BD CREATIVE
An accomplished Mechanical Project Engineer with broad experience across mining and
tunnelling disciplines. My skillset includes maintenance planning and management, planning and project programme requirements, financial forecasts and cost tracking, liaison with vendors and selection and procurement of the best products and suppliers as well as contract management.
I am dedicated in all aspects of my profession and am passionate about the ever-evolving facets of innovative engineering and business development. Professional Accomplishments: Started my career with the De Beers Group of Companies
(2016) and after 2 years with them I was given the opportunity to work on a one of a kind project in Sydney, Australia (2018). I started as a Mechanical Site Engineer and was promoted to a Project Engineer and gained permanent residency in Australia after one year with the company.
Johannesburg, Gauteng – South Africa
***********@*****.***
https://www.linkedin.com/in/mon%C3%A
9-nagel-144634b7/
EDUCATION
M O N É N A G E L
MECHANICAL PROJECT ENGINEER
Matric Certificate
Noordheuwel High School
2010
Bachelor of Engineering – Mechanical
Engineering
University of North West
2015
PROFESSIONAL PROFILE
CONTACT
WORK EXPERIENCE
MECHANICAL PROJECT ENGINEER
John Holland Sydney Australia (Rozelle Interchange Project) January 2020 – June 2020
Key Functions Delivered & Achievements:
• Ensure accurate forecasting of month to month spending for various cost codes, track CTD vs forecasted values and accruing for expected costs.
• Compile tracking sheets and compare expenditures and forecasted values to the project budget.
• Responsible for the coordination and planning of all major asset deliveries to site as per project programme requirements. This included 6 x Roadheaders for tunneling purposes and supporting plant such as excavators, dump trucks, forklifts and other earth moving vehicles.
• Successfully planned and executed the delivery, assembly, and commissioning of 6 x Roadheaders and supporting fleet of equipment. This included direct communication with local and international suppliers, compiling lift studies for the delivery of equipment, hiring cranes for offloading and installation and planning with other stakeholders on site to coordinate deliveries and installation of equipment, obtaining necessary permits and complying with environmental guidelines.
• Planning and executing maintenance schedules and ensuring availability targets are reached and minimizing downtime in order to achieve production targets.
• Oversee the procurement of all spare parts, consumables and warranty claims for entire fleet and mechanical workshop.
• Implemented systems and tracking sheets for accurately keeping track of the usage of consumables and spare parts as well as reordering.
• Kept track of GET consumption rates and made improvements to this by changing the carbide tip on the front on the picks to a different size, which still gave us the daily BCM rate while reducing pick consumption.
• Sold used picks back to supplier for a portion of the profit when he sells the remaining carbide in the tips to a buyer.
• Managing subcontractors and ensuring supply contracts are adhered to.
• Responsible for the planning and installation of supporting site services. This included the layout of the entire site, planning the distribution layout for supporting services such as compressed air piping, industrial water supply on surface and in the tunnel as well as the dewatering of the tunnel.
BD CREATIVE
Maintenance Management & Planning
Requirement Identification &
Implementation
Project Management, Planning &
Execution
Programme Management
Financial Forecasting & Cost Tracking
Budget Management
Vendor & Supplier Management
Supplier Sourcing & Selection
Procurement & Demand Planning
Contract Management & Negotiation
Mechanical Engineering
Team Management
Crisis & Change Management
Quality Management
Health & Safety Compliance
Machinery & Equipment Coordination
Site Support Services Set-Up
Performance Management &
Evaluations
Production Management
Reading Designs & Implementing
Changes
Plant Management
Commissioning & Decommissioning
Stakeholder Engagement
Relationship Building
Time Management
Startegic Planning
Analytical Thinking
Interpersonal Skills
SKILLS
WORK EXPERIENCE
• Successfully installed compressors and air receivers for the supply of compressed air, industrial water pump installation and commissioning as well as constructing the tunnel dewatering plan, pump selection and designs for buffer tanks.
• Successfully installed 2 x 355 kW fresh air ventilation fans each weighing 17 tonnes and hanging vertically from the tunnel portal due to space limitations. This included making changes to designs, obtaining and interpreting as-built drawings in order to space proof, obtaining certifications for my design changes and following all other engineering principles to safely install the fans such as NDT testing and FEA on ventilation ducting changes.
• Set up of quality control documents such as Inspection and Test Plans, ensure quality controls are adhered to and that witness points are signed off.
• Raising RFIs and resolving any non-conformance issues, compile safety documents such as Safe Work Method Statements (SWMS) and Safe Operating Procedures (SOPs) and ensure safety procedures are adhered to by doing weekly inspections and in the field audits.
• Provided all mechanically related supporting services to the production team such as making changes to equipment to increase productivity.
• Complete designs for structures and equipment as required.
• Following design plans and drawings, making changes to proposed designs to better suit site requirements and temporary design proposals.
• Implemented an accurate fuel tracking system in order to keep track of bulk fuel deliveries as well as fuel usage on site.
MECHANICAL ENGINEER
John Holland Sydney Australia (Sydney Metro 2 Tunnel Boring Project) May 2018 – December 2019
Key Functions Delivered & Achievements:
• Assisting in the coordination and planning of the delivery, assembly, and commissioning of 2 x tunnel boring machines. This included arranging shipments from Germany, obtaining necessary permits for release of items from ports and all other logistic arrangements involved in getting the machines from Germany to Australia.
• Obtaining road permits for oversized vehicles and configuring the best route from storage facilities to site.
• Procurement of all tools, equipment and consumables required to assemble the machines .
• Making use of and managing subcontractors to assist in the assembly (welding and lifting operations).
• We successfully assembled the machines in 6 weeks for production to start.
• Planning and executing the demobilization of the machines from the ground after we have reached our 8.1 km target chainage. This included lift studies, demobilization of the machine in segments in order to lift it out and for transportation, designing push cylinders to side shift the machine in order to lift it out, logistics of getting the machine back to Germany and all other OEM demobilization requirements.
• Responsible for coordinating the delivery, assembly, and commissioning of supporting equipment such as segment carriers, forklifts, excavators, skidsteers, telehandlers, dump trucks and agitators.
• Maintenance scheduling, execution and monitoring of entire fleet.
• Responsible for planning the site layout and site supporting services layout and distribution of surface and into the tunnels. This included compressed air supply, industrial water supply, tunnel dewater plan, setup of cooling plant and grout plant and the diesel refuel bay
• Design of tunnel and surface service pipe brackets, securing a contract with a supplier for manufacturing 8.1 km worth of service brackets.
• Successfully implemented systems to keep track of the consumption of service brackets, service pipes and all fittings in order to ensure there are always enough on site and to arrange deliveries in advance.
• Successfully designed platforms to be mounted onto our existing segment carriers for demobilization of the tunnel services.
• Installation of permanent fresh air fans and jet fans throughout the tunnel.
• Compiling safety documents such as Safe Work Method Statements (SWMS) and Safe Operating Procedures (SOPs).
BD CREATIVE
Evin Crean
Mechanical Project Engineer - CPB
Contractors
****.*****@************.***.**
+61 (0-438-***-***
Leonardo Pia
Tunnel Manager - CPB Contractors
***.***@************.***.**
+61 (0-419-***-***
Hans Janse van Rensburg
Senior Manager Business Improvement
and Systems - Venetia Mine
Hans.JansevanRensburg@debeersgroup.
com
+27 (0-82-429-****
Gustav van der Linde
Engineering Manager - Venetia Mine
******.***********@************.***
+27 (0-83-308-****
WORK EXPERIENCE
JUNIOR MECHANICAL ENGINEER
De Beers Group of Companies
February 2016 – April 2018
Key Functions Delivered & Achievements:
Completed Government Certificate of Competency Engineer in Training Programme and obtained permission to write the exam.
Acting senior engineering foreman for the primary crusher plant:
• Achieved availability and production targets
• Managed and co-ordinated maintenance planning and execution
• Increased artisan availability and completion of planned maintenance
• Decreased planned vs unplanned maintenance in the section Acting section engineer for mine and town services with 5 direct reports:
• Managing maintenance of Light Delivery Vehicle and utility fleet
• Managing mine personnel transportation contract with Vaal Maseru bussing
• Managed and maintained 670 houses in town
Acting section engineer for CAT 6060 shovel fleet and primary crusher plant, with 4 direct reports:
• Successfully planning and coordinating the annual Primary Crusher Plant shutdown
• Achieved availability and production targets
• Contract manager for Barloworld Equipment
• Managed the maintenance for the primary crusher plant
• Compliance to Mine Health and Safety Act