Construction of Spanish House Projects in DHA Phase – IV comprises of multi story buildings,
with the total estimated Cost of $8.9 Million . The salient features of this grand residential initiative include the offerings of a community lifestyle, modern infrastructure and architecture, high-quality life amenities and compliance in all project design and development elements. MUHAMMAD BURHAN UL HAQ Cell # : +923**-*******
PLANNING ENGINEER (CIVIL) E-Mail: **************@*****.*** EXECUTIVE SUMMARY:
About Two years of Experience in Public, High-Rise & Residential Buildings, Civil Infrastructure, Road Construction & Utilities Projects. Flexible, team player, Analytical & Strategic approach, Leadership qualities, High degree of integrity and demonstrated work ethics, able to complete the task within time & budget.
KEY SKILLS / AREAS OF EXPERTIES:
COST & RESOURCE
MANAGEMENT
COST CONTROL &
PRODUCTIVITY
CONTRACTOR SCHEDULE
ANALYSIS
EARNED VALUE
MANAGEMENT
PROJECT RECOVERY &
FORECASTING
CHANGE CONTROL & EOT
EDUCATION:
BSc Civil Engineering-2019
University of Engineering & Technology, Lahore
PROJECTS:
Public, High-rise & Residential Buildings, Civil Infrastructure & Utilities. COMPUTER APPLICATIONS
Primavera ® P6 17.1v
Microsoft office (2013 & 2016)
AutoCAD 2015
EMPLOYMENT HISTORY
Design Line Constructions, Lahore Planning Engineer House Construction, DHA Phase-IV, Lahore
(August,2020 – )
Habib Construction Services, Lahore Trainee Engineer Penta Square, DHA Phase-V, Lahore
(Jan,2020 –March,2020 )
DHA Penta square phase – V is an essence of business & trade admiration. This self-sustained building features the luxurious and comforting apartments with all modern facilities. Extravagant shopping mall that will be the high rank shopping destination. It will be a multi-story tower involving apartments, business units, and offices with a total cost of $51.6 million. Sarwar & Co Pvt-ltd, Lahore Trainee Engineer
Metro Orange Line Train Package-IV, Lahore
(June,2017-Aug,2017)
The Orange line is the first of the three proposed rail lines proposed for the Lahore Metro. The line will span 27.1 km (16.8 mi) with 25.4 km (15.8 mi) elevated and 1.72 km (1.1 mi) underground. The line will be served by 26 stations and is expected to handle 250,000 passengers daily with a total cost of project $1.6 billion.
Maintaining:
Establish and maintain multiple level schedules, Resource & Cost loaded Schedules and ensure project control mechanisms are in place to monitor performance by application of primavera P6,18.8 software.
Managing Planning Package (Integrated Planning Network, WBS, KPIs, Equipment & Manpower, S- Curve, Reporting, Methodology for Project Controls)
Creation of project master schedule based on BOQ, planning and progressive elaboration, as well as, incorporating Design, drawings approval and procurement process.
Preparation of project total man-hours, craft-wise manpower histogram, and cash flow requirement reflecting project planned earnings and actual performance.
Responsible for effective execution of Project, Prepares the Project Controls plan for assigned projects and Plans staffing needs for assigned projects.
Monitor site progress with reference to related targets by regular updates of project program, highlight and analyze the areas of delays.
Produce S Curve for resource units, labor units and remaining budgeted cost to specify the trend & forecast.
Controlling:
Timely updating & forecasting report related to delay and conveyed to the concerned project team.
Monitoring progress throughout the construction process, comparing actual status with the project schedule baseline and recommend preventive or corrective actions to the senior management.
Check & verify purchase orders from contractors.
Conduct material reconciliation & control wastages.
Carry out document controlling.
Reporting:
Provide weekly, fortnightly & monthly look-ahead schedule to the site constructionmanagers
Attend meetings associated with construction progress, and issues related to project variation orders, material procurement/logistic, manpower productivity and design/drawing issues. PERSONAL PROFILE