Profile:

Focused and Resourceful Electrical Engineer with the knowledge of Site Execution, Operations, Project Management, Team leadership, Safety and Quality assurance abilities.

TOTAL EXPERIENCE:

More than 6 years of total experience in Installation, Inspection and Design fields for EPC Sector in Building, Substation, Power Plants and Petrochemical.

Professional Experience:

Experience in Saudi Arabia

Electrical engineer

Contractor: SEPCO

April 2019 – Jan 2020

Project Name: JIGCC Package-4

Client: Saudi Aramco.

Responsible for site execution, testing coordination of all electrical work in 15 dia-380KV substation.

Planning & monitoring of activities within time, cost & quality constraints and specifications.

Smooth execution of work at site according to approved standards & drawings.

Work permit & Implementation of HSE & conducting tool box talk prior to start work.

Laying and testing of HV,MV,LV Power cables and Control Cables for panels and equipments.

Planning and Coordination with client for all testing activities and arranging witness.

Actively coordinates with all other internal/external team members on moderately complex projects

Provide technical support for R&D external interface, e.g. production, quality, sales, supplier, HR etc

Electrical & Instrumentation QC Inspector,

Contractor: Nasser Al Hajri Corporation.

April 2018 – Feb 2019.

Project Name: Saudi Aramco Onshore Maintain Potential Project NA-2 (SAOMPP), Qatif.

Client: Saudi Aramco.

Implementation of Quality Plan of the project which includes Inspection, Testing and Proper Documentation and ensure that all works complied with client issued (IFC) drawings, applicable Aramco, International standards and Project specification.

Responsible to implement the Saudi Aramco’s Schedule-Q” through project quality plan.

To ensure that the Quality of material being delivered at site as per the requirements.

Inspect and witness the construction works as per approved Inspection Test Plan (SATIP & SAIC).

Attending Internal RFI’s prior to conduct final inspection with clients.

Responsible for material receiving inspection of all electrical equipment and accessories.

Perform surveillance inspection to minimize or avoid discrepancy and non-conformance rectification.

Raising Non-conformance report if any major violation or non-compliance noticed. Supports construction team to conduct, Root cause analysis, corrective action and preventive action plan.

Reviewing marked up as build drawings of completed jobs before hand over to the company.

Inspection of conduits, Cable trays & raceways as per drawings and standards.

Co-ordination with third parties & conduct testing and pre-commissioning activities of electrical Equipments.

Pre-commissioning of lighting, power & LCP Panels & continuity for cables.

Inspection of MV/LV Cable trenches, laying & witnessing the cable testing.

Inspection of Digital, Analog and PDHMS instrumentation cable laying, termination and Testing.

Familiar with the international Industry Codes and Standards related to Electrical Systems such as; NEMA, NFPA 70/NEC & SAES- P Series and SAEP.

Site Electrical Engineer

Nov 2016 – Feb 2018,

Grupo Maessa Saudi Arabia Ltd,

Al-Khobar, KSA.

Project Name: Power Supply to South Dhahran Home Ownership, 115/13.8Kv Substation.

Client: National Grid/SEC.

Duties & Responsibilities:

Ensure the work shall done as per project scope of work, technical specifications, SEC five star safety and Quality standards to meet the timely completion of the projects.

Managing, supervising and lead the team of Technicians, Contractors and materials on site.

Coordination with Consultant & Project Manager regarding Works and inspection.

Maintaining daily and weekly work records and reported to the higher officials.

Ensured that the correct equipment size and specifications were installed as approved in the drawing.

Taking action and follow the instruction of Consultant and project Manager.

Coordination of various departments, to discuss/resolve the problems faced during the design/execution of work.

Assisting with Vendors for 115KV GIS, Power Transformers (50/67MVA), 13.8KV Metal Clad Switchgears, Station Service Transformers Erections (500KVA) & Capacitor Banks.

Reading Electrical design specifications, Vendors drawings & Method of Statements.

Installation of LCC Panels, SAS Devices, Control & Protection Panels, Battery Monitoring Panels, Battery Banks, Communication Panels, Distribution Panels like ACDB, DCDB, LP and Sub Panels.

Installation of Cable trays, Cable Ladders for Laying of LV Power, Control and Fiber Optic Cables.

Handling MV Power Cables & LV Power and Control Cables Laying, Glanding and Termination.

Assisting with QC Inspector for Client’s Inspection (RFI).

Supporting Testing teams for the Commissioning Activities.

On-site Preparation for Lighting Fixture’s Routings like Conduits, Trunking.

Inspecting Duct Banks, Cable Trench and Direct Buried Cables as per the IFC & Conducting Mandrill test.

Installation of Flat Copper Earthing, Grounding Grids, Grounding Rods and Pits.

Clearing Punch lists as per the Client’s Requirements.

Providing Technical guidance to the team for installation, maintenance, and repair of electrical systems.

Coordination of various departments, to discuss/resolve the problems faced during the design/execution of work.

Grounding rod installation, Cad welding for joints, structures & platforms grounding and laying of bare copper cables for substation grid.

Site Electrical Engineer

May 2016 – Oct 2016,

Saudi Oger, Dhahran.

Project Name: KACWC, Dhahran.

Client: Saudi Aramco

Duties & Responsibilities:

Study and Review of all drawings, installation procedures, Standards, Specifications and project requirements prior to implementation of work.

Installation and termination of Distribution Transformers, LV Switchgears and low voltage power distribution boards.

Control Panel Installation (VFD, Star-Delta) and wiring for various motors applications.

Installation of PVC, EMT, RGS etc., Conduits for wiring raceways of power receptacles, lighting switches, grounding and lighting fixtures.

Installation of grounding system for all MV and LV system and equipment earthing.

Installation of Battery system and battery racks.

On-site Preparation for Lighting Fixture’s Routings like Conduits, Trunking.

Installation of grounding conductor to ensure both System & Equipment grounding shall done as per IFC, SEC Stds & NEC 250.

Pre-commissioning and loop checking for lighting and power circuits with QC personnel.

Continuity and Megger test for cables.

Electrical Engineer

June 2014 – April 2016,

Prabhat Powertech Pvt Ltd, India.

Duties & Responsibilities:

To assist the project head in the preparation of the project execution schedules and allocating the resources for the projects to ensure successful completion of the projects meeting time, quality and cost parameters.

To chair and minute kick-off meetings & progress review meetings with vendor, consultant and internal project members.

Providing guidance to prepare lighting layouts, power layouts, load schedule, Single line diagrams and the related Engineering calculations like Panel board circuits and main distribution board circuit breaker size selections etc.

Supervised Electrical wiring installation in commercial and industrial building including Power, security and communication.

Planning and monitoring the site activities as per the schedule and resolving, Planning and monitoring the site activities as per the schedule and resolving various site related issues by coordinating among the various sub-contractors.

Advice the contractor’s field staff of poor quality work and deficiencies detected during inspections and assists / advice on remedial works required.

Monitor and ensure that a comprehensive record of documentation and certification of work is maintained and assist in the satisfactory handover of the completed project to the Client.

Responsible for constant surveillance of the work force, quality of work, safety, schedule and productivity of personal, sub-contractor and associated support.

Maintained all safety and quality control project standards.

Major Activities:

HV, MV underground cable laying, Splicing & Termination also testing of cables such as continuity, Megger.

Preparation of Single line diagram layouts, specification for Electrical Equipments such as Transformers, Energy meter, Fuses, Circuit Breakers (MCB, MCCB), cables, Distribution Boards, etc.

Planning Conduit routing, LV cable wiring and cable Trunking as well installation of cable trays.

Installation & Commissioning of Oil type up to 3000KVA distribution transformers.

Erection of MCC panels and industrial motors.

Power and lighting system installation and Pre-commissioning

Installation & Commissioning of LV & MV Switchgears, Panels & Motors.

Educational Background:

B.E – Electrical & Electronics Engineering in Anna University, Chennai.

Training Qualification:

Site Training Program for Operation & Maintenance of 145KV GIS by Hyundai Electrics.

Have done AUTOCAD v2013 Designing Course.

Undergone an In-Plant Training to ‘Gas Turbine Power Plant’ Ramanathapuram, India (VGTPS).

Personal Details:

Nationality : Indian

Gender : Male

Marital status : Single

Religion : Islam

Languages known : Tamil, English & Hindi

Passport No & Place : M5587618, Madurai, Tamilnadu

Declaration:

I hereby declare that above mentioned details are true.

(JamalAnwar)



Contact this candidate