, HVAC Systems, Earthing system & Lighting facilities.

Expert in Troubleshooting of all Electrical Systems.

Good Experience on Variable Frequency Drive Systems.

Knowledge about Sucker Rod Pumps, Progressive Control Pumps & Electrical Submersible pumps.

Competent in Plant Shut down Maintenances activities

COMPANY NAME

VIMCCO

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Revamping of New Kelin Project

Owner: AP Cements

Contractor: VIMCCO

Role: Electrical Engineer

Duration: 1 Years 1 months

Scope: Electrical Maintenance activities at Well Head Sites

RESPONSIBILITIES HANDLED

Responsibilities include engineering coordination and management, Preparation and review of planning package/schedule/milestone dates fix the project quality targets and objectives Identify project risks

Preparation and review of schedule

Review and Track Document Control Index (DCI)

Review and Track Material Control Index (MCI)

Prepare Catch up plan/ Reschedule the delayed activities

Resource Planning and allocation( Man power, Materials )

Prepare Weekly and Monthly Progress reports to client

Attend Review Meetings with Contractor and Client

Discuss and close out the input requirements

Issue Change Notices to client for approval

COMPANY NAME

ASTER INFRASTRUCTURES SERVICES LTD., KABUL, AFGHANISTAN

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Master switching Stations, Branch Switching Stations, Base Terminal Units Electrification Works

Owner: MTN,AWCC,ZTE Teleservices,Afghanistan

Contractor: Baarg Engineering Contractors

Role: Electrical Engineer

Duration: 1 Year

Scope: Design, and Project Management Consultant

RESPONSIBILITIES HANDLED

Responsibilities include engineering coordination and management, Preparation and review of planning package/schedule/milestone dates fix the project quality targets and objectives Identify project risks

Preparation and review of schedule

Review and Track Document Control Index (DCI)

Review and Track Material Control Index (MCI)

Prepare Catch up plan/ Reschedule the delayed activities

Resource Planning and allocation( Man power, Materials )

Prepare Weekly and Monthly Progress reports to client

Attend Review Meetings with Contractor and Client

Discuss and close out the input requirements

Issue Change Notices to client for approval

Actively Participated on Designing and Electrification of MSC,BSC,BTU units on Telecommunication Projects.

COMPANY NAME

BHARAT TECHNICAL SERVICES

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: L & T Air Circuit Breakers Annual Maintenance and Repairs,

Owner: HPCL,Shipyard,Dockyard

Contractor: Bharat Technical Services

Role: Service Engineer

Duration: 1 Year 11 Months

Scope: L & T Air Circuit Breakers Annual Maintenance and Service.

RESPONSIBILITIES HANDLED

Responsibilities include Annual Preventive Maintenance Activities and Servicing of L & T Air Circuit Breakers.

Preparation of Daily Reports and Job Completion Documents.

COMPANY NAME

THE NATIONAL ELECTRICAL WORKS

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Plant Maintenance Activities on GAIL

Owner: GAIL(Gas Authority of India ) Visakhapatnam

Contractor: The National Electrical Works

Role: Electrical Supervisor

Duration: 8 Months

Scope: Maintenance of all Electrical Equipment’s in a plant

RESPONSIBILITIES HANDLED

Responsibilities include Predictive Preventive & Breakdown Maintenance Activities on All Electrical Equipment’s in Plant

Maintenance of MOV’s

Preparation of Daily Reports

COMPANY NAME

ALMEER TECHNICAL SERVICES W.L.L, KOC, KUWAIT

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: KOC West Area GC-17,GC-27,GC-28,MWIP, Maintenance

Owner: Kuwait Oil Company(KOC) West Kuwait

Contractor: ATSCO

Role: Electrical Technician

Duration: 4 Years 10 months

Scope: Maintenance of All Electrical Equipment’s

RESPONSIBILITIES HANDLED

Participated and Supervised Predictive, Preventive and Break down Maintenance of All Electrical Equipment’s like Switchgear, Vacuum Circuit Breaker, Oil Circuit Breakers, Air Circuit Breakers, Motor Starters, Power Transformers, HV/LV Motors, UPS, Battery Charger System, Batteries, MOV’s, Cathodic Protection Systems, Heat Tracing Systems, HVAC Systems, Earthing system & Lighting facilities.

Expert in Troubleshooting of all Electrical Systems.

Competent in Plant Shut down Maintenances activities

Experience in Electrical Submersible Pumps

COMPANY NAME

RAMAKRISHNA RAO CO PVT.LTD.

KEY PROJECTS / ROLE / DURATION OF THE PROJECT

Project: Plant Maintenance Activities on GAIL

Owner: HSL,HPCL,Dockyard

Contractor: Ramakrishna Rao co

Role: Electrical Technician

Duration: 2 Years 6 Months

Scope: Plant Construction Activities

RESPONSIBILITIES HANDLED

Power Cable Laying,Tray Errections,Glanding Terminations

Erection and installations of Electrical Equipment’s

Motors and Cable Meggring and Loop Checking’s

DECLARATION

I do hereby declare that the above mentioned facts are true and correct according to my knowledge and belief.

YOURS TRULY

LAKSHMI VENKATA GIRI BABU.Y

LAKSHMI VENKATA GIRI BABU.Y

COMPETENT ELECTRICAL PERSONNEL (OVER 20 YEARS OF EXPERIENCE IN GCC & INDIA)

***********@*****.***/************@*****.**.** Kakinada, A.P., India

0091 934-***-****/965-***-**** 009*********** giribabuvsp27

Date of Birth : 01/08/1977 Nationality : Indian

Marital Status : Married Languages Known : English, Hindi and Telugu

Passport No : U 7528076 Place of Issue : Visakhapatnam

Date of Issue : 16/02/2021 Date of Expiry : 15/02/2031



Contact this candidate