MUTHUKUMARAN

B.TECH CIVIL (****), D.C.E (****)

Address:

9c, G2, Sukkal Street Mobile: +91-877******* (INDIA)

Venkatapuram,Ambattur E-mail: adhg7i@r.postjobfree.com

Chennai- 600053

A prospective career in the field of Civil Engineering amidst challenging environments that would utilize and hone my professional and interpersonal skills and in the process augment values to the concern.

I, Muthukumaran Civil Engineer is having more than 23 years of professional experience in managing Construction Projects as a Construction Manager (STRUCTURES) right from development to delivery and controlling phases of project life cycle, overall inter-discipline co-ordination. A dynamic Engineer with expertise in Preparing the Method Statement, Planning, Scheduling, Resource leveling, Tracking, Monitoring Executing construction projects with a flair for adopting modern construction methodologies in compliance with quality and construction safety standards that holds the distinction of executing numerous construction projects within a strict time schedule with stringent measures for cost and quality control. I have excellent relationship management, analytical and negotiation skills with deftness in swiftly ramping up projects in co-ordination with clients, contractors, Independent Engineers, PMC and Conversant with, IRC, MORTH, IS Codes, BS Codes and several other standards and specifications.

.

B.Tech (civil) - Janarthan rai Nagar Rajasthan vidyapeeth University, Dec 2010 with 67.1% Grade B

In distance mode.

D.C.E – Valivalam Desikar Polytechnic Nagapattinam, April 1996 with 76.83% 1st class with honours

H.S.E - Swamy Dayanantha Higher sec school, Manjakkudi, March 1994 with 78.08%.

SSLC – R.K.R Govt High school, Thirucherai, April 1992 with 78.4%

Indian Road congress Life member LM-40861 from Feb 2014

Indian Concrete Institute Life member LM-10297 from March 2014

Association of Consulting Civil Engineers (India) Life Member LM-3425 from March 2014

Indian Society of civil Engineers Member from April 2014

Primavera P6 Release 8.2

Microsoft Project

AutoCAD 2004

Microsoft word, Microsoft Excel

Working as a Freelance Self Owner from May 2017 to Till date.

Working as a Construction Manager (STRUCTURES) in M/s LARSEN & TOUBRO LIMITED –ALWAKRA, QATAR from 30/03/2014 to April 2017.

Worked as a Deputy Construction Manager in M/s Simplex infrastructures ltd (SIL) from 24/08/ 2009 to till 21/11/2013.

Worked as a Manager (STRUCTURES) in M/s Maytas infra ltd -Bangalore from 21/02/2007 to 11/08/2009

Worked as a Senior Engineer (Bridges) in Galfar Almisnad W.L.L, QATAR from 04/12/2005 to March 08/01/2007.

Worked as a Site Engineer in M/s Bhagheeratha Engineering Limited (BEL) from 22/02/1998 to 19/11/2005

Worked as a Technical Trainee in M/s Madras Refineries Ltd (MRL) Nagapattinam, Tamilnadu from 21/08/1996 to 20/08/1997

From May 2017 to till date

Name of the Organization : Self Business

Post Held : Freelance Self Owner

JOB RESPONSIBILITIES:

Construction of Pipe culverts, Box Culverts, Drainages and Retaining wall.

Studying the drawing and Executing the Project.

Co ordination with Main Contractors in Various activities.

Maintaining the Manpower and Staff.

Submitting the Bill.

Maintaining the reconciliation report of materials.

From March 2014 to April 2017

Name of the Organization : Larsen & Toubro Limited, QATAR

Post Held : Construction Manager (Structures)

Client : Public Works Authority (ASHGHAL)

PMC : KBR

Consultant : Halcrow

Design Consultant : WSP

Name of the Project : Design & Construct Al-Wakrah Bypass Road (P015),Qatar

Project Value : 2.187 BILLION QAR

Duration : 33 months

SALIENT FEATURES

Expressway Programme Project 15 entails the construction of Al Wakrah Bypass and 11 kilometer, North-south freeway corridor between the proposed East West Corridor and the existing AlWakrah-Mesaieed Road. Al Wakrah Bypass is the southern segment of the major north-south high-speed corridor which connects to Al Shamal Road to the north and Al Wakrah-Mesaieed Road to the south, where it diverges towards the future Doha Port and the Mesaieed Industrial Area. The project will include five through lanes in each direction, with auxiliary and collector distributor roads as required. The proposed median includes the space allocation for the future construction of two additional lanes in each direction. The project includes 5 Interchanges namely IC-10, IC-11, IC-11A, IC-11B and IC-12 respectively.

JOB RESPONSIBILITIES:

Preparing the method statements of various construction activities.

Preparing the work programme for construction of Interchanges.

Preparing the Resource calculation of Interchanges.

Coordinating various departments to getting work permits.

Micro-level works program for each & every items of works was being done and accordingly implemented at site.

Ensuring that all quality control, environmental and health and safety requirements are met.

Managed daily operations, and planned the use of materials and human resources.

Generating work permit on daily basis and implementing its recommendations

Directing and supervising workers.

Conducting Daily Toolbox Talks

From August 2009 to November 2013

Name of the Organization : Simplex infrastructures ltd

Post Held : Deputy Construction Manager

PROJECT:1

Improvement of Existing Intermediate Lane Jagi Road - Morigaon Road to Two Lane

Configuration Under SARDP - NE (PH-B),Length-23km and construction of R.C.C Bridge NO-7/2

over River on KAPILI ON Jagiroad-Morigaon Road under SARDP-NE(PHASE B)

N.H Division,Nagaon,Assam .

CLIENT : PWD (NH), MINISTRY OF ROAD TRANSPORT & HIGHWAYS ASSAM

CONTRACTOR : SIMPLEX-SOM DATT BUILDERS (JV)

Contract Value : 85,70,35,284.90

Duration : 48 Month(s)

PROJECT:2

Project Management, Design, Engineering, Survey, Procurement, Supply, Fabrication, Inspection, Transportation, Storage, Construction, Testing, Installation, Modification and handover of Road and Pipe Bridges in Orissa.

OWNER : Indian Oil Corporation Limited (IOCL)

Consultant : Foster Wheeler Limited

CONTRACTOR : Simplex Infrastructures Limited

Contract Value : 57,58,80,949.71

Duration : 16 Month(s)

PROJECT:3

Construction of Approach Jetty, Main Berths and Mooring Dolphins for Gujarat.

Salient Features:

The Berth is a free standing structure about 520m long and 27m wide supported on pile foundation. This is connected to shore by 1170m long Bridge over the sea and 1240m bund structure.The Berth is designed to handle 10000 DWT to 80000 DWT Vessels with dredge level of 15.00m CD

Client : M/s Adani Petronet Port Pvt Ltd at Dahej

Consultant : M/s L&T-RAMBOLL

Duration : 60 Month(s)

Contract Value : Rs. 84, 00, 00,027/-

JOB RESPONSIBILITIES IN SIMPLEX PROJECTS:

Project Planning, scheduling, and Resource Leveling,Tracking and monitoring.

Co-ordination with the Concerned Client, Consultant & Sub Contractor for timely completion of the items of works in relation to the planned program set up for the project

Daily management of up to 10 project staff and multiple sub contractors & PRWs.

Preparing Method Statement for Structures.

Checking Piling operations, Rig Movement Plans and Maintaining its Records

Checking Island making, Well Sinking Operations and Maintaining Tilt Shift Records

Designing and Supervising of Scaffoldings’ and Shuttering of Structures.

Preparation of BBS for all type of structure

Detail calculation of Pre Stressing and maintaining its records and checking Pre casting and launching operations.

Maintaining operations in Precast Yard, Stock Yard and Its Records

Ensuring that all quality control, environmental and health and safety requirements are met.

Managed daily operations, and planned the use of materials and human resources.

Accurately estimate material, construction and labor costs as well as project timescales.

Directing and supervising workers.

Responsible for Rate analysis for Road work, Bridge work

Assisting & monitoring Billing Engineer for making Client Bill.

Checking of sub contractor rate, checking of subcontractor billing

From January 2007 to August 2009

Name of the Organization : Maytas infra ltd

Authority : National Highways Authority of India

Independent Consultant : M/s Renardet S.A, Ingenieurs conseils

Concessionaire : M/s Bangalore Elevated Toll way Limited

Cost of the Project : Rs. 756 Crore

Contract Value for MAYTAS : Rs. 224 Crore

Post Held : Manager (STRUCTURES)

PROJECT:1

Construction of3.5 km 4 lanes Elevated Divided Carriageway Road between Silk Board Junction and Electronic City Junction at Bangalore – Hosur section of NH-7 on a Build, Operate and Transfer (BOT) Basis for NHAI.

Salient Features:

The Elevated Roadway is supported on a one Pier in the centre of the median. The piers are founded in hard rock on 1200 mm dia bored-cast –in suit piles. Each module of the Elevated Roadway is 262 meters with span arrangement of 2x29 meters+6x34 meters.The Superstructure of the Elevated Road is one of the most elegant in the Country, designed to compress construction time, permit full and uninterrupted traffic flow, using the Segmented Construction Method. In this method the Elevated Roadway Superstructure units were match pre cast to their final orientation in three independent casting yards simultaneously, transported to the sites at night, hoisted in precise position by an Overhead Gantry, epoxy glued and post tensioned. Separate overhead gantry was deployed in each stretch thereby compressing the construction time. A cycle time of average 4 days per span was attained by fine tuning the activities.

JOB RESPONSIBILITIES :

Responsible for adopting of all procedure, drawings while execution and. also responsible to organize manpower, material, equipment to achieve targeted program of works.

Interact with Consultant regarding the works program, Co-ordination with the Concerned Client & Sub Contractor for timely completion of the items of works in relation to the planned program set up for the project.

Daily management of up to 6 project staff and multiple sub contractors & PRWs

Preparation of BBS for all type of structure and Fixing of Reinforcement for structures.

Supervising of Scaffoldings’ and Shuttering of Structures.

Checking laying, compaction of concrete including curing operations.

Checking of void formation and fixing in positions for void slabs.

Checking of Reinforced Earthen Wall construction.

Micro-level works program for each & every items of works was being done and accordingly implemented at site.

Checking of sub Contractors bills inclusive of all sorts of measurements for each item of works after getting proper workmanship at site.

Checking the Qualities of materials delivered at site and bills were being certified accordingly.

From December 2005 to January 2007

Name of Organization: Galfar Almisnad W.L.L, Qatar.

Client : Qatar Petroleum

Post Held : Senior Engineer Bridges

Project Value : 300 million QATAR RIYAL

PROJECT:1

Engineering, Procurement and Construction of New Roads and Extension of Existing Roads at Ras Laffan, and construction of a major bridge across the running Water Channel without disturbing flow in the Channel and meeting the environmental obligations of the RLC and building six bridges adjacent to Sea for Qatar Petroleum in Qatar

JOB RESPONSIBILITIES:

Construction and supervision of a major bridge across the running Water Channel without disturbing flow in the Channel and meeting the environmental obligations

Preparing Method Statement for Structures.

Supervising of Scaffoldings’ and Shuttering of Structures.

Preparation of BBS for all type of structure

Supervising construction of cofferdams.

Checking laying, compaction of concrete including curing operations.

Risk Assessment of every activity as according to work implemented with Significance aspects and risk.

Detail calculation of Post Tensioning and maintaining its records and checking Pre casting and launching operations and grouting operations.

Maintaining operations in Precast Yard, Stock Yard and Its Records

Ensuring that all quality control, environmental and health and safety requirements are met.

Managed daily operations, and planned the use of materials and human resources.

Generating work permit on daily basis and implementing its recommendations

Directing and supervising workers.

Conducting Daily Toolbox Talks

From February 1998 to November 2005:

Name of Organization: Bhagheeratha Engineering Limited

Post Held : Site Engineer

PROJECT:1

Construction of 3 Km Long Two laning Bridge Over Krishna river between Korti-Kolhar on the back water of Almatti Dam on NH 218 in Bijapur (Dist), Karnataka.

CLIENT : PWD, KRISHNA JAL NIGAM LTD, KARNATAKA

CONTRACTOR : Bhagheeratha Engineering Limited

Contract Value : 50 CRORE

Duration : 60 Month(s)

PROJECT:2

Construction of Four laning Etawah Bypass project length 13.6 km from km 307.5 - km 321.1 for NHAI at Etawah, Uttar Pradesh.

Post Held : Site Engineer

Consultant : SMEC International Pty Ltd.

Client : National Highways Authority of India

PROJECT:3

Construction of Two Laning Bassein Creek Bridge 556 m long of composite type with pre-stressed end spans cast in situ and the rest is of pre-stressed balanced Cantilever on Bombay-Ahmedabad section NH 8 for NHAI at Navi Mumbai, Maharashtra.

Post Held : Junior Engineer

Consultant : LEA International Pty Ltd.

Client : National Highways Authority of India

CONTRACTOR : Bhagheeratha Engineering Limited

Contract Value : 33 CRORE

Duration : 48 Month(s)

Salient features

The bridge is the first of its kind in India where shock transmission units have been installed to transfer seismic force up to 3100 KN shock loads .It has large caisson floated foundations, positioned 21 meters deep in water and anchored in rock at 30 meters depth against heavy water Currents and tidal variation. The superstructure of the bridge is of composite type with pre-stressed end spans cast in situ and the rest is of pre-stressed balanced Cantilever

JOB RESPONSIBILITIES:

Study the details about the foundation used (open foundation, pile foundation, well Foundation), drawings, soil testing reports, design mix reports etc.

Construction and supervising of superstructure of the bridge is of composite type with pre-stressed end spans cast in situ and the rest is of pre-stressed balanced Cantilever

Preparation of BBS.

Rehabilitation of Old Basin Creek Bridge.

Preparation of Daily Progress Report in accordance with B.O.Q.

Survey works including the checking of center line, calculation leveling and of quantities

of earth cutting and earth filling by using Auto level and Total Station.

Reconciliation of materials including reinforcement, cement, fine aggregate, coarse

aggregate, bentonite, boulder etc.

Reconciliation of Ms plates, Ms pipes, hand jack, propped jack, pipe clamp etc,

Laboratory testing of concrete, fine aggregate and coarse aggregate.

Preparation of Bar chart in accordance with the date wise activities.

Checking shuttering and layouts.

From August 1996 to August 1998

Name of Organization : Madras Refineries Ltd.

Post Held : Technical apprentice Trainee.

PROJECT:1

I Had part of Construction of Residential Staff Quarters and construction of Industrial Buildings, Office Buildings, additional Raw water Reservoir, Crude unloading Plot form,Compound walls for Madras Refinery Ltd, Nagappatinam, Tamilnadu.

JOB RESPONSIBILITIES:

Estimate preparation for buildings and additional Raw water Reservoir, Crude unloading Plot form.

Rate analysis for activities and lead Statement for materials.

Working Drawing preparation and its checking.

Extraction of Quantities for Excavation, P.C.C and R.C.C in raft, beams, slabs etc

Checked the site works for foundation and superstructure including water proofing treatments, concrete pouring, shuttering and formwork, production of concrete, precast elements, masonry construction and finishes.

Material Testing of Cement,Sand, Aggregates, Bricks, and testing of concrete cubes

Preparation of contractor’s bill, checking and certified quantity as per drawing.

Father’s Name : M.Vaithiyanathan

Date of Birth : June15, 1977.

Sex : Male.

Nationality : Indian.

Marital Status : Married

Passport details

Passport number : : L 3778398

Date of issue & expiry : 03/09/2013 & 02/09/2023.

Place of issue : Chennai.

Languages Known

To Read & Write : English, Tamil

To Speak : English, Tamil, and Malayalam & Hindi

Notice : One month notice period

Salary : Negotiable

I hereby declare that the particulars in the curriculum vitae are true and correct to the best of my knowledge and belief.

Place:

Date: (V.Muthukumaran)