RESUME
Edwin Pajara
EDWIN PAJARA
Scheduler
Mr. Edwin Pajara has over 14 years of experience with construction project scheduling. He has developed master and baseline schedules and is knowledgeable with work breakdown structure (WBS), critical activities, logic relationships, cost loading and preparing look-ahead schedules. Mr. Pajara has generated, and reviewed reports of earned value for month billings and tracked change orders and time impacts creating a recovery schedule for any slippage. RELEVANT EXPERIENCE
June 2021 – August 2021
In the Philippines on personal leave
October 2020 – May 2021
Maximum Nutrition, Inc. – Los Angeles, CA
Salesperson
March 2019 – September 2020
The Austin Company – Irvine, CA
Construction Scheduler
Projects: Northrop Grumman Aerospace Factory Modernization Project, $58 Million & Aerojet Rocketdyne Los Angeles Expansion Project, $24 Million
Created and developed baseline construction schedules from general conditions, and submittals
Reviewed processes and procurement delivery, construction phase with project specific WBS thru to the close-out requirements with team effort involving construction team who will execute the job
Identified the critical activities and created relationship and logic, tied-in activities with other trades and tracked constraints that may possibly affect our own scope of work
Prepared a cost loaded activity schedule as owner schedule of values
(SOVs)
Updated schedule periodically to monitor progress of the job in collaboration with the construction team
Prepared two or three week look-ahead schedules
Tracked change orders that affected the time duration of the project
Ran report with earned value for monthly billing
If required, developed, and created recovery schedule if there was slippage with the contract due to various legitimate reasons
Created a master schedule for the company for monitoring purposes and resources usage
Prepared and created a narrative report supporting the time impact analysis (TIA) and the chronology of events and constraints that affected the time durations
If required by the owner, submitted a TIA to justify delay due to various reasons such as a change order request (COR) or productivity delayed due to unforeseen conditions of the job or stocking of trades caused by multiple trades working on the project
Tracked productivity to meet our company profitability and or mitigate lost in the production line
YEARS OF EXPERIENCE
14+
EDUCATION
MS, Business Administration –
Collegio De San Juan De Letran,
Manila, Philippines, 2005
BS, Civil Engineering – Far Eastern
University, Manila, Philippines,
1982
CERTIFICATIONS / LICENSES
OSHA 30-Hour
OSHA 10-Hour
SOFTWARE
Primavera P6
Planswift
MS Project
World of Concrete – 2005
Microsoft Office (Word, Excel,
Outlook)
RESUME
Edwin Pajara
January 2019 – March 2019
VNSM Metal – Paramount, CA
Construction Scheduler
Various Projects
Created and developed baseline construction schedules from general conditions, and submittals
Reviewed processes and procurement delivery, construction phase with project specific WBS thru to the close- out requirements with team effort involving construction team who will execute the job
Identified the critical activities and created relationship and logic, tied-in activities with other trades and tracked constraints that may possibly affect our own scope of work
Prepared a cost loaded activity schedule as owner SOVs
Updated schedule periodically to monitor progress of the job in collaboration with the construction team
Prepared two or three week look-ahead schedules
Tracked change orders that affected the time duration of the project
Ran report with earned value for monthly billing
If required, developed, and created recovery schedule if there was slippage with the contract due to various legitimate reasons
Created a master schedule for the company for monitoring purposes and resources usage
Prepared and created a narrative report supporting the TIA and the chronology of events and constraints that affected the time durations
If required by the owner, submitted a TIA to justify delay due to various reasons such as a COR or productivity delayed due to unforeseen conditions of the job or stocking of trades caused by multiple trades working on the project
Tracked productivity to meet our company profitability and or mitigate lost in the production line 2007 – 2018
Best Contracting Services, Inc. – Gardena, CA
Construction Scheduler
Various Projects
Created and developed baseline construction schedules from general conditions, and submittals
Reviewed processes and procurement delivery, construction phase with project specific WBS thru to the close- out requirements with team effort involving construction team who will execute the job
Identified the critical activities and created relationship and logic, tied-in activities with other trades and tracked constraints that may possibly affect our own scope of work
Prepared a cost loaded activity schedule as owner SOVs
Updated schedule periodically to monitor progress of the job in collaboration with the construction team
Prepared two or three week look-ahead schedules
Tracked change orders that affected the time duration of the project
Ran report with earned value for monthly billing
If required, developed, and created recovery schedule if there was slippage with the contract due to various legitimate reasons
Created a master schedule for the company for monitoring purposes and resources usage
Prepared and created a narrative report supporting the TIA and the chronology of events and constraints that affected the time durations
If required by the owner, submitted a TIA to justify delay due to various reasons such as a COR or productivity delayed due to unforeseen conditions of the job or stocking of trades caused by multiple trades working on the project
Tracked productivity to meet our company profitability and or mitigate lost in the production line RESUME
Edwin Pajara
Projects Include:
Pier 33-Re-Roofing and Related Structural Repair, $2.7 Million
Golden Gate-San Rafael Administration Building, Re-roofing HVAC, electrical work, interior
Renovation, $ 1.4 Million
LAX-TBIT South/North and Gateway Concourses, Aluminum composite façade building envelope, $ 6.5 Million
Rancho Cordova Library Re-roofing, $800,000
Transbay Below Grade Roofing and Deck Water Proofing, $12 Million
China Lake Naval Facility, Complete tear-off and re-roofing, $2.4 Million
Fallon Naval Facility, $2 Million
Camp Pendleton, $5 Million
Dana Middle School Roofing, $1.3 Million
Hermosa Valley View Elementary School Roofing, $600,000
Inland Empire Utilities Roofing, $1.7 Million
Abraham Lincoln High School Roofing, $1.4 Million
LAX-Midfield and Gateway, $5.7 Million
Los Angeles Football Club, Roofing, paver, metal panels and water proofing, $4.5 Million
Oroville Thermalito Pumping Plant, Tear-off and roofing, $1.6 Million
Horrace Mann Middle School Classroom Building Roofing-$1.1Million
Calabasas High School Performing Arts Education Center Roofing, $500,000 1990 – 2000
E.L. Pajara Construction – Philippines
Owner/General Manager/Estimator
Various Projects
• Read plans and performed cost estimates for submission to bids
• Prepared budgetary cost for the implementation of project awarded
• Organized work force
• Purchased materials and scheduled deliveries
• Performed inspection and delegated instruction to the supervisor and foremen
• Prepared and submitted monthly billing
• Prepared close-out documents
1989 – 1990
R.B. Electrical & Construction – Saipan, USA
Project Engineer/Estimator
Various Projects
• Read plans and performed quantity take-offs and cost estimates
Submitted bids
Attended job walks
• Performed inspections and supervised the on-going project
• Prepared two-week look-ahead schedules
• Prepared progress reports
• Ensured safety at the job site and quality control the project RESUME
Edwin Pajara
1985 – 1988
A.C. Mojares Construction – Philippines
Project Engineer
Supervised construction projects of secondary, tertiary waterlines and house service connections, concreting and asphalting of various city roads
1978 – 1984
Department of Engineering – Philippines
Project Inspector
Performed inspections and checked quality of work for various city and government projects such as city roads, school buildings, libraries, and flood control projects