Qualifications: BSc. of civil engineering (structural) Damascus University graduate date 16/10/2001

Professional Summary

Faisal Youssef has over 20 years of experience in design, construction supervision and project management. Project construction manager professional with significant, demonstrable records in construction projects, including Palaces, luxury & VIP villas, medium to high rise mixed use developments, hotels & residential buildings. Leads & directs Engineers

& Inspectors; & maintains highest standards of safety & quality, while keeping cost within budget. Dynamic, results oriented, & adaptable, with superior relationship management skills. Analytical thinking, creative problem solver; cross functional leader who cultivates a positive, collaborative work atmosphere where multi cultural team members consistently exceed established objectives. Self directed, highly motivated, excellent listen & communicator who effectively conveys information, ideas clearly, concisely & persuasively; verbally & in writing via many different media. Have a high degree of computer literacy & able to use new technology and keeps abreast with current knowledge of issues. Industrial practices, trends & issues.

Skills and Core Competencies

Resident engineer manages and minute all technical and progress meetings and maintain all corresponding with client, contractor and follow up contractual issues

-Structural Engineering Design using AutoCAD, PROKON, (SAP, SAFE, ETABS) group & structural design software’s according to BS/ACI/IBC codes in creating new models or make updates of existing model to match final design of building (concrete, steel structure), review the design of PT slabs designed by specialist

-Steel structure design using STAAD PRO for elements design and for connections the available software tools include but not limited of

(Excel sheets, IDEA STATICA, LIMCON, and RAM CONNECTION) Construction Management Contract Management under FIDIC Conditions of Contracts Claims & Variations Review and Valuation, Payment Review, valuation & Certification Quantity Surveyor, Full-Cycle Project Coordination, Documentation and Progress Reporting Process Improvements, Cross- functional Collaboration, Quality Management & Quality Assurance Knowledge of Estidama Compliance Requirements, Cost Management & Control, Health & Safety Program & Extension of Time Claim Review, Budgets & Resources Management, Communication & Presentation, Design Coordination& Management, Training& Mentoring, Design Management & Coordination, Health

& Safety Management, Claims Review, Valuation & Certification of Payment Application, free-lance design for special structures such as VIP villas, micro piling design, tent’s structure design review, secondary steel structure for façade works, steel structure skeleton for GRP dome Experiences

RE civil &structural engineer November 2021 – present Company: HANNOVER consulting engineers LLC

Client: UAE Muay Thai & kick boxing federation

Developer: MOPA

company) Location: Abu Dhabi RAHA city

Project: construction of sports facilities building of UAE Muay Thai & kick boxing federation Projects value: 130 million AED

Duties and responsibilities included the following tasks:

Final review and approval for contractor plans logistic plan, HSE plan, ITP plan, CEMP plan, RMP plan…..

manages and minute all technical and progress meetings and maintain all corresponding with Employer/client, contractor and follow up contractual issues

final review and approval for weekly/monthly reports submitted by contractor and prepare weekly/monthly reports of consultant to employer and make sure to follow up with the base line time program and ask contractor for recovery program when need.

Final review and approval for monthly payments and coordinate with QS engineers and contract conditions

follow up variations, claims raised by contractor negotiation

follow up project mile stones, CPM, EVM to make sure the project will be finish within accepted time and budget by client

final review and approval of EOT after coordination with Employer and planer engineer

Follow up all construction day to day activities on the site and provide the site staff by final approved information.

Review site enabling works design and approval

Final Review & approval of structure technical submittals including shop drawings, materials, method statements, response to contractors RFI's.

Allocating daily and weekly tasks to my team members. Review Engineering Instruction before issue to contractor, review variation orders of contractor.

Final review for contractor structural calculations submitted for approval

Follow up all civil, technical, structural issues through the construction works

Follow up all inspection work requests with site engineers &, inspectors

Follow up the quality control of works on the site

review the NCRs before issue to contractor and review the close out of NCR's

Review closes out documents submitted by contractor RE civil &structural engineer JUNE 2020 – October 2021 Company: Altorath international consultant

Client: ADEK Department of education and knowledge Employer: Musanada (Abu Dhabi general services company) Location: Abu Dhabi Bahia city

Project: Abu Dhabi future school program phase 7 package 4 ABAHIA School Reference no: Eng. Isameldin Abdel Wahab (Musanada Project manager) 009*********** Duties and responsibilities included the following tasks:

Final review and approval for contractor plans logistic plan, HSE plan, ITP plan, CEMP plan, RMP plan…..

manages and minute all technical and progress meetings and maintain all corresponding with Employer/client, contractor and follow up contractual issues

final review and approval for weekly/monthly reports submitted by contractor and prepare weekly/monthly reports of consultant to employer and make sure to follow up with the base line time program and ask contractor for recovery program when need.

Final review and approval for monthly payments and coordinate with QS engineers and contract conditions

follow up variations, claims raised by contractor negotiation and finalize NPC before submission to Musanada procurement department

follow up project mile stones, CPM, EVM to make sure the project will be finish within accepted time and budget by client

final review and approval of EOT after coordination with Employer and planer engineer

Follow up all construction day to day activities on the site and provide the site staff by final approved information.

Review site enabling works design and approval

Final Review & approval of structure technical submittals including shop drawings, materials, method statements, response to contractors RFI's.

Allocating daily and weekly tasks to my team members. Review Engineering Instruction before issue to contractor, review variation orders of contractor.

Final review for contractor structural calculations submitted for approval

Follow up all civil, technical, structural issues through the construction works

Follow up all inspection work requests with site engineers &, inspectors

Follow up the quality control of works on the site

review the NCRs before issue to contractor and review the close out of NCR's

Review closes out documents submitted by contractor RE civil &structural engineer April 2020 – June2020 Company: Altorath international consultant

Location: Abu Dhabi Shakbout city

Project: ADM soil improvement project

Reference no: PhD Eng. ABD Al Aziz (Project manager) 009*********** Duties and responsibilities included the following tasks:

Coordinate works on site with 3 specialist soil improvement subcontractors

Follow up geophysical test on site and the analysis of results

follow up site test for bore holes and review the results

Follow up with design team for suitable geotechnical soil improvement solution grouting injection, stone columns, micro piles

Follow up all construction day to day activities on the site and provide the site staff by final approved information.

Review geotechnical and enabling works design and approval included but not limited to piling works design. And shop drawings by specialist.

Soil improvements using stone columns in some locations and on shoring/of shoring use sheet piling in some locations for deep excavations.

Prepare Structural report for impacted buildings by partial settlement existing situation reasons and propose the suitable solution for rectification

Review & approval of structure technical submittals including shop drawings, materials, method statements, response to contractors RFI's.

Allocating daily and weekly tasks to my team members. Review Engineering Instruction before issue to contractor, review variation orders of contractor.

review all contractor structural calculations submitted for approval

Follow up all civil, technical, structural issues through the construction works

Follow up all inspection work requests with site engineers &, inspectors

Follow up the quality control of works on the site

review the NCRs before issue to contractor and review the close out of NCR's

review close out documents submitted by contractor Lead civil &structural engineer / construction manager JUNE 2019 – JAN 2020 company: WSP/PARSONS BRINCKERHOFF LTD ABU DHABI

Project: SHIKAH ZAYED NATIONAL MUSEUM

Location: ABU DHABI, SAADIAT island

Client: ministry of culture

Reference no:

Duration: 01 07 2019 to 15 01 2020

Project description: museum has been designed by Foster + Partners with five solar thermal towers that will act as chimneys to draw cool air through the building.

The towers are shaped like falcon wings to commemorate Zaid’s love of falconry. Duties and responsibilities included the following tasks:

participating in all meetings as progress meetings, technical meetings, contractual meetings and prepare MOM when required and the drafts for all corresponding Letters to be confirm by top management before send

participating in design structural issues, construction management, Review of structure technical submittals including shop drawings, materials, method statements, Response to contractors RFI's. Allocating daily and weekly tasks to my team members. Review Engineering Instruction before issue to contractor,

Review variation orders of contractor. Review contractor payment applications. Liaised with local Authorities as required and obtain necessary building approvals.

• review all contractor structural calculations submitted for approval

• review all steel structure calculations of contractor using the suitable software STAAD PRO LIMCON, RAM CONNECTIONS, IDEA STATICA around 1200 tons

• Follow up all civil, technical, structural issues through the construction works

• Follow up all inspection work requests with site engineers &, inspectors

• Follow up the quality control of works on the site

• review the NCR's before issue to contractor and review the close out of NCR's RE civil &structural engineer JUNE 2017 – JUL 2019 company: WSP/PARSONS BRINCKERHOFF LTD ABU DHABI

Location: ABU DHABI, YAS Island

Project: YAS south IDR Yas south

FAMILY HOTEL B+L1+12 floors +R (550 keys), 2 basement parking levels, promenade/pier retails

YAS Bay arena 18,000 capacity indoor entertainment venue set to open on Abu Dhabi's Yas Island will officially be named Etihad Arena.

marine works for pier and sea wall

Reference no: Eng. IAN FRIEND (Project director) 009*********** Duties and responsibilities included the following tasks:

. participating in all meetings as progress meetings, technical meetings, contractual meetings and prepare MOM when required. And the drafts for all corresponding letters to be confirm by top management before send.

• Follow up all construction day to day activities on the site and provide the site staff by final approved information.

• Review geotechnical and enabling works design and approval included but not limited to piling works design. And shop drawings by specialist.

soil improvements using stone columns in some locations and on shoring/of shoring use sheet piling in some locations for deep excavations.

• Review & approval of structure technical submittals including shop drawings, materials, method statements, response to contractors RFI's.

• Allocating daily and weekly tasks to my team members. Review Engineering Instruction before issue to contractor, review variation orders of contractor.

• Review contractor payment applications. Liaised with local Authorities as required and obtain necessary building approvals.

• review all contractor structural calculations submitted for approval

• Review all steel structure calculations of contractor using the suitable software STAAD PRO, LIMCON, RAM CONNECTIONS, IDEA STATICA. Around 1200 tons

• Follow up all civil, technical, structural issues through the construction works

• Follow up all inspection work requests with site engineers &, inspectors

• Follow up the quality control of works on the site

• review the NCR's before issue to contractor and review the close out of NCR's

• review close out documents submitted by contractor RE civil &structural engineer JAN2015 – JULY 2017

company: Ewan architectural & engineering consultancy, Abu Dhabi – UAE Project: M TOWER

Location: AL REEM Island

M TOWER 3B+2P+29TYPICAL+R+UR

Reference no: Eng. ALAN SHEEPWASH (operations director) 009*********** Duties and responsibilities included the following tasks:

participating in all meetings as progress meetings, technical meetings, contractual meetings and prepare MOM when required and the drafts for all corresponding letters to be Confirm by top management before send

Reviewed & approved of technical submittals including workshop drawings, materials, method statements and risk assessment; responsible for responding to contractors’ request for information. Responsible for allocating daily and weekly task to team members; mentoring and supervising subordinates. Issued Engineering Instruction and variation order after consultation with the client. Reviewed & certified contractor’s payment applications; reviewed valuated & recommended Contractor’s claims for Extension of Time and associated costs. Liaised with local Authorities as required and obtain necessary building permits.

Follow up all civil, technical, structural issues through the construction works

Redesign all structural modifications &update SAFE/ETABS models accordingly

Follow up all inspection work requests with site engineers & inspectors

Follow up the quality control of works on the site Structural civil construction engineer DEC 2013 – JAN 2015 Company: Ewan architectural & engineering consultancy, Abu Dhabi – UAE Project: presidential palace (supreme council)

Location: new presidential palace

Main building B+G+M+1ST+R

Club house G+M+1ST+R

Mosque BUILDING

Reference no: Eng. Sameer Ali (PM) 009***********

Duties and responsibilities included the following tasks:

Review all reinforcement shop drawings & BBS; check up all structural drawings,

Follow up all civil, technical, structural issues through the construction works

Redesign all structural modifications &update SAFE/ETABS models accordingly

Follow up all inspection work requests with site engineers &, inspectors

Response all structural & civil RFIs

Follow up the quality control of works on the site Structural civil construction engineer OCT 2010 – DEC 2013 company: Ewan architectural & engineering consultancy, Abu Dhabi – UAE Project: Watani residential development

Khlifah City Abu Dhabi (17/10/10 – 15/12/2013)

Phase2 400 villas Budget (550million AED)

Reference no: Eng. Hatem Hamodah (PM)

009*********** Client: UPC

Developer: SOROUH

PMC: PMDC Management Company

Duties and responsibilities included the following tasks:

Review all reinforcement shop drawings & BBS; checkup all structural drawings,

Follow up all civil, technical, structural issues through the construction works

Redesign all structural modifications &update SAFE/ETABS models accordingly

Follow up all inspection requests of works at the phase 2 with site engineers & inspectors

Response all structural & civil RFIs

Follow up the quality control of works on the site Structural civil construction engineer – Aug 2009 – Oct 2010 COMPANY: Ewan architectural & engineering consultancy, Abu Dhabi – UAE Project: THE MALL AL AIN project Sanaya area (2B+G+M+2Typical+4th+R+UR Reference no: Eng. Tom Walsh (PM) 009*********** Client: SOROUH Developer: SOROUH

PMC: turner Management Company

Duties and responsibilities included the following tasks:

Review all reinforcement shop drawings & BBS for all the reinforcement concrete works

Check up all structural drawings, coordinate & get approvals for structural drawings from Al Ain municipality

coordination between architectural & structural drawings and all MEP services

review all steel structural design for skylights & steel structural roofs

follow up all civil, technical, structural issues through the construction works

Response all structural & civil RFIs

Follow up the quality control of Works on the site

Structural design for all modifications &updates SAFE/ETABS models accordingly Structural civil /construction manager – Jan 2007 – Aug 2009 Company: ACICO Construction Company, Dubai – UAE

Project: ACICO twin towers Sheikh Zaid Road

5 star Hotel tower (2B +G+M+4MECH+51) 5star hotel tower

(MUT) Mixed use tower (1B+G+M+4MECH+45) offices & residential MUT car park (3B+G+11)

Hotel car park (1B+G+10)

Budget (700 million AED)

Reference no: Eng. Salah Alden Nagy (PM) 009*********** Duties and responsibilities included the following tasks:

Construction Shift manager in hotel tower (1st stage underground up to 20th floor Skeleton works)

Later on (structural& technical project engineer) prepare all reinforcement shop drawings for both towers & manage staff of draftsmen &, checkup all structural drawings

reinforcement coordinating with 3 suppliers (check all BBS) & follow up steel orders in the site

follow up all technical issues & prepare coordination plans for tower cranes& site plans

prepare all steel structural design inside the towers and checkup the design of facade steel structural & link bridges (techno steel subcontractor)

coordination between architectural & structural drawings and all MEP services Structural civil construction manager FEB 2006 – Jan2007 company: ACICO Construction Company, Dubai –UAE

Project: ACICO Business Park (3B+G+M+9Typical+R) 04/02/06 to 01/01/07 Budget of project (77million AED)

Client: GASSAN AHMED ALKALED

Consultant: dimensions engineering consultancy

Reference no: Eng. Salah Alden Nagy (PM) 009*********** Duties & Responsibilities (such as but are not limited: Manage all construction works on site, prepare all reinforcement shop drawings and details, and coordinate all the works with subcontractors, Coordinate structural with MEP& architectural drawings, Submit all structural & civil RFI, s and proposals. Project engineer April 2005 – Feb2006

company: Suhaib contracting company

Project: (B+G+7+R) Moyleh area Sharjah (Skeleton +finishing) works Duties & Responsibilities such as but are not limited: Manage all construction works, prepare all reinforcement shop drawings and details, coordinate with all subcontractors, coordinate structural with MEP& architectural submit all RFI and proposals. Structural design engineer – OCT 2001 – Apr 2005

Civil engineering section irrigation ministry (Syria) Buildings Design section 16/10/2001 to 24/03/2005 EMPLOYMENT HISTORY

Altorath consulting engineers LTD ABU DHABI 01 04 2020 to present RE civil structural engineer

WSP/PARSONS BRINCKERHOFF LTD ABU DHABI 09 07 2017 to 15 01 2020 RE civil structural engineer

Ewan architectural & engineering consultancy, ABU DHABI 2009 to 201*-**-**-**** to 06 07 2017

RE. STRUCTURAL &CIVIL CONSTRUCTION ENGINEER

ACICO Construction Company, Dubai 2007 to 2009

2007 to 2009 STRUCTURAL&CIVIL CONSTRUCTION MANAGER GASSAN AHMED AL KHALED CONTRACTING unit of ACICO group of Companies, Dubai DERA port said area 2006 to 2007 structural construction manager

SUHAIB contracting company, Sharjah 2005 to 2006

2005 to 2006 CIVIL PROJECT ENGINEER

Irrigation ministry, Syria 2001 to 2005

2001 to 2005 building structure engineer (designer) Personal information:

Visa status: employment visa

Nationality: Syrian

Date of birth: 15/03/1976 Syria, Dara

Marital status: married

Drive license: UAE /Syria DL

Languages: Arabic/English