QA/ QC Electrical Engineer
Electrical Engineer
NELLIX A. LORETE
Email : **************@*****.***
Mobile : +639********* - Philippines
+639********* - Philippines
Location : Palo, Leyte Philippines
PROFILE:
I am an Electrical Engineer, 15 years of experience and depth knowledge in Construction Supervision, Management, Site Coordination and QA/QC Inspections. Involved in various construction of Energy, Power Plants, Railways/Metro, High Rise and Industrial Building projects in UAE, KSA, Philippines and Qatar. I'm involve in survey of system site requirement, review of Method Statement & Installation Drawing, I'm full supervision of execution of the installation and coordination other services. Maintain the high standard of quality and maintain high value health and safety and sustainability policies and legislation. Attend the meeting with the client and present the progress and discuss any issues in construction and quality. Conduct site visual, dimensional, testing inspection. Provide technical advice and solution to the site requirement and issues. Accustomed to leading highly effective multidisciplinary teams to complete projects in alignment with corporate goals. Hardworking and reliable with strong ability in supervision, management, inspection, testing and Review. Highly organized, proactive and punctual with team-oriented mentality. QUALIFICATION:
Bachelor of Science in Electrical Engineering, 2001 Eastern Visayas State University, Philippines
Registered Electrical Engineer
Professional Regulations Commission, Philippines
PROJECT HIGHLIGHTS:
2016 TO 2018 Mitsubishi Heavy Industries, Qatar Rail Projects, (Greenline, Redline & Goldline) Doha, Qatar
2015 TO 2016 Bouygues Batiment International, Qatar Petroleum District Towers Doha, Qatar
2014 TO 2015 Hyundai E& C & Samsung E & C JV, Baraka Nuclear Power Plant Abu Dhabi, UAE
2012 TO 2014 Daewoo E & C & Siemens JV, S3 1600 MW Gas & Steam Power Plant Abu Dhabi, UAE
2008 TO 2012 Saudi Lebanese Tarouk Construction Company, Al Wassil Tower Prince Sultan Palace, Riyadh National Hospital
Riyadh, Saudi Arabia
2002 TO 2008 Various Construction Projects in the Philippines
- Infrastructure, Utilities and Telecommunication Projects
- Commercial and High Rise Building Projects
EXPERIENCE:
Duration: February 1,2019 – Present
Position: Private Practitioner
Company: Self Employed
Project : Electrical Installation
Phili[ppines
Duration: November 1,2016 – December 30,2018
Position: QA/ QC Electrical Engineer / Tunnel Ventilation System Installation Coordinator Company: Mitsubishi Heavy Industries
Project : QATAR RAIL PROJECT (DOHA METRO)
DOHA QATAR
Duties &Responsibilities
Supervise and manage construction activities daily.
Conduct site inspection with the client
Review method statement.
Review Installation drawing.
Perform dimensional, visual, electrical, and mechanical inspection using standard document and procedures, Close out NCR/SDR /Snags.
Conduct RFI (Request for inspection) / ITN (Inspection Test Notices)/ IRE.
Maintain the highest standard of quality.
Review the work progress on a daily basis.
Prepare internal and external reports pertaining to job status.
Undertaking surveys.
Oversee all onsite and offsite constructions to monitor in station/tunnel and safety regulations daily.
Coordinate and supervise construction workers and sub constructors.
Maintain a high value of health and safety and sustainability policies and legislation.
Attend the meeting with clients and PMC. Provide technical advice and solution to the problem on site. Duration: November 4,2015 – October 31, 2016
Position: QA/ QC Electrical Engineer
Company: Bouygues Batiment International
Project: QATAR PETROLEUM FINANCIAL DISTRICT
West Bay Doha, Qatar
7 – Unit of Highrise building
1 – Unit of 47 stories hotel
1 – Energy center
1 – 3 Story underground park
1 – Data center
Duties & Responsibilities
Discuss Quality Issues with the consultant/ Supervise construction on site.
Maintain that health and safety and sustainability policies and legislation.
Hand Over of Electrical System
Close out of Non-conformance Report (NCR) & Surveillance Deficiency Report (SDR)
Maintain high quality standards in accordance with contract specification and local laws (QCS and KHARAMAA)
Perform dimensional, visual, electrical, and mechanical inspection using standard documentation and procedures
Conduct RFI (Request for Inspection / ITN (Inspection Test Notices)
Maintain high standard of quality, comply with Methods Statement. ITP. Project specification & QCS.
Observe and record activities in site if accordance with approved latest drawing and method statement. Duration: May 4, 2014 – July 15, 2015
Position: QA/ QC Electrical Engineer
Company: Jonghap E & M Constructing Company
Daewoo E&C & Samsung E&C Joint Venture
Project: Baraka Nuclear Power Plant
Abu Dhabi, United Arab Emirates
25 number of staff and worker facilities building.
Simulation training center building
Administration building
Operation and maintenance building
Water reservoir/treatment building
Electrical sub - station
Duties &Responsibilities:
Monitoring and administering the QA/QC plan or program.
Supervise construction on site.
Discuss Quality Issues with the consultant
Maintain that health and safety and sustainability policies and legislation.
Hand Over of Electrical System
Closeout of Non-conformance Report (NCR) & Surveillance Deficiency Report (SDR)
Maintain high-quality standards in accordance with contract specification and local laws
Perform dimensional, visual, electrical, and mechanical, inspection using standard documentation and procedures
Conduct RFI (Request for Inspection / ITN (Inspection Test Notices)
Maintain a high standard of quality, comply with Methods Statement. ITP. Project specification
Observe and record activities in the site if accordance with approved latest drawing and method statement.
Duration: June 4, 2012 – May 3, 2014
Position: QA/ QC Electrical Engineer
Company: Jonghap E & M Constructing Company
DAEWOO E & C COMP. & SIEMENS Joint Venture
Project: S3 IPP GAS & STEAM POWER PLANT
Combine cycle power plant (1600 Megawatts)
Abu Dhabi, United Arab Emirates
Monitoring and administering the QA/QC plan and program.
Close Coordination construction executions.
Assuring that the work is performed as required by the contract and meets the required qualities.
Follow and maintain company standard of quality in accordance with comp. quality system requirements.
Perform dimensional, visual, electrical, and mechanical, inspection using standard documentation and procedures.
Conduct RFI (Request for Inspection) / ITN (Inspection Test Notices).
Maintain the highest quality standard
Maintain the procedure health and safety are followed, sustainability policies and legislation. Duration: June 4, 2008 – March 2, 2011
Position: Site Electrical Engineer/ QA/ QC Electrical Engineer Company: SAUDI LEBANESE TAROUK CONSTRUCTION COMP. LTD. Riyadh, Kingdom of Saudi
Projects:
Al Wassil tower
Prince sultan palace
Riyadh national hospital
Duties & Responsibilities:
Prepare electrical drawings and specifications and progress report and conduct toolbox meeting
Manage project schedules and budgets.
Maintain the highest quality standard
Maintain the procedure health and safety are followed, sustainability policies and legislation.
Make engineering calculations in connection with field and office assignments.
Investigate problems and recommend solutions.
Ensure compliance with safety requirements and standards procedures.
Prepare requests for proposals and evaluate bids.
Direct site supervision.
EARLY WORK EXPERIENCE:
Duration: January 23, 2006 – August 26, 2006
Position: Project Engineer
Company: Jaca Construction and Management Corporation Design, Builders & Engineering Services
Project: Vertical & Horizontal Building(Project)
Dasmarinas, Cavite, Philippines
Duration: February 2005 – December 2005
Position: Safety Engineer/Project Engineer
Company: M. E. Sicat Construction & Consultancy
2ndFlr. Forab Bldg., 121 Kamuning Road,
r : Project: Vertical & Horizontal Bldg. Water Reservoir &Treatment Facilities Duration: January 6, 2004 – January 7, 2005
Position: Electrical Engineer
Company: R.S. Developer Co., Inc.
Tacloban City, Philippines
Project: Telecommunication (Project)
Duration: April 18, 2002 – August 15, 2002
Position: QC/QA Engineer
Company: Ionics EMS, Inc.
LISPP_-1 Cabuyao Laguna, Philippines
TRAINING AND CERTIFICATE:
Basics Occupational Safety and Health
March 7-11, 2005, Philippines
MV/LV Transformer Protection and Earth System
April 23, 2010, Riyadh, Kingdom of Saudi Arabia
Basics KNX-EIB System and Programming
June 18,25, 2010 to July 02, 09 2010, Riyadh, Kingdom of Saudi Arabia
High Voltage Substation Design Seminar, Basics of Power Cables August 7,2009, Riyadh, Kingdom of Saudi Arabia
Short Circuit Calculation, DOC Version and ABB Low Voltage Awareness January 10,2010, Riyadh, Kingdom of Saudi Arabia
Fire Safety
Incident /Injury Investigation
Site Incident Prevention Program
Control of Hazard Energy: LOG OUT /TAG OUT
Basic and Advance Electrical Safety
QS-9000 (Quality System)
ISO-9002 (International Standard Organization)
ISO-14001 (Environmental Management Organization) PERSONAL DATA:
Date of Birth: 17 February 1979
Civil Status: Married
Nationality: Philippines