Post Job Free

Resume

Sign in

Construction Manager Site Engineer

Location:
Al Masfalah, Makkah, Saudi Arabia
Salary:
10000
Posted:
July 27, 2022

Contact this candidate

Resume:

Shahnawaz

Khan

Construction Manager

Nationality – Indian

Age – 28 years

Positive attitude results oriented, creative, motivated

PO Box No. 1311, Yanbu Al-Bahr, KSA

adrwa0@r.postjobfree.com

+966-*********

Professional Skilled

CIVIL Infrastructures: Construction, Installation &Testing, of Electrical MANOLES, DUCTS, FOUNDATION.

Transmission & Distribution: Transformers, PSS, PMS, and MV & LV Metering Cubical.

MV (34.5 – 13.8 KV) Cables:

Duct Bank and Direct Buried.

Awards

Appreciation Letters from STICCO

Computer Skilled

Microsoft Office Suite, AutoCAD CIVIL,

STAD PRO

Professional Educations:

Diploma in Civil Engineering– 2012, INDIA

Work Experience

08 years in the field of civil Infrastructure.

April 2017 –Till Date, Construction Manager

Royal Commission PIC I-T-7054

Royal Commission: SOLAR FIELD PILOT PROGRAM (STAGE 1A)–

SITE PREPARATION (ROUGH GRADING). - Yanbu – KSA

M/s Saudi Al-Terais Trading & Industrial Contracting Co. Ltd

Responsible for:

Upgrading of Electrical Utility Distribution 13.8 and 34.5 KV Network.

Construction of Electrical duct bank, Equipment foundation and Electrical manholes.

Repair of Existing Manhole & Duct as per Requirements.

Responsible for:

Monitor all project activities are carried out in accordance with project Specification, Method of Statement and ITPS. Develop a master audit Schedule and arrange execution of the audits to the schedule requirements.

Implementing Quality Control activities and ensuring compliance of project work with the Contract.

Coordinating with the construction engineers and client’s inspectors for Clearing designated inspections (Hold and Witness point), perform in Progress and final inspections of Civil and other activities in accordance With IFC Drawing.

Conduct Material Receiving Inspection at site and ensure material to be confirming to Contract Plans.

Issuance and Close out of NCR for Non Conformity work and Product, Suggesting and verifying the proposed actions in Coordination with the Client’s Technical Engineers.

Consulting with Quality and Construction Manager for improving quality System at Site. Updating revision of drawing according to amendments and modification carried out in field .Preparation

And reviewing of Hand over Documentation packages as required by the Client.

Monitored project QA/QC activities during the construction phase.

Setting up and monitoring quality’s system including quality control procedure (QCP) and quality plan’s (QP) for civil construction projects.

Prepared and implement QC plans, ITP’s plan and keep records for ITL’s reports.

Supervised a multi discipline team of QC engineer/inspectors on site including a site civil material

Testing laboratory.

Attained meetings with consultants, vendors, subcontractors and took necessary action against

Deficiencies and resolved site issues.

Conducting audits to verify that plans and procedure are being followed and provided documentary evidence is produced and maintained.

Prepared, Reviewed and coordinated shop drawing, submittals, answering RFI’s and quotations

From the consultants, vendors, subcontractors.

Prepared handover initial Acceptance inspections (IAI) to consultant end user.

Handle all quality issues with project management.

Also responsible for the monthly progress report, monthly invoicing.

Anchoring on site construction activities to ensure competition of project with the time & cost

Parameters and effective resource utilization to maximum the output.

Implementing quality plans/manuals ensuring high quality standard at different stages of project

& construction activities

Employment Records:

April 2017 Till Date, Construction Manager[CIVIL]

Project Title: PIC I T-7054

April 2016 – April 2017, Assistance QA/QC Manager[CIVIL]

Project Title: MARAFIQ-: Upgrading of Electrical Utility Distribution 13.8 and 34.5 KV Network systems - Yanbu – KSA Outline Agreement No # 730*******

Saudi Al-Terais Trading & Industrial Contracting Co. Ltd (STICCO)

April 2014 to April 2016, Senior Civil Engineer

Project Title: MARAFIQ-Upgrading of Medium Voltage Underground Electrical Utility Distribution Networks, Yanbu, Royal Commission. Outline Agreement No # 730*******

Saudi Al-Terais Trading & Industrial Contracting Co. Ltd (STICC

August 2014 to April 2015, Site Engineer

Project Title: PIC I-1095 C- General Services for Utility Connections to various Investments at Industrial Area (Project at Royal Commission, Yanbu)

Saudi Al-Terais Trading & Industrial Contracting Co. Ltd (STICCO)

August 2012 to January 2014,, Site Engineer

Project Title: BTU Constructions and Interior PVT. L.td.

Delhi, India.

Recent Projects in Saudi Arabia:

Upgrading of Electrical Utility Distribution 13.8 and 34.5 KV Network systems – MARAFIQ, Yanbu – KSA

Repair of Medium and Low voltage cables & Upraising of distribution Equipment’s - MARAFIQ, Yanbu

General Services for Utility Connections to various Investments at Industrial Area

(PIC I-7715, 7716 & 7709 Project at Royal Commission, Yanbu)

Main project features & activities performed: Responsible for MARAFIQ Upgrading of Electrical Utility Distribution 13.8 and 34.5 KV Network system Transformers, PMS (Pad Mounted Switchgear) MV Metering Cubical and 13.8 to 34.5 KV Cables (Duct Banks & Direct Buried System) Erection and Installation, Testing and Commissioning etc.

General Services for Utility Connections to various Investments at Industrial Area (Project at Royal Commission, Yanbu)

(PIC-7715 & 7709). Worked as a SENIOR SITE ENGINEER from 10 April 2017 -2014 to till.

Maintaining all RFI of contractors

Reviewing and maintaining of Drawing, BOQ and specification

Maintain the testing of soil (compaction) FDT sub grade and backfilling layer by layer as per RC

Standard for DUCT BANK, MANHOLES witness with CLIENT Representative.

Conduct pressure test for the duct Bank as per RC standard

Maintain the testing of concrete (slump, unit weight, temperature, air content) test as per

Approved concrete design mix with CLIENT Representative

Preparing BAR BENDING SCHEDULE (BBS) on Excel

Preparing material Reconciliation

Maintaining Monthly progress Report of contractors

Analyzing the requirement of the project and preparing the estimations accordingly

Having quantity duties including measurement from AutoCAD drawing and site measurement as

Per specification

Manhole concrete Repair work

Maintain the quality as per specification for structure (Duct Banks, Manholes)

Attending Weekly meeting with client, consultant

Saudi Al-Terais Contracting Co. Ltd (STICCO) – Site Engineer

UPGRADING OF ELECTRICAL UTILITY DISTRIBUTION NETWORK (SAUDI AL-TERAIS CO. Ltd) –YANBU

DURING July -2014 to 10 April 2017

Hands on experience in installation of DUCT BANK, MANHOLES & FOUNDATIONS.

Provided site supervision and field engineering on underground ELECTRICAL, MECHNICAL utilities, during construction.

Supervision on the installation of Conduit Pipes, FDT sub grade soil testing, BACKFILLING layer by layer testing, by Approved ITL as per approved “ITP”.

Capable of preparing and reviewing of method statement, ITP, material submittals and risk assessment as per standard procedures related to civil works.

Material Quantity takes off, ordering and follow up for same according to project planning and budget.

Knowledge in Construction Safety, Confined Space Entry, and First Aid

Role and Responsibility:-

Preparing of documentation which is required for the current bill as for example, sieve analysis of

The coarse aggregate and fine aggregate and also elongation index and fluking index of aggregate.

Preparing of register which is related to quality as per IS code provision like, cube register, slump

Register, BOI register, structural register, coarse aggregate &fine aggregate register like

10mm, 20mm, sand, cement register, steel register.

Preparing of current RA bill according to completion of work as per BBU per month.

Preparing of pour card according to Delivered concrete at site.

Preparing of CHP clearance report for current bill.

Testing of cube according to IS 456-2000 for 7 & 28 days.

●Slump test according to IS 456-2000 for every batch of concrete

Role and Responsibility:-

Housing project.

Earth work (Mass Excavation, Backfilling).

Foundation structure work

Recent Projects in Saudi Arabia:

Upgrading of Electrical Utility Distribution 13.8 and 34.5 KV Network systems – MARAFIQ, Yanbu – KSA

Repair of Medium and Low voltage cables & Upraising of distribution Equipment’s - MARAFIQ, Yanbu

General Services for Utility Connections to various Investments at Industrial Area

(PIC I-7715 & 7709 Project at Royal Commission, Yanbu)

Main project features & activities performed: Responsible for MARAFIQ Upgrading of Electrical Utility Distribution 13.8 and 34.5 KV Network system Transformers, PMS (Pad Mounted Switchgear) MV Metering Cubical and 13.8 to 34.5 KV Cables (Duct Banks & Direct Buried System) Erection and Installation, Testing and Commissioning etc.

Personal Details:

Name: Shahnawaz Khan

Parentage: Qamaruddin

Date of Birth: 1st May 1993

Marital Status: Married

Languages Known: English, Hindi, Urdu

Permanent Address: 116 Laxman Ganj, Chandousi Distt. Sambhal (U.P) India.

Contact No’s:+966-********* (KSA)

Passport No: L 2109654

Valid Saudi Driving License

Certification:

I, the undersigned, certify to the best of my knowledge and belief that:

This CV correctly describes my qualifications and my experience.

I understand that any willful misstatement described herein may lead to my disqualification or dismissal.



Contact this candidate