PROGRESS REPORT
WBS # ***
TASK ORDER # 29
Report Period: 05/1/2022 till 05/31/2022
I.WORK ACCOMPLISHED THIS PERIOD
Pavlick Benjamin – ARE/Construction Inspector
EA #: 0K122-3
Project ID: 08-1500-0244
Review project plan, specification, special provision, standard plan &
Spec before starting the work shift .
. Check e-mails & respond accordingly .
. Complete daily diaries & submitting electronically .
. Attending at 6:00 pm on daily bases at prime contractor construction yard
Discussing with superintendent about work shift activities upon 4 weeks
Look ahead schedule & agreed about performed contract item works
Quantities on previous work shift .
. Filling agreed contract item works quantities at quantity folders for
Preparing monthly estimate Q sheets .
. Checking, inspecting daily routine contract item works & approved
SWPPP plan BMP’S .
. Incase of BMP’S maintenance needed asking contractor to proceed
, Taking photos, informing project resident engineer & following
On maintenance work .
. Checking, inspecting performance of approved change orders, singing
The tentative agreement form after job completion.
. Attending on bi-week bases on safety meetings .
. Attending on weekly construction meeting .
II.WORK SCHEDULE FOR THE NEXT PERIOD May 1 till May 31, 2022
Pavlick Banjamin – ARE/Construction Inspector
EA #: 0K122-3
Project ID: 08-1500-0244
Continue Roadway excavation at I-15, fine sub grade per plan & median
Paving within project construction limit upon 4 weeks look ahead & Approved CPM .