RESUME FOR THE POSITION OF GENERAL MANAGER – MEP
MR.SISIRA KUMAR RATH
Phone: +91-986******* / 993-***-****
E-mail: adjrp3@r.postjobfree.com,
adjrp3@r.postjobfree.com,
adjrp3@r.postjobfree.com
Skype ID: sisira.rath1
OBJECTIVE:
To pursue a successful and rewarding career in an esteemed organization which would provide me an opportunity to work in an innovative and challenging environment by utilizing and contributing towards the achievement of organizational goals along with my career growth.
To excel at leading a team and take responsibility to ensure timely completion of projects on approved budget without compromising on quality and safety.
To take on new challenges including managing multiple projects simultaneously and leading a bigger team.
I am confident that with my experience and expertise, I would be an asset to the Organization.
PROFESSIONAL SUMMARY:
A passionate, dedicated and hardworking Electrical Engineer having over 26 years of experience with in the construction industry in India and 14 years in Middle East;15 years of which as Project Manager.
Highly innovative and thorough in Electrical& MEP Projects; capable of applying practical knowledge and coming out with effective solutions to problems even in the most difficult situations.
Excellent communication skills combined with situation based analytical abilities to handle various circumstances.
Excels at liaising and negotiating with stake holders and local authorities to satisfy
all involved parties and expedite procedures.
Dynamic and diligent, able to mobilize team members and produce high quality results while ensuing compliance to all relevant health and safety regulations.
Proven track record in managing project costs and resource allocation for various projects viz. Oil &Gas, High Rise Buildings, Hotels, Hospitals, Electrical substations and transmission lines etc.
Friendly and approachable with excellent interpersonal and management skills.
Proven track record on completing multiple Projects related to energy efficiency, energy performance contracts using BIM Green Building approach.
Strong history of leading high-performance teams to meet or exceed objectives. Dedicated and hardworking with internal drive to deliver excellence. Tactical team builder with strong background in training and team development
Recognized for assessing operational needs and developing solutions to save costs, improve revenues, and drive Client satisfaction. Resourceful and well-organized with excellent leadership and team building record.
Motivated with solid experience in managing all levels of large scale projects, including budgeting and administration.
Establishing action plans and translating strategic priorities into reality.
Effective involvement and persuasion strategies to gain acceptance of ideas and commitment to
Actions.
AWARDS & HONORS:
In the year 2006,received the most prestigious & globally recognized “VikasRatna Shiromani Award” and “India Achievers Gold Medal” from the Government of India for excellent achievement in profession and in the field of Electrical Project Design, Execution, Implementation, Testing &commissioning and successfully handing over of Electrical &Electromechanical Projects.
KEY FACTORS OF STRENGTH:
SKILLS
CORE COMPETENCIES
VALUE PROPOSITION
Electrical Engineer
Execution, Operation and commissioning of 132/33 KV EHV Substations
Project Execution for 33/11KV Substations,
11KV/415V Project Execution
400 KV Overhead and underground cabling etc.
MEP: Electrical Systems, HVAC, Fire Fighting, Plumbing, Water Treatment, WTP & STP,CC TV, SMATV,SCADA,
IBMS
Access Control and DG Sets etc.
Project Manager
Lighting
Cabling
Structure Cabling
Design/Shop/As-built drawings
Baseline Schedule Creation
ITP
Method Statement
RFI
Material Submittals
Variation Orders
O&M Manuals and Project Close out documents
Inspection
Electrical Distribution
Industrial Machinery
Refinery
Oil and Gas
High Rise Buildings
High& Low Voltage Systems
Estimation
Preventive maintenance
Testing and commissioning
AMC Contracts.
Setting high goals for self and others.
Consistently trying to meet goals and exceed them.
Electrical & MEP Project Management
Site Supervision and coordination
Engineering & technical support
Design review and analysis control
Strategic planning and scheduling
Estimation and techno commercial operation
Resource planning and management
Contract terms and conditions
Construction management
Budget analysis and cost control
Vendor Management
Material management
MEP installations, testing & commissioning
Safety procedures
Quality control
Risk management
Team management, Effective communication and Leadership
Creative thinking and decision making
Motivation, conflict resolution and diplomacy
Permit processing
Building Codes and regulations
Site temporary facilities, gate pass processing and mobilization
EDUCATIONAL DETAILS:
QUALIFICATION
SUBJECTS
YEAR
A.M.I.E. (Electrical)
Degree in
Electrical Engineering from
The Institution of Engineers (India)
Ele. Measurement, Ele .Machines
Network Analysis, Ele.Design,
Power System, Control System,
Ele. Engg. Materials,
Electromagnetic Theory.
1991
Elected as Member of the
Institution of Engineers
M129816-4
2005
Chartered Engineer (India)
M129816-4
2005
Diploma in Computer Application
(DCA) from CST Computer
Education, Chennai
Duration – 12months.
Fundamentals, PLT and MS-DOS,
Windows-95, & MS-Office 2000,
Internet, Basics & HTML, UNIX &
C, Visual FoxPro 6, System
Analysis Visual Basic 6 Design &
Project Work Exposure to
Windows NT-4 and Oracle 8 with
D6.
2001
APTECH Computer Education,
Chembur, Mumbai.
Vidya 2000, Latest version of
M.S.Office course.
2008
APTECH Computer Education,
Chembur, Mumbai
Advanced Excel.
2008
KGL Systels Ltd.,Mumbai
Primavera P 6.0
2007
CADD Centre, Mumbai
Course on Revit MEP
2015
COURSES RELATED TO SAFETY MANAGEMENT PROGRAM:
Sr.No.
Course Ref
Date
Name of the Institution
Gradation
01
HSE Induction
Program - SF ( 105 )
15/12/2013
Global Institute, Oman
Excellent
02
Basic First Aid SF
(170)
16/12/2013
Global Institute, Oman
Excellent
03
Managing Safety SF
(160)
17/12/2013
Global Institute, Oman
Excellent
04
Electrical Safety SF
(101)
06,07/01/2014
Global Institute, Oman
Excellent
05
Managing Safely Certificate
November 2018
IOSH(U.K.)
Successfully
CAREER HISTORY:
Name of the Company
Sodexo -Teyseer Services L.L.C,Qatar
Duration
09/09/2018 to 20/10/2020
Position Held
Project Manager for M/S – Shell GTL Ltd., Qatar
Responsibility
In charge of 105 Nos. of Medium and Small Scale Oil & Gas Projects with Shell GTL, Qatar.
Roles and responsibilities included planning, execution, budgets, operations & documentation of all aspects of the projects with Shell GTL Ltd.
Review of contract documents ( BOQ, Drawings & Specifications ) for technical completeness and code adherence, preparation of the bid packages, construction scheduling and site supervision.
Responsible for quality work at Project sites for execution of Civil & MEP Works in strict adherence to highest quality performance and safety standards.
Overall responsibility of Projects based on strategic priorities and managed budget, quality, schedule and HSE throughout the project lifecycles.
Developed budget in consideration with cost optimization and reduction goals.
I was tracking, monitoring and controlling expenses budget and budgetary guidelines and ensured all projects execution with in defined budget and timelines.
I was conducting regular project status meetings with project team and addressing the issues, concerns and questions of Management, Clients and Team members.
I have developed and implemented the project management procedures & methodologies to achieve business goals.
I always conduct performance review and provide feedback to my staff.
By doing so I always demonstrate my resourcefulness, creativity, innovation,team work, adaptability and problem solving skills to achieve my Projects successful.
Name of the Company
Radius Engineering Co.W.L.L, Doha -Qatar
Duration
04/ 01 /2016 to 19/07/2018
Position Held
MEP Project Manager
Responsibility
In-charge of MEP Installations for the Construction of Kahrama New Tower Project in Lusail City ( Storey-5B+GF+M+19+T, Area – 121,125 Sqm.),Contract Value -QAR.160 Millions.
Review of Contract Specification and study of technical and commercial terms and condition of contract necessary for Project Execution.
Responsible for planning and scheduling of all major activities of the Project to achieve timely completion.
Preparation and updating of periodical progress reports.
Cost Controlling, monitoring and savings.
Fully responsible for all contractual issues related to day-to-day running activities of Site in order to ensure successful achievement of project mission statement and goals.
Responsibility of all staff, labor and material management on-site to ensure a successful completion of the Project within the budget and time frame.
Follow up with various departments within the company for all Project related matters and smooth operation of the Project.
Determining all technical and general requirements ensuring timely submission &approval of Material submittals, Samples, Shop Drawings, Design Details, Work Procedure, Method Statements, ITP, Schedules and Programs etc.
Overall responsibility for overseeing and effective execution of all project related activities under the instructions of Senior Management.
Timely arrangement for obtaining of all clearances, approvals, permissions, etc. as required from time to time from any of the statutory authorities during the execution of the Project.
Planning & scheduling for all project activities in line with Master Program in co-ordination with the Planning department.
Receiving all project related instructions from the Client, Engineer, Main Contractor, etc. and transmit, communicate and arrange effective action in co-ordination with the Management.
MEP Services inclusive of HT/LT Substations, HVAC, Fire Fighting, Lighting & Power, Structured Cabling, FA,PA & BM,CCTC,IBMS, SCADA,PHE, FPS,UPS and DG Sets etc.
Obtained approvals from Kahramma and QCDD approvals during project execution.
Name of the Company
KCC Engineering & Contracting Company(KCCEC),Kuwait
Duration
01/07/2015 to 05/10/2015.
Position Held
Project Manager (Electrical)
Responsibility
Testing, Commissioning & Handing over of MEP Scope of Works for Commercial Building Project with Kuwait Oil Company-KOC as per International and GCC Standards for complete Power Distribution network to the Building, Street& Landscape Lighting Control Panels, Low Current Systems: Access Control System, Pump Rooms, Switch Boards, CCTV, Fire Alarm, Security, BMS and HVAC System.
Name of the Company
M/s – Hasan Juma Backer Trading &Contracting L.L.C, Oman
Duration
01/06/2010 to 30/06/2014
Position Held
Project Coordinator –MEP
Responsibility
Project Planning & Management
Design, Estimation, Engineering, Procurement and Execution of all HV/MV/LV Electrical Systems, HVAC& Electromechanical Projects.
Finalization of requirements as per specifications in consultation with Collaborators/Promoters and project scheduling including material & manpower planning.
Responsible for monitoring of entire MEP Services, Interior Finishing and other allied works on Site by ensuring cost optimization, quality work for timely completion of the Projects.
Contract Administration & Management
Coordinating with Consultants and Clients and responsible for checking & finalizing Project documents such as BOQ, Specification, Drawings, Designs and appointing Sub-Contractors in order to ensure timely completion of Work.
Construction Site-Management/Resource Planning
Administered all construction activities by providing technical inputs and methodologies for Construction in coordination with Site-Management.
Preparation and review of Method statements, Quality Control Plans and documents as per Contract Documents.
Organized Engineering Procurement, Site-Execution and Commissioning activities and controlling material procurement schedule related to Project’s Progress & Inventory Control.
Additional Responsibilities:
Contributed to Project’s procurement, estimation & costing for all Electrical and Electro-mechanical Works related to HVAC Projects for Building automation & Services, Oil & Gas, Water-supply and Sewage Treatment Plant Infrastructure System.
MEP Projects successfully completed in Oman
oExtension Building to Ministry of Foreign Affairs
o Construction of 17 Buildings at different locations for Rloyal Guard of Oman,
o Al Alam Heights Building
o190 Villas in Yetti Village
o Hasan Juma Headquarters Building at Wadi-Kabir
oExport Credit Guarantee Agency Building for Ministry of Finance at Airport Heights,
oConstruction of Haematology and BMT Centre Building at Sultan Qaboos University Hospital
o Annex Building for Ministry of Supreme Council for Planning,
oPolice Station Complex at Sohar Port and 33/11 KV & 11/0.415 KV Substations at various locations.
oEstimation for High Rise Residential and Commercial Buildings up to 60 Stories for Qatar projects.
Name of the Company
M/s - Verger et Delporte UAE Ltd.
Duration
12/05/2008 to till 20/01/2010
Position Held
Deputy Project Manager - MEP, for Ritz Carlton Hotel Project - D.I.F.C, Dubai
Responsibility
DesignBuild Project, Streamlined, Managed DIFC requirements, strategies, expectations and took overall responsibility for Project’s conceptualization and management, execution, timely completion of activities as per scheduled program, contractual and financial aspects, budget control, overall planning for optimum production yield, control and monitoring sub-contractors and their team, implementation of QHSE procedures. Liaised and coordination with local authorities Standards, rules and regulations for DEWA, DCD & DM where required for completion and handing over of MEP Works.
Managed Client requirements, project team, finances, adopted professional approach in project management, Costing and control, Pre-planning of material requirements& formulated availability by identifying standard and the cost of materials used for construction Site. Developed project specific plans, outlined timelines, schedule of activities, resources and controlled as per project plans.
Projec Contract Value: 220 Million Dirhams
No. of Floors: LB+UB+GF+14 Storied Building including 11KV/0.415 KV Substation
Name of the Company
M/s - COMSIP AL A’ALI, Cegelec, Doha (Qatar)
Duration
31 / 05 / 07 to 20 /11/ 07
Position Held
Sr. Electrical Engineer
Responsibility
In charge of Estimation, Costing, Quantity take off, Project planning, Scheduling of Building Services projects up to 37 Storied High Rise Building as per tender drawings & specification.
Material submittals & approvals through weekly material approval status.
Review and study of Technical Submittals and Shop drawings received from Subcontractors.
Review of daily work report from the Sub contractors and to compare with the quantities with executed works on Site.
Handled the Staff, work force and the daily progress reports received from the sub-contractors and monitored whether it is matching with the requirement or not and
to be sure that available tools & equipment are enough to execute the works.
Follow up with the quality control and inspection for the works executed and materials received on Site and to make sure that it is complying with the approved technical submittal and contract specification.
Preparation of estimation, expenditure, forecasts and monitors the Site situation of resources as compared to planned activities and to recommend remedial action plan. Support project implementation and monitor progress as per programmed activities by reviewing, verifying and analyzing program, work plans, progress reports and to find whether the final reports and data ensuring that the results are achieved.
Duties include coordinating, scheduling of activities for MEP Works.
Name of the Company
M/s - AIRMECH L.L.C, BAHRAIN
Duration
14 / 04 / 06 to 08 / 04 /2007
Position Held
Senior Electrical Engineer
Responsibility
Execution of MEP Works in Commercial & Residential Buildings up to (G+L1+L2+30) Storied Residential Buildings. Execution of MEP scope of work in Crown Plaza Hotel project.
Various Systems handled are as follows.
HVAC,MV/LV Switchgears,CC TV System, Access Control System, BMS, Fire Alarm System, Fire Fighting System, Structured Cabling system, PA & BGM System, UPS, Lighting Control System, Lightning Protection System, Earthing System & Emergency Generator and Gate Barrier Systems.
Name of the Company
M/s - Jay Krishna Industries Ltd, Mumbai
Duration
05 / 01/ 2005 to 12/ 04 / 2006
Position Held
Sr. Manager- Projects
Responsibility
Design, planning, execution, successful completion and handing over of 24 Nos. of 33/11 KV Sub-stations in Madhya Pradesh State Electricity Board (India)
Recipient of VikasRatna Shiromani Award and Certificate of Excellency from the Government of India, New Delhi on 20th May 2006 for successful for timely completion of all Projects as per guidelines and contractual obligations.
.
Name of the Company
M/s - Rohini Industrial Electricals Pvt. Ltd, Mumbai.
Duration
30/ 07/ 2003 to 04/ 01/ 2005
Position Held
Senior Deputy Manager
Responsibility
Overall In charge of project design, execution, internal electrification, installation, testing and commissioning of 11/0.415 KV Sub-Station for Reserve Bank of India’s Main Office Building. In addition to that planning, execution, testing& commissioning of MEP Works for AxaBusiness Centre Building in Pune and 132/33 and 33/11 Substation in Maharashtra.
Projects handled:
Grand Hyatt, Santacruz(E) – 5 Star Hotel
Raheja Complex, Awagoda.
State Bank of India, BandraKurla Complex.
Tata Chemicals.
LUPIN – Goregaon
Raghuleela Shopping Complex-Borivali.
Name of the Company
M/s - Oman National Electric Company, Oman
Duration
03/07/2002 to 25/07/2003
Position Held
Shift Control Engineer, MEW Muscat (Oman)
Responsibility
Worked as Shift Control Engineer for Ministry of Electricity and Water Authorities
(MEW) Muscat. The Control Center controls entire Oman Grid Power network especially all major Power Stations such as Ghubrah, Manah, WadiJizzi, Rusail, Al Kamil & Barka having total 2500 MW Generation Capacity. The entire power generation is distributed through 400KV/220 KV/132KV/33KV Grid Stations and 33/11KV& 11/0.415 KV S/S.The Control Center receives Real Time Data, Power Generation from each Power.Plant and Power Flow through each tie line, System Frequency and Grid Voltage. Evaluates the data, determines the action sends instruction to each generating stations as to how much generation they should increase or decrease depending upon the system demand. The entire process is achieved through Automatic Generation Control(AGC) integrate with SCADA network.
Name of the Company
M/s - Oman National Electric Company, Oman
Duration
05-07-1999 to 30-06-2002
Position Held
Project Manager (Electromechanical Construction
Responsibility
In charge of Company’s AIS & GIS Substations, Grid Station Projects up to 400 KV with MRL In Electromechanical Construction Project division responsible for Tendering, Estimation, Material Management, Labor Management and Site Supervision of large Electrical & HVAC Installations for Office buildings, Star Hotels, Hospitals, Shopping Centers, High Rise Buildings Internal Electrification Projects and Industrial Electrifications etc. Review, evaluation, Preparation of technical documents, construction supervision of Project Sites and looking after entire MEP Works for all Projects. Site In charge and project manager for execution of MEP Project Sites including installation of 30 Meter High Mast Poles with1000 Watt HPS Lighting inside Madras Sea Port Trust for Construction Site and allied works, right from initial stage till handing over of the project in a professional and systematic manner as per Building codes, practices & specifications. Administered HVAC Installation Works, HV/MV/LV Panels, Fire Alarm, Video/Audio Intercom, MCCs, Transformers, HV cabling work in MEP Projects.
Name of the Company
M/s - Tamil Nadu Power Devices (P) Ltd, Chennai.
Duration
12-01-1992 to 30-06-1999
Position Held
Project Engineer (Electrical Construction)
Responsibility
TNPD Tamil Nadu Power Devices (P)Ltd, is a leading contractor for Electrical &Instrumentation works for major Port Trusts, Oil &Gas, Petrochemical, Fertilizer, Power Plants and various other Industrial Plants. In the company’s electrical construction project site experience in supervision of work Execution for Transmission Over Head Lines and underground cables up to 400 KV level. Exposure to planning, coordination and execution of primary sub-stations including inspection and monitoring conditions, troubleshooting sand correction of problems in Power Transformers, Switch gears of a high voltage system. Worked as Project Engineer in Vizag Port Trust Site for HT/LT Substation and7 Story 3 Buildings Electrification works and handled all installations successfully as per Company’s contract. In electrical distribution utilities, exposure in routine and preventive maintenance of 11KV distribution network consisting of Switch gears, Transformers and Overhead Lines. Experience in maintenance of HT/LT Sub stations, Street lightings, and other LV Installations, Exposure to fault identification and rectification in different locations of 11KV/415 V System. Also experience in operation & maintenance of different types of Circuit Breakers, RMU’s, OLU, HFU. Experience in Supervision of underground cable laying and OH Lines ranging from 11 KV to 400 KV EHV Lines.
PERSONAL DETAILS:
Address: Flat No.-408(A), Nandighosh Avenue, Jayaprakash Nagar, Brahmapur,Ganjam,Odisha,India.,PIN: 760010
Date of Birth :01-07-1961
Nationality : Indian
Marital Status: Married
Passport No : U 5443865
Date of Issue : 02/07/2020
Date of Expiry: 01/07/2030
Place of Issue : Bhubaneswar
Languages Known: English, Hindi, Oriya, Tamil and Arabic (to some extent)
I hereby declare that the above mentioned details are true to the best of my knowledge and belief.
SISIRA KUMAR RATH
Date: