Power Projects, Estimation

Location:
New Delhi, Delhi, India
Salary:
Negotiated
Posted:
August 24, 2021

Contact this candidate

Resume:

CURRICULAM-VITAE

KAVENDRA SINGH Contact No. +91-893******* Vill- Ramhuth Post-Kailsa +91-843*******.

Dist- J.P. Nagar (Amroha) (U.P.) (E mail- adob5k@r.postjobfree.com)

Pin -244221

OBJECTIVE:

Seeking challenging assignments across Electrical Projects / Industry where I can be most effective in providing quality and speed in Electrical work.

ACADEMIC QUALIFICATION:

12th from U.P. Board with 55.6% .

10th from U.P. Board with. 63.33%.

TECHNICAL EDUCATION:

Diploma (three years) in Electrical Engineering from Govt. Poly. Moradabad with 74.67% in 2006.

PROJECT PROBLEM:

Wiring Installation & Estimating Costing of a Polytechnic building.

VOCATIONAL TRANING:

One month vocational training in 400KV substation in Majhola in Moradabad.UP.

COMPUTER KNOWLEDGE:

Ms word, Excel and Internet etc.

PROFILE:

Anchoring on-site work activities to ensure completion of

project within the time & cost parameters and effective resource

utilization to maximize the output.

Decide the work plan & schedule.

Material Procurement and Inspection at vendor site.

Dealing With Contractors.

Project scheduling including material & manpower planning.

Participating in project review meetings for tracking project progress & implementation of QA/QC procedures as per norms and standards.

Ensure on time delivery of materials without hindering construction activity to achieve overall on time completion of project.

Survey, Erection, Testing and commissioning, Measurement, Preparing bills of contractors and clients, filling the MB, handing over the work.

Making daily progress Report.

EXPERIENCE: (14+ Years)

Worked in M/s RK Industries Ltd. (A Unit of SRCIL) Bareilly (U.P). As a Quality Officer since July 2019 to Sep 2020.

Worked with PMC “Electrical Research development Association” Deputed at Aligarh Zone DVVNL, Agra (U.P.) DDUGJY/IPDS Projects” since July 2016 to July 2019.

NKG INFRASTRUCTURE LTD. as a Site Engineer under “RAPDRP WORK” for MVVNL LUCKNOW ZONE since 1st July – 2014 to July 2016.

HYTHRO POWER CORPORATION LTD/GET POWER LTD.( Tecpro Group) Project Engineer under “RGGVY”, “RAPDRP” for MPPKVVCL INDORE and “SOLAR PROJECT for NTPC FARIDABDAD” since Sep-2011 to 23 June 2014 .

A2Z MAINTINANCE & ENGINEERING SERVICES LTD. Project Engineer under “HVDS PROJECT” at KARNAL, and “METER SHIFTING PROJECT” at JALANDHAR since March -2010 to Sep-2011

A Square Automation (P) LTD. New Delhi. Site Engineer under Project “L PICK System” for Maruti Suzuki India Ltd. Manesar Gurgaon (HR) since 04.10.2008 to March-2010.

ENGINEERING PROJECTS (INDIA) LTD., Electrical Supervisor under “RGGVY” for PVVNL U.P. in BIJNORE distt. Since Jan 2007 to Aug 2008.

1. RAPDRP/IPDS WORK:

1.Survey of Town and Consumer indexing for Load calculation.

2.Construction of New/ Augmentation 33/11 KV S/s (Installation of Switch yard Structures & Switch Gears, PTR Plinth, Control room, VCBs, Control panel) and Its 33/11 KV associated lines.

3.Construction of 11KV & LT lines [pole spotting, pole erection, hardware fixing, stringing of conductor].

4.Erection of new 11/.4 KV, 25 KVA/63KVA/100KVA/250KVA substations, at load center Location fixing Trivector Meter, TPNIC, energy meters at Double pole mounted substations.

5.Shifting of Mother DTR according to their Load centre, reduce the length of LT lines.

6. Replacing the overloaded LT lines/ damage conductor by new rabbit conductor at Cable in theft prone areas in place of bare conductor lines.

7. Meter shifting inside to outside at consumer house, provide service cable with minimum length of LT lines. Change the damage /off Energy meter.

8.Testing, commissioning & charging the lines and DTRs.

9.Strengthening the lines, DTRs, change the Damage /Rough parts, in R&M work.

2.HVDS WORK:

10.Existing LT lines survey for Conversion by 11KV (High Voltage AC System).

11.Construction of 11KV lines [pole spotting, pole erection, hardware fixing, stringing of conductor].

12.Erection of 11/.44 KV 3 phase, 6.3, 10,16,20 KVA Single Pole mounted substations, 11/.44 KV 3 phase, 25, 40 KVA Double Pole mounted substations..

13.Testing & commissioning of converted lines and tube well connection sub stations and offer for handing over, Preparing the measurement, drawings & erection bills of contractors, and data entry of the records.

3. METER SHIFTING PROJECT:

14.Existing LT lines survey for Conversion by XLPE 4Core Cable 440V.

15.Erection of 20*1 pillar box, meter shift from consumer house to pillar box, and provide service cable to consumer according their electrical load.

16.Erection of XLPE 4Core Cable 440V.

17.Testing & commissioning & handing over the work to PSPCL.

18.Preparing measurement, drawings & the erection bills of contractors, and data entry of the records.

4.RGGVY/DDUGJY PROJECTS:

19.Construction of New/ Augmentation 33/11 KV S/s (Installation of Switch yard Structures & Switch Gears, PTR Plinth, Control room, VCBs, Control panel) and Its 33/11 KV associated lines.

20.Villages survey for electrification by 11KV & 220V LT AB cables lines.

21.Construction of 11KV & LT lines [pole spotting, pole erection, hardware fixing and stringging of conductor].

22.Erection of 11/.25KV,16 KVA substations, fixing Trivector Meter, TPNIC,energy meters at Double pole mounted substations, providing service connections wiring kit with energy meter to BPL household.

23.Testing & commissioning of electrified village and offer the village to Inspection Agencies ERDA, Safety Department to receive NOC for charging the lines.

24.Preparing the erection bills of electrified villages and handing over the electrified village to Client/Discom.

25.Erection of Outgoing 11KV Lines/feeders and 11 KV BAY at 33/11KV substations[Testing & Commissioning, Preparing erection bills, Handing over the lines].

26.11 KV Feeder separation of domestic load & Agriculture Load.

27.System strengthening work of existing network.

5. SOLAR POWER PROJECT:

A.CIVIL WORK:

1. Find Mark for structure foundation, Pit digging, RCC and piling for Structure Installation. Common leveling of structure by Water level, Sprit level and Sahul. And grouting of Structure Member. Structure Erection.

2. Cable trench execution/ back filling for UNDER GROUND AC, DC POWER AND COMMUNICATION CABLES.

3. Foundations / plinth for switchgear structure, control panels, VCBs and Power transformer.

B.ELECTRICAL WORK :

1.Installation of Solar Photo voltaic module, String combiner box, Making string using by MC4, Y- connector.

2.Cable laying work of UNDERGROUND AC HT CABLE (1C*240,3C*120 33kv), AC LT CABLE (1C*300 415 v), DC POWER CABLES (1C*185, 1C*240 1000v), COMMUNICATION CABLES FOR SCADA AND ETHERNET FIBER OPTICAL.

3.INSTALLTION AND GROUTING OF HT PANEL, INVERTOR, LT ACB, POWER TRANSFORMER,CT, PT, LA, BATTERY CHARGER WITH BATTERY BANK, UPS, AUXILIARY SUPPLY TRANSFORMER, PDBs, LDBs, RTU, CONTROLLER,

4.Earthing arrangement for Structures, Inverter, power transformer Switch yard by 25*6 /50*6 mm GI flat.

5.CABLE TERMINATIN AND CABLE GLANDING.

6.SWITCH YARD WORK AND EARTHING BY EARTHMAT (50*6 GI STRIP) etc.

6. L-PICK SYSTEM (INDUSTRIAL AUTOMATION):

1.Hardware installation for L- PICK (Fool Proofing) system like CLW /CW, which is two wire communication system.

2.Data feeding of vehicle models for identification.

3.Making report of daily status of system for Client/ Costumer.

4.Maintenance/modification of system and network etc.

Expected CTC : Negotiable

Ready to work in Abroad:

PASSPORT NO : M1708015

DECLARATION:

I here by declare that the above written information is true to the best of my knowledge and belief.

Date:

Place: (KAVENDRA SINGH)