abdul khaliq
Senior Land Surveyor
Contact Me
Mobile
***************@*****.***
Address
Zone 43 DOHA Qatar
Birth Date
Awards
Best App of the year
Skills
construction&Engineering
Languages
Arabic,English,urdu
Summary
Qatar ID+NOC +immediate availability on own visa
Worked as senior land surveyor in uae with
knowelege in AUTOCAD AND land surveyor from feb 1988 to2022 I have full controll to handle projects by use of latest survey equipments
&AUTOCAD
building construction high-rise medium Rise and Large scale construction of villas projects by using all latest survey equipments &AUTOCAD 2 all infrstructure pipe line projects CONSULTANT and client meetings attended in my past projects in UAE
I have done the job of cosultancy&Inspection of civil construction with ECG in Dubai 4Years
Please check details of my experience in cv
Thanks for kind action
Education
1987 - 1988
INSTITUTE OF SURVEYING
KHEWRA(DIST.JEHLUM)
Diploma In Surveying
attested from uae foreign affair
2006 - 2007
ICCI
Certificate AUTOCAD
Experience
july2021 -
oct2021
REDCO INTERNATIONAL WLL
Cheif Surveyor
Construction of bus depot
• Following the shop drawing for civil work.
• Attending the progress meeting with consultant.
• Controlling the quality of the finishing civil work at site.
• Reporting senior engineers P m
• stockpile calculation
• as built site survey
march2014 -
Aug2017
Khansaheb Civil Engineeringllc
Senior Land Surveyor
Project: Premier inn Hotel construction building works B+G+8STOREY+Gymnasium+roof at plot no 3265612
Location Al jadaf dubai
DUTIES
• Following the shop drawing for civil work.
• Attending the progress meeting with consultant.
• Controlling the quality of the finishing civil work at site.
• Reporting senior engineers
April2011 -
november2013
Ccc
Land SURVEYOR
Project: Presidential palace wings package Abu Dhabi Client: Ministry of presidential Affairs
United Arab Emirates
Duties and Responsibilities
• Following the shop drawing for civil work.
• Attending the progress meeting with consultant.
• Controlling the quality of the finishing civil work at site.
• Reporting senior engineers
apr2007 -
jun2010
Engineering Consultant Group(ECG)
Land Surveyor
● Inspection of shifted bench marks from approved Municipality bench marks
as project required, checked OGL, keeping record for verifying quantities for payments to contractor.
● Inspection of Layout out and levels Road works, sub base, wet mix, base course, wearing course, single face barrier, double face barrier, variable barrier, kerb stone, for Infrastructure works, excavation, formation, aggregate, centerline for laying pipe.
Inspection of structure work, measuring natural ground levels, control horizontal and
vertical alignment of piles, piles caps,,, side walls and back walls. Alignment and leveling
building works columns walls beams
Aug2003 -
Aug2006
AL HAMED DEVELOPMENT&CONSTRUCTION
Land Surveyor
Project Date : November 2005
Project Name: GASCO 3rd NGL Train Project (Abu Dhabi) Client : GASCO
Consultant : Snamprogetti
Project Description
● The Project consisted of four large tanks (two propane & two butane) each with a
capacity of 83600 m3 and constructed using steel line with 50 and 80 cm of concrete
outer wall and dome roof. Some of the special features incorporate into these tanks
include a corrosion monitoring system, heating system, inclinometer system,
embedment plates, stair tower, external ladder, 60” flare line, nitrogen line, elevator,
ship vapor line 24” main vapor line, main pipe rack line, external monorail wall, plate
form and ladder, roof plat form, trumpets in buttress walls, and the post tension
tendons in walls.
● This project stringently controlled by the Client specification for both quality and
safety.
Project Name: VIP Terminal Expansion II, Dubai Intl. Airport Client : DCA Dubai
Consultant : RMJM
Project Name : New Fire Station Dubai Intl. Airport Client : DCA Dubai
Consultant : DAR Al Handasah
Project Name: Up Town Midriff Development Package B & D (Dubai) Client : Union Properties
,
Duties and Responsibilities
● Setting out and leveling of formation, blinding, foundations, wall, retaining
walls, tower cranes, concrete beams, steel beams, concrete columns and steel columns.
● Alignment as per grid line and leveling of glass, aluminum and wooden cladding.
● Layout & Leveling internal side, doors, windows, block work, staircase. Electrical Lift, marble tiles, ceramic tiles on the floor or at the walls.
● Road works, carriageway, footpaths, parking, road marking, road signs, landscaping & MEP works.
1997 - 2003
Dhabi Contracting
Land Surveyor
Project Name : 1= Beda Zaid pipe line infrastructure project302 2=Gayathi pipe line line infrastructure project306 Consultant : KEO
Duties and Responsibilities
● Topographic survey, FOR NGL centerline, cross section for check cutting or
back filling as per profile grade level.
● Setting out for pipe line excavation.pipe line setting out
● Construction of pumping station treatment plants and reservoirs
● Calculation of levels, horizontal and cross slope.
● Restate of infrastructure
july1992 -
Dec1996
Daewoo Carporation
Land Surveyor
Project Name : Pakistan motor way
Client : National Highway Authority (NHA)
Consultant : National Engineering Services (NES, PAK) Duties and Responsibilities
● Topographic survey, road centerline, cross section for check cutting or filling
as per profile grade level.
● Setting out curves, culverts, retaining walls.
● Calculation of levels at super elevation, vertical curves, horizontal and cross
slope
March1988 -
apr1992
Hyundai Hidco
Land Surveyor
Project Name: Indus Bridge M1 Section II
Client : Pakistan Motorway
Consultant : Binder Engineering Consultant (Turkey) Project Name: Lei Bridge II
Client : National Highway Authority (NHA)
Consultant : Republic Engineering Consultant (REC) Duties and Responsibilities
● Measuring natural ground levels, Control Horizontal and Vertical Alignment
of piles, piles caps, abutment, piers, and transoms.
● Alignment and leveling bearing pads, Precast & pre stress girders bed, formwork, anchor plates.
● Ducts and supports arrange horizontal and vertical with profile for post tension cable internal and external, launching of girders.
● Setting out and leveling diaphragms, deck slabs, earth walls, approach slabs, expansion joints, side walk and handrail.