Arcadious Smith
832-***-**** **************@*****.***
Objective
Dedicated and accomplished Rigging and Iron Supervisor focused on completing projects in a professional, safe and timely manner. Seeking opportunity to apply 27 years of Construction experience to a new project.
Skills & Abilities
MANAGEMENT
·Throughout years in supervision as a General Foreman, and Foreman, gained valuable skills including the ability to lead multiple crews and perform practical daily duties
·Safety remains top priority, personally and within a crew of employees, as assigned tasks are performed
·Under direction of the Construction Manager, able to hold daily and weekly safety meetings, complete incident reports and performance evaluations, and record attendance of multiple crews
COMMUNICATION
·Able to communicate effectively with employees with proficiency in multiple crafts including Crane Rigging and Ironwork
·Evaluate situations where improvements can be made and clearly voice suggestions with respect and professionalism
·Possess strong interpersonal skills and able to effectively listen and follow instructions
LEADERSHIP
·Mentor from the position of General Foreman and Foreman to instill values of pride, and workmanship in all employees
Experience
RIGGER MCDERMOTT AUGUST 2017 – MAY 2020
·Set up, tear down, and rebuild cranes
·Load/unload steel from trucks, constantly evaluating effective methods of rigging based on weight, shape, and size
·Set equipment and material on elevations for various crafts
RIGGING GENERAL FOREMAN FLUOR AUGUST 2014 – FEBRUARY 2017
·Held meetings, filled out necessary paperwork, and signed permits for Heavy Lifts
·Set equipment, based on priority, to meet scheduled deadlines
·Managed foreman and developed daily plans to achieve expected progress
RIGGING & IRON FOREMAN L-CON INC. / LEXICON SEPTEMBER 2012 – MAY 2013
·Supervised the building of transmission towers in West Texas
·Directed crews in timely tower erection per manufacturer’s specifications
·Conducted safety meetings and daily meetings to ensure adherence to strict site assembly requirements
IRON FOREMAN J.V.I.C. JUNE 2006 – APRIL 2012
·Directed crews working on gas units in Fort Stockton, TX
·Oversaw crew safety meetings and ordered required materials
·Reviewed drawings in order to build and fabricate according to factory specifications
RIGGER S&B MARCH 2003 – MAY 2006
·Built and dismantled cranes in Florida
·Calculated crane/rigging specifications, including weights and parts per line
·Set equipment and placed materials where needed
References Upon Request