Michael Michael, CCM. QSP. CPSI. LEED AP. (BD+C)

Seal Beach, CA

949-***-****

adnm3m@r.postjobfree.com

Education: B.Sc. in Civil Engineering May 2001.

Licenses:

•Contractors' State License Board CSLB # 1026252 Classes A, B & C-10

•Certified Construction Manager CCM # 8650.

•Certified Safety Playground Inspector. CPSI # 21082.

•Project Management Professional PMP.

•Certified LEED AP (BD+C).

•QSP, Qualified SWPPP Practitioner.

•CASp - ADA Compliances Certificate.

•State of CA Notary Public. COMM #2355621.

•Enrolled in online JD Program with Northwestern California University School of Law.

Experience:

A- RenewAge Energy Solutions:

Position: Senior Construction Manager/ Chief Estimator (02/20 – Present)

1.Julianna Park. Anaheim, CA. (850k).

2.LACCD Improvements and Classrooms upgrades. (1.4M).

3.Multiple EV Commercial Projects.

B- GKK/ Cannon Design:

Position: Projects Construction Manager (12/2017 – 02/2020)

1- Project: New Admin. Bldg. for West Hills College. Coalinga, CA, ($ 15M)

2- Bakersfield College GYM and Field House "GMP". Bakersfield, CA ($ 54M)

3- ADA Campus Wide Barrier Removal. Santa Clarita, CA ($ 3.8M).

C- AEC Development Inc.

Position: Part Time Projects Estimator & Schedular (01/2015 - 01/2017)

1- Project: AGIA Pharmacy & Cafe (Design Built contract)

Location: Tehachapi, CA.

Budget: $4,700,0000.

2- 48 Units Multi-unit building apartments. (Design Built contract)

Location: Riverside, CA.

Budget: $36,000,000.

3- Rowland HS Classrooms Additions

Location: Rowland Heights, CA

Budget: $44,600,000.

D- Hellas Construction Inc.

Position: Projects Operation Manager (01/2015 - 01/2017)

1- Heritage Soccer & Baseball Field renovations. (Puyallup, WA). Budget: 6.4M

2- Bell Harden soccer field improvements. (Bell Garden, CA). Budget: 1.7M.

3- Folsom USD Soccer Field & Track replacement. (Folsom, CA). Budget: 2.2M.

4- Cleveland HS New Soccer field & Track. (Seattle, WA). Budget: $3.8M.

5- Tacoma USD New Baseball & Soccer field. (Tacoma, WA). Budget: $3.2M.

E- Aghapy Construction, Inc.

Projects Manager/ Senior Estimator (08/2010 - 01/2015)

1- Santa Monica Pier Rehabilitation. (Santa Monica, CA). $6,970,000.

2- Pasadena Rec. Park Renovations. (Pasadena, CA). $7,800,000

3- Stanton Park Playground Installation. (Stanton, CA). $1,988,000

4-Mason regional Park (Irvine, CA). $8,850,000

5-Raymond Arbor Park playground replacements (Signal Hill, CA). $3,786,000.

6-CDC N. Classroom Expansion (Antelope Valley Joint Union HSD). $5,595,000.

7-Whittier OFF Leash Dog Park (Whittier, CA). $9,100,000.

8-Holly-dale Regional Park (South Gate, CA). $5,400,000.

9-Phelan Pinion Hill park Expansion (Phelan, CA). $8,895,000.

10-Rosamond Playground Upgrades (Rosamond, CA). $2,210,000.

11-Hamilton Clinic Phase II (Long Beach USD). $25,400,000.

12-Wasco State Prison Clinic Renovation & Upgrades. $19,12,000.

13-Kern Medical Records upgrades (Bakersfield, CA). $23,645,000.

14-Moon River Park Playground Improvements (Jurupa Valley, CA). $4,960,000.

15-Arrowhead Regional Medical Center Improvements $27,800,000.

16-Earlimart Clinic. (Earlimart, CA). $14,800,000.

F- Y&M Construction, Inc.

Project Manager/ Senior Estimator: (06/2009 - 08/2010)

1- San Antonio College Expansion (Walnut City, CA). ($4,800,000)

2- Lincoln Middle School New Modular Classroom Expansion (Santa Monica USD, CA). ($3,650,000)

3- Decker Elementary School (Pomona USD, CA). (8,850,000)

Position Duties:

Supervising & Managing various site activities which included:

■HV. Main Switch Gear and Distribution Panelboards.

■Underground Electric PVC. Pipes and Concrete Encasement.

■Transformer Units, Circuit Breakers and Electric Panels.

■EMT Conduits & Junction Boxes.

■New Light Fixtures.

■Pulling of high and low voltage cables.

■TV. Distribution System.

■PA & Data Work.

■Coordinating the Work with Edison & Local agencies.

■FA, grounding, and testing

■Site Flatwork (AC & Concrete works).

■ADA Compliances.

■Site infrastructure (wet & dry utilities).

■Testing & Punch List.

■Project handing over.

■“TIA” Time Impact Analysis.

G- SSC Construction:

Position: Project Manager: (04/ 2007 - 06/2009)

Project: Henry C. Garnett Water Treatment Plant Purification Location: Bakersfield, CA

Project budget = $95,000,000

Position Duties:

Supervising, managing & preparing the following:

Material, Resources Control & Tracking.

Rebar Detailing & On Screen Take off.

Massive earthwork, over-excavation, backfilling & compaction.

Heavy Civil, Asphalt & concrete work.

Managing subcontractors and vendors.

Coordinating submittals with various design consultants.

Generating RFI's & Change Orders.

Maintaining Cal OSHA Safety Compliance Standards.

Preparing Shop Drawings & Details.

Concrete & Steel Structures Erection & Supervision.

HV & LV. Electrical eqpt.

Dewatering & GWT Level Monitoring.

Site infrastructure (west & dry utilities).

SWPPP Monitoring & Implementations.

Testing and videotaping.

Preparing of Potential Claims and Change orders.

Delay Time impact analysis.

Evaluating Cost Overruns.

Subcontractors & vendors Claims analysis & evaluation.

Contractual Risk Identification and Mitigation.

Reviewing baseline, weekly and monthly progress construction schedule, evaluating delays, and preparing schedule review reports.

Monitor & Improve labor productivity rates.

“TIA” Time Impact Analysis.

H- Minco Construction Inc dba Minako Corp.

Position: Projects Engineer/ Estimator: (10/ 2004 - 04/2007)

1- Dec.2006 - April 2008.

Project: Cerritos Infrastructure & Central Plant Bldg. Location: City of Norwalk, CA.

Budget = $26,000,000.

2- Feb. 2006 - Nov. 2006.

Project: Costa Mesa community college new classrooms addition. Location: City of Costa Mesa, CA.

Budget = $6,700,000.

3- May. 2005 - Feb. 2006.

Project: Santa Monica College Parking Lots Improvements Location: Santa Monica, CA. Project Budget = $5,500,000.

4- Oct. 2004 - May. 2005.

Project: Valley High School Improvements.

Location: Santa Ana, CA.

Budget = $4,400,000

Estimator Position Duties:

-Bid Documentations and administration DBE, SBE and Minority compliances.

-Obtaining bid bonds.

-Preparing of a complete Take off and Cost estimates based on project plans, specs. and addendums if applicable.

-Preparing of bid tabulation spreadsheets.

-Negotiate prices with Vendors and Subcontractors.

-Coordinating submittals with the architect and engineering consultants after receiving the NTP.

-Generating as needed Pre-bid Request for Clarifications.

-Preparing bid Pre-qualification packages.

-Preparation of Procurements Plan upon receiving of the NTP.

-Complete understanding of recent project labors ‘agreements "PLA", “Davis Bacon” and/ or “PW” rates and classifications.

I- John Labib & Assoc.

Position: Design Engineer (March 2003 - Oct. 2004)

1- Design Engineer Using Etabts, Sap2000.

2- Drafting Using Cad's Programs.

J- Arab Contractors Co.:

Position: Project Engineer (May 2001 - March 2003)

1- Complex of King Fahd schools.

2- Complex of head offices of Cairo Bank.

3- Relocation of Military Factories.

4- International Medical Center.

K- Computer Programs & Certificates:

-Cad's (Autodesk certified 2007).

-SAP 2000.

-Etabs.

-MS OFFICE.

-Primavera (P3, P5, P6).

-Sure-Trak.

-Prolog.

-MS Project.

-Timberline (Estimating Software)

- CESSWI

-Plan-swift (Estimating Software)

-CPR.

-Procore.

-Gordian.

•Relocation: May be considered.

•References: Available upon request.



Contact this candidate