Jerry B. Cruz
E: *********@*****.***
T: +63 2-822******
Education: Bachelor of Science in Customs Administration
**** – 1984 (undergraduate)
Philippine Maritime Institute
Career History:
Dec. 14, 2019 - Jan.26,2021 E-Formula, DMCB and SVR Tel. Philippines
TELECOM RIGGER
Key Accountabilities and Responsibilities
Worked in data center by installing servers and switch in their corresponding rack
Installing and connecting of fiber optics, LAN cables, power plugs and transceivers
Cable grooming and re-routing
Worked on antenna transfer project (ATP-Ericsson)
Mounting or installing of proposed AAU, AMB, RRU’s/ERS and other accessories and equipment’s
Checked the proper orientation of installed antennas specially the proposed azimuth and tilting
Supervising on basic rigging on mounting of antennas and other technologies including pre laying and termination of CPRI’s and power cables
Installing of cabinet or rectifier in the proposed base pad
Assisting the Team Leader in power tapping and termination
Receiving of deliveries (MOS)
Antenna dismantling, integration, power tapping, and rectification
Working at height on a range of telecommunications structures including poles, towers and masts to install antennas
Place insulation over conductors or seal splices with moisture-proof covering (waterproofing)
Permitting job and performed other related job as assigned
Aug. 25, 2019 – Oct. 07, 2019 PLB FORTUNA NORD STREAM 2
RUSSIA - GERMANY
RIGGING FOREMAN
Key Accountabilities and Responsibilities
Hauling of cement coated pipes and setting up to roller for welding
Preparation of mooring anchor and pennants for deployment
Installing and dismantling of working platform
Installing of pipe straightener
Banking/signaling to crane
Supervises and coordinates activities of workers engaged in all rigging and lifting activities to ensure compliance with safety procedures and method statements
Familiar with heavy lift plans and procedures
Assists and determines the proper method of lifting equipment for each assigned project
Ability to optimize resources (manpower, equipment, and materials) to ensure efficient and timely completion of project
Ensure good and proper workmanship are applied in all stages of work.
Feb. 01, 2019 – March 20, 2019 COES Shanghai Salvage Company
QATAR Petroleum WHP-3/NFA-FIELD
QATAR
RIGGING FOREMAN
Key Accountabilities and Responsibilities
Loading/unloading of materials and equipment from the quayside to to the vessel and or from the vessel to the quayside
Preparation of anchors, chains and wire slings use for mooring points
Vessel to vessel transfer of materials and equipment and off-signers/on signers personnel
Banking or signaling on crane
Slinging of temporary platform for lifting
Assisting on lifting of the topside platform (2,900) Tons for installation
Installation of Flare Boom
Conducting toolbox talk
Oct. 12, 2017- Aug. 20, 2018 PHILSPEC CONSTRUCTION
Quezon Power Plant
Mauban, Quezon
RIGGING SUPERVISOR
Key Accountabilities and Responsibilities
Hauling of ESP materials and accessories
Erection of casing column and structure
Pre-assembly of hopper, collecting electrodes, discharge electrodes, inlet and outlet funnel, ducting from ESP (electro-static precipitator) to FGD (fuel gas duct), pre-assembly of ducting for IDF (induce duct fan)
Erection of roof beams, ducting for IDF, and Smoke stack
Installed slide bearing, casing structure and casing panel
Erection of collecting and discharge electrodes
May 01, 2017- June 15, 2017 HEEREMA MARINE CONTRACTORS
Gulf of Mexico, USA
RIGGER TEAM LEADER
Key Accountabilities and Responsibilities
Transporting and installation Stampede Platform TLP (Tendon Leg Platform)
Banking the crane during lifting operations
Preparations of corresponding rigging for the recovery of corrosion cover
Taking off all the towing lines
Setting of pulling lines during riser’s installations
Keep an eye on the support crane during TSB (Tendon Support Buoy) recovery
Assisting on Torque Winches during the pulling of Tendons
Securing the rigging of diver’s camera
Aug. 29, 2016-Dec. 25, 2016 SAIPEM INDONESIA
Karimun, Indonesia
RIGGER (pipe erector)
Key Accountabilities and Responsibilities
Installation/erection of Gas Turbine Generator
Proper sequence of erection of different columns, large platforms, channel, handrails, diagonal pipe bracings and gratings
Continuous erection of different types of valves and their support
Installation of clamps, pipe support and pipe shoe
Installing of large spool piece
Banking or signaling the crane
Aligning double ending pipe for welding
Participate in tool box talks and ensure all instructions from the supervisor are fully understood and responded promptly
Punch listing
May 2015 - Oct 2015 EMAS, AMC
USA/Germany
RIGGER
Key Accountabilities and Responsibilities
Operating carousel, deck winches and falfinger (crane)
Cable laying
Plan the route of the load and inform relevant personnel and surroundings of the move to minimize disruption to normal operations
Attend all relevant briefings prior to the job commencing and ensure all instructions are fully understood
During operations communicate accurate information to colleagues and Deck Foreman
Flow line recovery
Deployment of structure protection on the seabed
Deployment of concrete mattresses
Pipe and umbilical laying
Installing track way for the umbilical and A/C cables
Banking the crane
Assisting lay technicians and ship welder
Preparing all the accessories and equipment needed during laying and recovery operations
Maintaining or do some function test on the equipment on board before the operations
March 2009 – January 2015 SUBSEA 7 / ANGLO EASTERN
Makati City, Philippines/UK
AB/RIGGER
Key Accountabilities and Responsibilities
Assisting VLS technicians
Operating winches during spooling and pipe laying operations
Working together with the HLO during crew change as a helideck team member
Assisting on my foreman during spooling or reel walking for choking the pipe
Material handling and lifting
Preparing all the rigging needed for lifting
Installing pipe buoyancy and accessories
Loading/unloading, deploying of concrete mattresses, steel structure, PLEM, PLET, jumper, risers and flow lines.
Banking of the crane
May 2008 – December 2008 PETROMAR COMPANY ( GPS )
CHEVRON Project Cabinda, Angola
RIGGER FOREMAN
Key Accountabilities and Responsibilities
Preparing all the materials for hauling, erecting and laying
Participate in tool box talks and ensure all instructions from the Supervisor are fully understood and responded to promptly
Request suitable assistance from colleagues in a polite and courteous way without causing undue disruptions to normal work activities
Concrete pouring
Aligning double ending pipe for welding
Setting up pile driving equipment
July 12, 2007 – August 12, 2007 KIKEH FIELD DEVELOPMENT PROJECT
KIKEH FIELD, MALAYSIA
AB/RIGGER
Key Accountabilities and Responsibilities
Double check the rigging orientation of the rigid jumper before lifting by the rig crane
Loading all the necessary torque tools to the ROV basket before deploying it to the sub sea
Loading / offloading of all the materials needed before go on sailing
Making sure all the sea fastening is properly done
March 12, 2007 – April 21, 2007 HORIZON OFFSHORE COMPANY
STA. MARTA, COLUMBIA
PIPELINE RIGGER
Key Accountabilities and Responsibilities
Detecting holiday in the pipe
Wrapping of shrink sleeves to the welded joint of the pipe
Laying pipe in the roller
Assisting in the installation of the riser pipe
July 29, 2006 – Sept. 13, 2006 AMEC / V-PEOPLE ENERGY
BUZZARD PLATFORM
NORTH SEA, SCOTLAND
RIGGER FOREMAN
Key Accountabilities and Responsibilities
Participating in tool box safety meeting and securing all the work permit
Installing clamps and pipe support
Lowering vertical pipe column of the sea lift water pump
Hauling and rigging of valves on the lower level of production platform
Assisting pipe fitter’s on the installing spool piece
Piping erection
Material handling and lifting
Removing spool piece of the medium water pump for the inspection of each strainers
Writing report and performed other related job as assigned
Feb. 13, 2006 – Apr. 12, 2006 HEEREMA MARINE CONTRACTOR
Gulf of Mexico, USA
RIGGER TEAM LEADER
Key Accountabilities and Responsibilities
Setting up new rigging for the spool piece before transferring to the winch system number 9
Installing a set of sling to use to the winch system for the recovery of the pulling head connected to the riser
Assisting the Valkyrie personnel for the positioning of SCR vacuum system equipment including pumps with associated rigging and hose hook – up
Assisting in transferring and pull in of 10” steel catenary’s riser and associated with rigging and maintenance
Assisting the versabar winch operator for the 6” chain transfer and keel haul procedure /dummy flex joint transfer and riser abandonment procedure
Operating winch in the ROV skid for the lowering and positioning of the cursor frame in the pontoon
Assisting for the hooking up of the chain jack, chain locker and OCEANEERING dive trolley’s
Sept. 17, 2004 – Dec. 11, 2004 TORCH OFFSHORE INC
MARATHON OIL COMPANY
MALABO, EQUATORIAL GUINEA
RIGGER FOREMAN
Key Accountabilities and Responsibilities
Material handling and lifting
Pipe laying of PIP (pipe in pipe)
Put umbilical line to the pipe for submerging underwater
Putting insulation on both end of the pipe by painting the welded joint of primer
Installing fiber glass in the inside the PIP (pipe in pipe)
Installing half shell of PUF (polyurethane foam) in the inner pipe where the joint has been weld
Wrapping ROCS sleeve (shrink sleeve) around the area to be coated
Detecting holiday in pipe by using JEEP HOLIDAY DETECTOR
Assisting technician for terminating umbilical loading valves line through umbilical termination assembly
Assisting for submerging the condensate, butane and propane PLEM
Maintain good level of housekeeping on the loading or offloading area
Assisting divers for all the rigging related works
Rigging and assisting mechanics mounting heavy structures and oil rig/shipyard machineries
Cleaning, painting and greasing deck winches and crane
July 21, 1999 – Mar, 28, 2000 MDK International
MALABO, EQUATORIAL GUINEA
STEEL ERECTOR
Key Accountabilities and Responsibilities
Material expediting
Erecting different types of columns in each foundation
Assembling trusses or a supporting framework for a roof to support a structure
Erecting side beam, center girder, vertical bracing, side girth, horizontal bracing and installing sag rod
Assembling and installing fin fan cooler
Installing gratings in every platforms
Bolt tightening
Piping erection
Installing hand rails and ladders
Performed other related job as assigned, having a good leadership, writing report and a good knowledge of safety
June 05, 1991 – May 02, 1997 Gulf Marine Maintenance and Offshore
DUBAI, U.A.E.
Mechanical, Structural and Offshore Rigger
Key Accountabilities and Responsibilities
Material Handling and lifting
Rigging and assisting mechanics mounting heavy structures and oil rig/shipyard machineries
Removing, replacing large pieces or part of a ship
Capable of removing, replacing, re-installing and repositioning heat exchanger, turbo charger, panel boards and different type of valves and pumps
Assisting or tendering divers during salvage and clearing operation
Cleaning, painting and greasing deck winches and cranes
Capable of erecting scaffoldings and do some painting job
Inspecting of rigging tackles and equipment
Maintaining good level of housekeeping on loading or offloading area especially in the work site
Continuous rigging while on board the ship, platforms, dry docks, and ship repair facilities
Installing or erecting beams for horizontal and vertical construction
Erecting pressure vessel
Installing trusses or supporting framework or to support a structural for heavy iron fitting
Rigging an upright pole or other structure for carrying blower, turbines, panel boards etc.
Jan. 21, 1988 – Aug. 02, 1990 AL-SOULAH TRADING LTD
STATE OF KUWAIT
OFFSHORE RIGGER
Key Accountabilities and Responsibilities
Material handling and lifting
Rigging and assisting mechanics mounting heavy structures and oil rig/shipyard machineries
Maintain good level of housekeeping on the loading or offloading area
Knows perfectly the sign of communication with crane operator
Estimate the weight of the objects
Choose appropriate sling and other rigging equipment
Cleaning, painting and greasing deck winches and cranes
References
Available upon request.