To acquire a remarkable and versatile position in my profession, by working noticeably and with up to the mark performance in an organization of repute, through my knowledge, qualifications, analytical, problem solving, communication and interpersonal skills and fast learning abilities and confidence.
Professional Experience
An analytical and proactive Graduate Engineer with over 18 years of experience in Civil Project management Engineer in Industrial and Oil and Gas Plant Projects, Oil & Gas Onshore Piping & Pipeline Projects,Oil Storage Terminals and Petrochemical Construction Projects in the various parts of Middle East and India.
Qualification
B.E in Civil Engineering
Training and Course
ISO 9001-2008 Lead Auditor
SKILL
●Review and monitor contractors planing schedule and execution, continual monitoring of contractor quality, safety and progress performance.
●Reviewing and Approving Contractors submittals.
●Familiar with International Codes, Aramco Standards and QCS.
●Good experience in project management and controlling.
●Timely taking corrective and preventive action for all non-conformation.
●Reviewing and approving technical and material approval documents.
●Updating and doing root cause analysis of NCR and CAR
●Conduct training for Site quality members to achieve project quality plan target.
●Control and monitoring daily basis Inspection completion and daily progress.
●Reporting to Management regarding all outstanding issues.
●Attend various Project Management Team meeting and Participate Team decision in line with Project Quality Requirement.
●Review and Approving Contractors Documents of Control Procedures like Material management Control Procedure, No-Conformity Control Procedure, Inspection Procedure etc.
●Using Various Software like, Microsoft word, excel
●Ability to work independently, hardworking and dedication to work.
●Attend EPC quality control weekly meeting and solve the quality issues in line with Project requirements.
Experience
●Proven ability & Technical Competence as Lead Engineer (PMC) at various infrastructure projects, Non Process facilities, Buildings, HCIS security fencings,Mega Oil and Gas Plant Project, Major Oil & Gas, Oil Storage Terminal facilities and Petrochemical development projects in GULF and INDIA
●Implementing and maintaining the management systems as per ISO 9001-2008.
●Familiar with Saudi Aramco, QATAR Petroleum, and Other Oil/Gas related Job Specifications, ASTM, BS and QCS-2014 Codes and Standards.
Current Employer
Company Name - Intertek global
ASSIGNMENT
CNG Station and pipe line project at Rasalafan, Qatar.
Position - Lead PMC Civil Engineer (June 25 - 19 onwards)
Project Description
Handling as Lead Civil PMC Engineer for CNG stations and pipeline routes having three location, construction of launcher facilities from existing plant and underground buried service line from launcher station to CNG Station where receiver is located with major infrastructures and control/ office buildings, substation building facilities.
Bridges, culverts, primary Roads and service Road construction.
PREVIOUS EMPLOYERS
1,Company Name –DNV GL through LA Recruitment
ASSIGNMENT
Hamad International Airport Jet A1 Supply pipeline project.
Position - PMC lead Civil Engineer (July 25 - 18 to June 15 - 19)
Project Description
Handling as Lead Civil PMC Engineer for Hamad international Airport infrastructure facilities.Bridges, culverts, primary Roads and service Road construction, Pavement/Runway construction and maintenance .Supply pipeline project which is having 132 km long 24 inch down stream pipeline and 15 km long 28 inch upstream pipeline,jet fuel tank farm area which is consist of 4 numbers tank having 66 M dia and 20 M height,
2,Company Name - TUV
Jizan Refinary and economic city
Position
Saudi Aramco Civil Lead Engineer (October 2017 to May 2018)
Project Description
Handling as Lead Civil PMC for Jizan industrial economic city infrastructure.
Petro rabigh Phase II
Position
Saudi Aramco Civil Lead Engineer (Jan 2015 to April 2017)
Project Description
Non Process facilities which ishavingSix EPC as a one package (Non process BuildingsPackage, Early works -01, early work-02, ROD (for full road construction), COM (Permanent communication and temporary communication works) and PRSU (Petrorabigh Security upgrade system)
Position
Saudi Aramco Sr. Civil Engineer (Jan 2014 to Dec 2014)
Project Description
Refinery Naphtha and Aromatic Complex package civil industrial infrastructures, foundations for Pipe racks, Heavy equipment, Concrete and Asphalt Pavements works, Several Substations and Process interface buildings Construction.
Manifah Central Processing Facility
Position
Saudi Aramco Civil Engineer (Nov 2011 to Dec 2013)
Project Description
Construction of Mega Plant Project its consisting of several packages, Construction of foundations, Road and Pavers, Crude storage tanks, Water storage tanks, Huge numbers of pump foundations, Equipment foundations, Several number of Substations, other Utility Buildings, as per Saudi Aramco Standards, ASTM and Other International Standards.
3,Black Cat Engineering and Construction (EPIC)-Qatar
Position
Lead QA/QC Engineer - Approved by Qatar Petroleum, November 2010 to Sep 2011
Project Description
Construction of 42 Km. 36" & 18" Underground Pipe line, 87 Km. 12", 6" & 4" Above ground Pipe line and Right of Ways, Valve Chambers, Culverts for Road crossing, Duct Bank for Future road crossing, Pipe Sleepers, Electrical Substations, DG Building and Compressor Buildings in four locations, Electrical & Instrument Cabling, Trench Excavation, underground Existing service crossings, Pre padding, Lowering, Post padding, backfilling and Berming works as per Qatar Construction Specification (QCS-2014), BS and QP Engineering Standards.
4, Commodore Engineering
Position
PMC Civil Engineer -June 2007 to Oct 2010
Project Description
Construction of Twin towers which is having 94 and 56 floors height at Dubai Marina, Construction of Housing Units and its infrastructure development including Roads, Utilities, Substations, Bridges and culverts.
5, KITCO, A public sector Consultancy
Position
PMC QA/QC Engineer, April 2005 up to May 2007
Project Description
Construction of Oil Storage Terminal Facilities- 6 numbers of huge Oil Storage Tanks resting over Sand pad Foundations, Asphalt roads and Concrete Roads, Culverts and Small Bridges for Road crossing, Duct Bank crossing, Pipe Sleepers, Pipe line support foundations, Electrical Building, Utiliy buildings, Electrical & Instrument Cabling, Trench Excavation, underground Existing service crossings, Heavy machinery foundations As per Engineering Standards.
6, Artech Group, Consultancy firm in India
Position
Consultant Site Engineer, May.2002 up to March.2005
Project Description
Infrastructure works and high rise buildings at Trivandrum.
Personnel Information Date of Birth 05-04-1978
Sex Male
Nationality Indian
Religion Islam
Marital Status Married
Passport No K9633067
Date of Issue 16-12-2012
Date of Expiry 15-12-2022
Declaration:
I hereby declare that the above mentioned details are true to the best of my knowledge and belief.
Date: M.A.Amjath Khan