Dnyaneshwar

Bute

MECHANICAL ENGINEER

Summary:

An astute professional offering over 11 years of cross- cultural experience in Project Execution, Erection, Pre- Commissioning, Commissioning of Rotary, Static,

Vibratory & Bulk Material handling Equipment &

Erection & Fabrication of Structure Work with Oil & Gas Refineries, Aluminum Refineries, Power plants,

Electromechanical Projects and Wish to pursue my

career with environment where my technical expertise, leadership quality & Skills will make positive

contribution.

Scholastics:

• 2009 BE (MECH) 62.57%

• 2005 HSC 63.00%

• 2003 SSC 69.86%

Career Chronology:

• 2017 Mechanical Engineer (TEC, UAE)

• 2015 Sr. Engineer (PLL, India)

• 2013 Sr. Engineer (PLOG, Malaysia)

• 2012 Deputy Manager (EPIL, India)

• 2010 Assistant Manager (EPIL, India)

• 2009 Graduate Engineer Trainee

IT Skills

• Microsoft Office

• Microsoft Excel

Driving License

• UAE Driving License – 2569230

• INDIA Driving License - MP66N-201*-*******

Personal Dossier

Address:

Present: - BUHASA OIL FIELD,

MADINAT ZAYED, ABU DHABI, UAE

Permanent: - L-102, Mhada Colony,

In front of ST Workshop, Kaulkhed,

Akola, Maharashtra, India (444004)

Phone:

+971*********, +971*********

Email ID:

adgtvz@r.postjobfree.com

Passport No:

S9814361 (Valid Up to 13/02/2029)

Certifications:

Internal Auditor for ISO 9001:2008

by BUREAU VERITAS.

White Belt in Six Sigma in 2009

Certified for WAH by BUREAU

VERITAS

Certified for LOTO by BUREAU

VERITAS

Certified for Cargo Handling by

BUREAU VERITAS

Get Appreciation for EHS in 2014,

2015 & 2018.

Career Record Since MAY’20 – BU HASA INTEGRATED FIELD DEVELOPMENT PROJECT (ADNOC ONSHORE, BU HASA, ABUDHABI, UAE)

Profile

Title: MECHANICAL ENGINEER–STRUCTURAL (TARGET ENGINEERING & CONSTRUCTION COMPANY)

Duration : 5 Months (Current Role)

Significant Responsibilities

To carryout various shut down at CDS in BUFID PROJECT.

Installation & Alignment of Various Mechanical, piping & Structure inside CDS.

Installation of around 1000 MT of Technical Steel Structure for Compressor Shelter & Various Technical Buildings.

Installation of Cladding for Various technical Buildings.

Preparation of Method statement for Various Mechanical (Equipment) & Structural activities.

Responsible for official communication with client & vendor to solve technical issues for completion of project as per schedule.

Responsible for handling of technical issues like NCR, Technical Queries (TQ) etc.

Plan job as per Shut down or Project requirement.

Preparation of MTO as per project specification.

Arrangement of Material as per requirement of project by coordinating with Vendor. Since APRIL’19 – PE3 REVAMP PROJECT (BOROUGE POLYMER REFINERY, RUWAIS, ABUDHABI, UAE) Profile

Title: MECHANICAL ENGINEER–STRUCTURAL (TARGET ENGINEERING & CONSTRUCTION COMPANY)

Duration : 1 Years & 1 Months

Significant Responsibilities

To carryout various shut down at BOROUGE Refinery.

Installation, Alignment & Pre-commissioning of Ethylene Compressor (Reciprocating Compressor).

Installation, Alignment & Pre-commissioning of Overhead Crane.

Installation, Alignment & Pre-commissioning of Bagging Machine for Bagging Unit.

Installation, Alignment & Pre-commissioning of Palletizing Unit.

Installation, Alignment & Pre-commissioning of Autoloader Unit.

Installation & Alignment of GPR Polymer Vessel.

Installation & Alignment of Various Vessel & Pumps for Catalyst System (Catalyst feed mixer, tank filter etc.)

Installation & Alignment of conveyor System including Mechanical, piping & Structure.

Installation of Technical Steel Structure for Compressor Shelter, Conveyor & Various Technical Buildings.

Installation of Cladding (Sandwich & Single skin) for Various technical Buildings.

Preparation of Method statement for Various Mechanical (Equipment) & Structural activities.

Responsible for official communication with client & vendor to solve technical issues for completion of project as per schedule.

Responsible for handling of technical issues like NCR, Technical Queries (TQ) etc.

Plan job as per Shut down or Project requirement.

Preparation of MTO as per project specification.

Arrangement of Material as per requirement of project by coordinating with Vendor.

Preparation of Billing & Reconciliation as per break up & specification Since May’17 to March’19- ALUMINA REFINERY (EMIRATES GLOBAL ALUMINA, ABU DHABI) Profile

Title: MECHANICAL ENGINEER–STRUCTURAL (TARGET ENGINEERING & CONSTRUCTION COMPANY)

Duration : 1 Yrs 11 Months

Significant Responsibilities

Installation & Alignment of Conveyor Steel Structure & Mechanical Parts.

Installation of 8000 MT Technical Steel Structure for Conveyor & Various Buildings.

Carried out pre-commissioning activities for Conveyor run test.

Closing of punch list to complete the project.

Support for Commissioning activity to startup the plant.

Preparation of Method statement for Various Mechanical (Equipment) & Structural activities.

Responsible for Material Management & Transportation as per site requirement.

Responsible for official communication with client & vendor to solve technical issues.

Responsible for handling of technical issues like NCR.

Preparation of MTO as per project specification.

Preparation of Billing & Reconciliation as per break up & specification Feb’15- April’17 – J3 ASU, GASIFICATION PLANT (RELIANCE REFINERY, JAMNAGAR) Profile

Title : Sr. Engineer- Punj Lloyd Ltd

Duration : 2 Yrs. & 3 Months

Significant Responsibilities

Installation & Alignment of various Static Equipment for Air Separation Unit. (Vessel, Cold Box, Skid etc.)

Installation of 1500 MT Technical Steel Structure for Air Separation Unit.

Assembly of Closed Structure Module to increased Safety & Quality of job.

Carried out pre-commissioning activities for Air Separation Unit.

Responsible for Material Management & Transportation as per site requirement.

Responsible for official communication with client & vendor to solve technical issues.

Responsible for handling of technical issues like NCR.

Preparation of MTO as per project specification.

Closing of punch list to complete the project.

Plan job as per Project requirement & Execute it as per site condition.

Preparation of Billing & Reconciliation as per break up & specification Dec’14- Jan’15- MB LAL RECCOMANDATION AT VARIOUS TERMINALS (IOCL TERMINAL, AKOLA) Profile

Title : Mechanical Engineer- (Pragati Engineering Management Services) Duration : 3 months

Significant Responsibilities

To carryout various shut down at IOCL Terminal.

Fabrication & Installation of Water Tank.

Hydrotesting of Petrol, Diesel & Water storage tank.

Installation Firefighting system at IOCL Terminal.

Installation & Commissioning of ROSOV & DBBV Valves for Petrol & Diesel Tanks at Terminal.

Responsible for official communication with client & vendor to solve technical issues.

Responsible for handling of technical issues like NCR.

Closing of punch list to complete the project.

Plan job as per Project requirement & Execute it as per site condition. March’13- Aug’15- ONSHORE ELECTROMECHANICAL PROJECT (VALE MINERALS MALAYSIA SDN BHD) Profile

Title : Sr. Engineer- Punj Lloyd Oil & Gas Malaysia SDN BHD. Duration : 1 Yrs & 6 Months

Significant Responsibilities

Installation & Commissioning of Full Conveyor System.

Installation & Pre-Commissioning of Drive Units for Conveyor.

Carried out pre-commissioning activities for Conveyor run test.

Closing of punch list to complete the project.

Support for Commissioning activity to startup the plant.

Installation & Alignment of various Mechanical Parts for Conveyor System.

Installation of Steel Structure for various Junction Towers, Pipe racks & Pumphouse.

Installation of Lubrication & Dust Separation System for Conveyor.

Responsible for handling of technical issues like NCR.

Preparation of MTO as per project specification.

Responsible for Material Management & Transportation as per site requirement.

Closing of punch list to complete the project.

Responsible for official communication with client & vendor to solve technical issues. Aug’09- Feb’13- 2 X 600 MW SUPER THERMAL POWER PROJECT (ESSAR POWER MP LTD.) Profile

Title : GET to Deputy Manager- Essar Projects India Ltd. Duration : 3 Yrs. & 6 Months

Significant Responsibilities

Installation & Commissioning of Electrostatic Precipretator.

Installation & Commissioning of Flue Duct System.

Installation of Technical Steel Structure for Boiler, ESP, Ducting & Pumphouse.

Installation & Commissioning of various equipment’s & Mechanical parts required for ESP completion.

Responsible for handling of technical issues like NCR.

Preparation of MTO as per project specification.

Responsible for Material Management & Transportation as per site requirement.

Closing of punch list to complete the project.

Responsible for official communication with client & vendor to solve technical issues.

Perpetration of Billing & Reconciliation as per break up & specification



Contact this candidate