DCS/SIS/F&G/Telecom

Systems

Vibration

Monitoring Systems

Transmitters/Flow

Meters

Control Valves/ESD

Valves

Pneumatic/Hydro

Testing

Pre-commissioning,

Commissioning, Start-

up

Cracking Furnaces,

Fired Heaters, HRSG,

GTG, Boiler,

Compressor, Heat

Exchangers

MARIAPPAN PARAMASIVAN

Mobile: +919*********

Email : ************@*****.***

Skype: mariappan.paramasivan

Sr.INSTRUMENTATION ENGINEER/COMMISSIONING ENGINEER

[ 11+ YEARS OF MULTINATIONAL WORK EXPERIENCE]

CAREER OBJECTIVE

To associate with an organization that gives me scope to apply my knowledge and skills in the area of developing applications for electronics and instrumentation industry and acquire new skills. In addition, contribute to innovative design solutions and effective Implementations. Professional Summary

11+ Years of comprehensive work experience as an Instrumentation Engineer in executing various EPCM projects (Green & Brown field) in Malaysia, Gulf (Middle East Qatar) & India.

Hands-on experience of coordination effort in the Electrical & Instrument / F&G Construction, Pre- Commissioning, Commissioning in Offshore / Onshore Oil & Gas industries, Refinery, Petrochemicals, and Combined cycle Power Plant.

Strong Knowledge and Hands-on Experience in Honeywell Experian C-300, Max DNA, Foxboro IA Series Invensys Distributed Control Systems & Invensys Triconex, Honeywell Safety Manager PLC system, GE Mark VI controls System.

Good working knowledge in international codes and standards API, ASME, ANSI, IEC, IP, ATEX & SHELL DEP.

Study and review of tender documents, contract requirements & technical correspondence submitted in the proposal stage.

Effective coordination of various interfaces including project execution team, Vendor, contractors, and their sub-contractor, asset team or other client organizations, Pre-commissioning, Commissioning and handover of facilities and end-of-line facilities.

Manage potential execution phase project risks and uncertainties and take proactive mitigating measures to reduce their impact on the project.

Adept in efficiently handling activities related to coordination with the internal and external departments for smooth plant operations.

Guide & Assist design engineering to implement as per Requirements.

Ability to Read and review P&ID,PFD/data sheet/cause & Effect /HZOP/ instrument Index / IO list /Hook-up / Panel Layout/ Interconnection, Loop Drawings and DCS / SIS system Architecture.

Installation of Field Instruments in Line With Corresponding Drawings.

Knowledge in the design review in construction, commissioning, Start-up and operation of new projects.

Prepare mechanical completion; update commissioning Matrix and start- up progress reports, check sheet run-down reports, certification system & Subsystem reports, punch list of system completion reports.

Prepare Loop Folders, Work Packages, and Completion Dossiers to support the approval/acceptance of Systems or Subsystem Groups according to the Handover Philosophy.

Prepare temporary equipment, tools and consumables lists from Commissioning Procedures material requisitions using SAP/ERP tools as per code & Standard of project specifications.

Bridging Potential Gap between Plant Engineering & Operations team.

All associated project interface activities to ensure the timely & Best practice deliverables are achieving skills.

ACADEMIC QUALIFICATIONS

Bachelor of Engineering 2004 - 2008

Specialization – Electronics & Instrumentation,

Kamaraj College of Engineering & Technology, Anna University Secured First Class – 72%

PROFESSIONAL EXPERIENCE

Jun’ 2018 to May 2020 working as Field Engineer Instrumentation in Tecnimont E&I - Malaysia

Dec’ 2016 to Jun ‘2018 worked as Senior Instrumentation Engineer in Reliance Industries Limited.

Mar’ 2012 to June 2016 worked as Engineer-Instrumentation in Madina Group W.L.L, Doha, Qatar.

Jun’2010 to Nov’ 2011 worked as Instrument Engineer in M/s Chemin Controls & Instrumentation Pvt Ltd, Pondicherry, India.

Apr’ 2008 to May 2010 Worked as Instrumentation Engineer in EI TECH Erectors, Chennai, India. T-BOSIET /SEA SURVIAL TRAINING & COURSES

T-BOSIET OPITO Sea survival, Boat transfer, BA & H2s training course completed in QISC Qatar.(Card No: 74065501310712101466).

Ras Gas liquefied natural gas company limited safety induction training, work management system

(PTW) completed in Ras Gas LNG Company limited Training Centre.

Oryx GTL safety induction, PTW level 1 & PTW level 2(Permit Applicant/Receiver) training course completed in Oryx GTL HSE Training Centre and QISC.

Qatar Shell GTL safety induction training completed in QISC.

Qatar Petroleum visitor’s safety induction attended in Qatar Petroleum HSE training centre.

Completed ‘PLC’ course – Practical knowledge in programming ‘PLC’. CAREER HIGHLIGHTS

Refinery & Petrochemical Projects

Position : Field Instrument Engineer (Construction). Duration : Dec 2016 to Jun 2020.

Company : Tecnimont E&I SDN.BHD-Malaysia.

Client : PETRONAS Malaysia,

Project : EPC of the Flexi HDPE Plant for RAPID Project-Package 27.

Field Supervision of all construction activities related to field Instruments, Fire & Gas devices, PAGA & CCTV etc.,

Coordinating with Clients to get approval for all Review Engineering works and site activities.

Prepare MAR (Material Acceptance Report) for fabrication Materials and other Construction related consumables materials as per Petronas Standards & project specification.

Read & review of MTO, Instrument Index, P&ID, field instruments layout, Cable tray layout, cable schedule, and instrument data sheets, Hook up diagrams, wiring diagram, Vendor Package documents.

Attend site coordinating & meeting, arranging necessary permits and documents to resolve site matters, engineering issue to raise STQ.

Monitoring the all construction related activities of field Instruments, Fire & Gas devices, PAGA & CCTV etc., to release the RFI to QA/QC department.

Co-ordinate with Contractor & Petronas Quality team to resolve the priority of major category punch list of system Completion and Monitoring the Construction Matrix.

Participate in PSSR walkthrough with Petronas operations & Maintenance with management of EPC Construction representative.

Position : Senior Instrumentation Engineer (Construction). Duration : Dec 2016 to Jun 2018.

Company : Reliance Industries Limited.

Project : Refinery Off Gas Cracker Unit - Petrochemical Complex Expansion Project-J3

The world’s first ever and largest Refinery Off-Gas Cracker (ROGC) complex of 1.5 MMTPA capacities along with downstream plants and utilities.

As a part of working with Reliance Project Management Group to executing projects under prestigious J3 Projects worth $4.5 Billion.

Participate in and advise on all instrument construction activities and initiatives.

Responsible for the Construction scope to ensure the Contractor and sub-contractors perform the work to agreed scope of work, Project specifications and schedules all to an acceptable standards.

Supervise the contractor and sub-contractor personnel to ensure performs all the construction activities Instruments, Fire & Gas, and Telecom related work to agreed Project standards for HSE and to attaining high levels of HSE performance.

Responsible to assign the scope of work is carried out in time and without any significant HSE incidents, and Reliance standards and quality requirement.

Responsible for construction instrument activities through the contractors supervision in respect of HSE, method, working practices, quality and timely execution of the works.

Responsible for the instrument Project staff aspect of Risk Management to ensure all risks / opportunities are identified and appropriate controls / mitigations developed and implemented

Responsible for coordination with regard to SIMOPS activities

Ensure that construction hazards and risks are fully considered by designers and contractors and that appropriate mitigation actions are implemented and appropriate action taken.

To be fully familiar with the contractors methods of construction, schedule and procedure

Initiate and manage the instrument project element of the continuous improvement processes

Monitoring the site activities for potential contractual / claims problems.

Maintain records of site activities and check Contractor records for accuracy.

Carry out inspection, surveillance witnessing of contractor activities, ensuring records are maintained, including as-built data.

Endorsed daily/weekly/Monthly progress report and time sheets.

Detailing the work progress, number of contractor personnel and equipment available on site and other related items identified in the scope of work.

Carry out walkthrough with EPC contractor representative and assessment on site construction activities Involvement in the System walks downs and coordinating with QC and subcontractor to clear the punch list for mechanical completion.

Participate in PSSR walkthrough with Reliance operations & Maintenance team.

Oil & Gas Onshore/Offshore Projects

Position : Instrumentation Engineer (Pre-commissioning). Duration : Nov 2014 to Jun 2016

Client : Qatar Shell GTL/Qatar Project Hup (QPH)

Project : HRSG-9 Duct Burner – II

Project : Fired Heater Modification & Tempered water cooling system project. Company : Madina Group-Qatar.

Study and understand the contractual scope of work requirement.

Prepare project execution procedure, Method statement, jobs hazards identification, job safety analysis, safe to work check list.

Coordinating with Clients to get approval for all Review Engineering works and site activities. Prepare MAR (Material Acceptance Report) as per international standards project specification.

Review material specification data sheets, field instruments layout, cable schedule, instrument data sheets, Hook up diagrams, I/O list.

Testing and Pre-Commissioning of HRSG-9 Duct Burner– II with Honeywell Experian Process Knowledge system DCS (C300) & Honeywell Safety Manager PLC (IPS) based Burner Management System

Prepare Method statement for Testing & Pre-commissioning procedure, jobs hazards identification, job safety analysis, safe to work check list.

Prepare loop test folder and review of inspection test reports.

Assist with Honeywell system Engineer to Initial power up DCS & PLC Marshalling cabinet & system cabinet, Graphics modification as per Requirements.

Hot & Cold loop checking of MCC fed Motors/Heater, HT & LT switchgear and their interfaces with DCS, PLC I/O Module etc.

Pre-Commissioning of Fuel gas Burner Skid & Hot & Cold loop checks & functional check of all the field instruments.

Hot & Cold loop checking & functional checking of F&G instruments.

Familiar with Calibration & Commissioning of Field Devices such as PT, DPT,LT,TT,vibration Proximity Probes,RTD,T/C, Control Valves with Smart Positioner, Pneumatic Actuator ESD ON/OFF valve, MOV, safety relief valve & pressure Switch etc.,

Position : Instrumentation Engineer (Construction & Pre-commissioning). Duration : Jan’ 2014 to Nov’ 2014

Client : Ras Gas Limited, Qatar.

Project : PIC of LNG sampling system modification Berth 2 & 3(Offsite) Company : Madina Group-Qatar

Study and understand the contractual requirement and provide input to various departments Procurement, Environmental Health & safety and Quality control etc.

Prepare technical Bid for estimation, working man hours, project execution procedure Method statement, jobs hazards identification, job safety analysis, safe to work check list.

Coordinating with Clients to get approval for all Review Engineering works and site activities.

Prepare MAR (Material Acceptance Report) as per international standards & Ras Gas project specification.

Review of vendor documents, cable sizing & calculation.

Prepare & review material specification data sheets, field instruments layout, cable schedule, instrument data sheets, Hook up diagrams, I/O list.

Co-ordinate with QA/QC department to inspect materials, Equipment’s, Instruments etc.

Supervise vendor activities LNG probe installation, LNG Vaporizer panel installation at loading & Recirculation of LNG line, Mixing vessel panel, HMI panel installation, Hot & Cold loop checking, Testing, Pre-commissioning & commissioning of system.

Reviewing of VESDA wiring Drawing, loop diagram, graphics status, Physical I/O List and System I/O List.

Attend site coordinating & meeting, arranging necessary permits and documents to resolve site matters, engineering issue and work progress at site.

Supervise the Installation of VESDA panel and aspiration tube, Testing and setup system, Cable Laying, meggering & wiring termination.

Attend site inspections to ensure installation work meet job specification and Ras Gas Standard.

Lead & execute Hot & Cold loop check, performing functional tests.

Monitor and prepare weekly and daily progress report.

Prepare Red line Mark-up /As built drawing as per site condition & Modification of site requirement. Position : Instrumentation Engineer

Duration : March 2013 to January 2014

Client : Ras Gas LNG Limited, Qatar.

Project : PIC of LNG Expansion Project AKG-1, Train 3, 4&5 Company : Madina Group-Qatar

Prepare & review material data sheets, field material requisitions using ERP tools, cable schedule, instrument data sheets, Hook up diagrams and As build drawing.

Attend site coordinating & meeting, arranging necessary permits and documents to resolve site matters, engineering issue and work progress at site.

Reviewing of Triconex ESD Marshaling wiring Drawing, loop diagram, graphics Physical I/O List and System I/O List.

Coordinating with Clients to get approval for all Review Engineering works and site activities. Prepare MAR as per international standards & Ras Gas Standards.

Monitor and prepare weekly and daily progress report.

Supervise Installation of field Instruments, Calibration and setup Instruments, Cable Laying, meggering

& wiring termination.

Attend site inspections to ensure installation work meet job specification and Ras Gas Standard.

Lead & execute Hot & Cold loop check, commissioning phase, performing functional tests.

Attend site coordinating & meeting, arranging necessary permits and documents to resolve site matters, engineering issue and work progress at site.

Position : Instrumentation Engineer ( Construction & Pre- Commissioning) Duration : Mar 2012 to Mar 2013

Client : Oryx GTL, Qatar

Title : Unit-135 HER Bypass pipeline

Project : PIC of Unit-135 Heavy Ends Recovery Pipe line Relocation Project. Company : Madina Group-Qatar

Study and understand the contractual requirement and provide input to various departments Engineering, Procurement, safety and Quality control etc

Monitor and prepare weekly and daily progress report.

Coordinating with Clients to get approval for all Engineering works and site activities.

Prepare MAR as per international standards.

Prepare material data sheets field material requisitions using ERP tools, cable schedule, instrument data sheets, Hook up diagrams and As build drawing.

Verifying material as per ORYX Standard for code & process standard specification.

Attend site coordinating & meeting, arranging necessary permits and documents to resolve site matters, engineering issue and work progress at site.

Reviewing of DCS loop diagram, graphics Physical I/O List and System I/O List.

Supervise FBM card Installation at Foxboro I/A DCS. Critical control valve,PT & TT installation, Hot & Cold loop checking, functional check, calibration, Testing & Commissioning.

Attend site inspections to ensure installation work meet job specification and Oryx Standard.

Attend site coordinating & meeting, arranging necessary permits and documents to resolve site matters, engineering issue and work progress at site.

Involved the group management activities like Target Handling, coordinating with group members and Affiliates.

Refinery CPP Project

Position : Instrument Engineer (Commissioning)

Duration : June 2010 to November 2011

Client : HMEL(HPCL & MITTAL ENERGY LTD)

Project : 153 MW CPP, Guru Gobind Singh Refinery

Company : BHEL/Chemin C&I Pvt Ltd

Captive Power Plant of Guru Gobind Singh Refinery Project for our company is responsible for 2X34.5 GT,2x110 TPH HRSG,4x240 TPH UB's,2x36 MW STG,1x32 MW BPTG all the instrumentation Construction and Erection & Commissioning activities in the project.

Handled Lead and Execute Pre-commissioning of unit start-up and performance tests. Preparation of Control System Requirements and Test procedures.

Responsible for Prepare the Commissioning Protocol & Inspections test plan (ITP) Format.

Participate in technical meeting with Project lead to understand Requirement/scope of work/schedule and Quality requirements and share the lesson learnt.

Documentation for Control system requirements for development and Testing.

Prepare the list of Open Loop & Closed Loop Control System. Gas Turbine

Installation & Initial power up Mark VI control panel-TMR & System, Cimplicity SCADA.

Involving in Assistance of commissioning & start up control activities of 3 stage Heavy Duty gas Turbine with Dual fuel combustion system water injection & N2 Purge system.

Hot & Cold loop checks all the field instruments. Calibration of variable inlet Guide vanes & liquid & gas fuel stroke valve.

Commissioning of Air intake filter house system & Evaporator Coolers as applicable & dehumidification for the compartments.

Comm. of heat ventilation system, which controls the compartment temp.& lube oil/Trip oil system.

Checking of MCC fed Motors/Heater(HT & LT)switchgear and their interfaces with DCS, Mark VI control System I/O Module etc.

Gas Deduction & Fire fighting system & Co2 system commissioning & conducting puff/ concentration test for all the compartments.

BENTLY NEVADA 3500 Vibration Monitoring panel commissioning.

Assistance for checking cranking speed turbine, unit first fire, FSNL, Synchronization, over speed test, Redundancy TMR etc.

Hands of experience with combined cycle power plant. HRSG & Utility Boiler

Commissioning of 2x110 TPH HRSG, 2x240 TPH UB’S with MaxDNA DCS & Honeywell Safety Manager PLC with Experian Server based Burner Management System.

Erection & Initial power up DCS & PLC Marshalling control panel& system.

Checking of MCC fed Motors/Heater, HT & LT switchgear and their interfaces with DCS, PLC I/O Module etc.

Commissioning of Oil & gas Burner Skid & Hot & Cold loop checks all the field instruments.

Familiar with Calibration & Commissioning of Field Devices such as PT, TT,Pressure Switches,Temperture Switches, vibration Proximity Probes,RTD,T/C,IGV,LVTD, Control Valves with Smart Positioner, Pneumatic Actuator, safety relief valve, SD valve,MOV.

Defence Project

Position : Instrument Engineer (Construction & Pre-Commissioning) Duration : April 2008 to May 2010

Title : SPTF (Scramjet Propulsion Test Facility)

Title : STTF (Space Craft Thrust Facility)l

Client : LPSC-ISRO, Mahendragiri, TN

Company : EI Tech Erectors.

Installation of PXI PC based control system.

Prepare G.A drawing for instrumentation Panel.

Troubleshooting & power up instrumentation control panel.

Supervise Installation of field instruments, Junction box, Cable tray, and laying cables, impulse line tubing installation as per hook up drawing.

A team of skilled manpower to perform construction activities like panel testing, IR test Hot & Cold loop checking of field instruments.

Manpower planning and mobilization, Material planning, safety coordination, attending safety and progress meeting coordination with client, arranging necessary permits.

Identify tools and test instruments required for performing various activities & prepare data sheet for the procurement.

Handled Instruments

1

Pressure,

Level, Flow &

Temp

instruments

Calibration, troubleshooting, and maintenance of Magnetic Flow, vortex Flow Clamp type flow, Displacer type LT, LS & Float type LS, Honeywell, Rosemount, Yokogawa, ABB Make Smart type temperature/Pressure/Level, Flow transmitters & all type of control valves, etc.

2

Vibration

A) Testing and calibration of Bentley Nevada make Radial vibration and Axial displacement Proximity sensor (model -3300 and 3500 monitors) and protection control.

b) Seismic vibration sensor.

3

Fire & Gas

Telecom

Devices

Hot & Cold loop check, Calibration, and maintenance of Honeywell

& Crowcon Open path & Infra-Red Gas detectors (IRGD), Toxic Gas detector(TGD), Caustic Gas Detector(CGD), Early Warning Smoke Detector(VESDA), Heat detectors, Smoke detector, UV/IR Flame Detectors/ Scanner, Co2 release Fire protection, MAC, Deluge fire Protection, etc.

4 DCS System

Performed Hot & Cold loop check and logic check and pre functional Check, commissioning of Honeywell Experian C-300, Invensys Foxboro IA series, MaxDNA DCS.

5

PLC

Performed Plant shut down logic check, Hot & Cold loop check, and sequence check for ESD and F&G system (safety system) like Allen-Bradley, Honeywell Safety Manager, GE Mark VI control system, Invensys Triconex control system.

Computer Exposure

Operating System : Windows XP/98/2000/2007

Tools Used : SPI (INTOOLS), ERP-SAP, MS-office, MS-Outlook, Auto cad etc. Personal Details

Name Mariappan

Age & Date of Birth 33 [30-April-1987].

Nationality, Gender & Status -- Indian, Male & Married.

Passport Indian Passport # S8120097, valid until 15 Jan 2029.

Countries Worked India, Qatar.

Driving Licence Indian Driving licence(LMV)

Languages Known Fluent in Tamil, English, Hindi

Permanent Address 31,Mangapuram East Side South St, Srivilliputtur-626125, Virudhunagar District, Tamilnadu, India

Permanent Contact Number +91-967*******

Email Id ************@*****.***.

Skye Id mariappan.paramasivan Declaration

I hereby declare that all the details provided are true to my knowledge and I assure that if I am placed at your concern I will perform to the best satisfaction of my superiors. Place: Yours Truly,

Date: (MARIAPPAN.PARAMASIVAN)

REFERENCES

Mr. Karthik Dey (GM)

HOD of E&I Construction.

SEZ PCG- Cluster 5.

Reliance Industries Limited- Jamnagar.

*******.**@***.***