CURRICULUM VITTAE
P.KIRAN KUMAR
S/O P.SIMHACHALAM,
D.NO UD/LD-604,
NEW B COLONY
KONDAPALLI, IBRAHIMPATHANAM,
VIJAYAWADA, 521456
Email:adfu99@r.postjobfree.com
Cell: +919*********
CAREER OBJECTIVE:
To work in a challenging career in an esteemed organization where I can utilize my education and technical skills to attain organizational goals.
ACADEMIC QULIFICATION:
STUDY
PLACE
ACADAMIC YEAR
AGGREGATE
PG Diploma in Health Safety & Environment
IISS – Hyderabad (thru Annamalai University)
2012-13
70%
Diploma in Electrical Engg
Govt. Polytechnic, Vijayawada
2009 – 12
67%
S.S.C
VSV High School
2008 – 09
89.6%
PROJECT EXPERIENCE:
Six months Industrial Training in T.V.L Electricals, Vijayawada (nov 2011 to april 2012)
MECHANICAL TECHNICIAN EXPERIENCE IN 6 YEARS:
WORKING ACTIVITIES:
Work Experience in .Turbine rotarys and pumps and valves.
Knowledge and experience on mechanical job and tools
Casing bolt removal and installation
Hands on experience on assembling and disassembling
GULF EXPERIENCE:
Project Name: QATAR CHEMICAL COMPANY (QATAR)
Project Site : Compressors and pumps
Work : overhauling the compressors
Period : 60 Days (FEB 2020-APRIL 2020)
Site Attend as shutdowns jobs, overhauling and errection plants
1 . Project Name: DR.NTTPS IBRAHIMPATNAM (VIJAYAWADA)
Project Site : 500MW
Work : Overhauling works for STG
Period : 45 DAYS
2 . Project Name: TNEB THERMALPOWER STATION,TUTICORAN (CHENNAI)
Project Site : 2*80MW
Work : Erection work for STG
Period : 6 months
3 . Project Name: K.T.P.S
Project Site : 500MW
Work : overhauling (STG)
Period : 45 Days
4 . Project Name: ULTRA TECH CEMENT PLANT TADIPATRI
Project Site : 2*25MW
Work : full steam turbine overhauling
Period : 30Days
5. Project Name: RTPP (KADAPA)
Project Site : Boiler valves
Work : overhauling the boiler valves
Period : 20Days
6. Project Name: DR.NTTPS VIJAYAWADA
Project Site : 210 MW
Work : Major overhauling STG
Period : 20 Days
7. Project Name: JINDAL STEEL PLANT (RAYAGADA)
Project Site : 35 MW
Work : overhauling the STG
Period : 30 Days
8 . Project Name: INDORAMA SYNTHATIC PVT LTD (NAGPUR)
Project Site : 25 MW
Work : Major overhauling
Period : 28 Days
9 . Project Name: CSTPS (CHANDRAPUR)
Project Site : 2*500 MW
Work : Erection works for STG
Period : 1 year
10. Project Name: AMBUJA CEMENTS LIMITED (BATAPARA) C.G
Project Site : 25 MW
Work : Overhauling the STG
Period : 30 Days
11. Project Name: NCC Power Plant (Nellore)
Project Site : 2*660 MW
Work : Erection work for STG
Period : 6 Months
12. Project Name: SRI DAMODHARAM SANJEEVAIAH THERMAL PLANT(NELLORE)
Project Site : 800 MW
Work : Overhauling the STG
Period : 30 Days
13. Project Name: KORBA SUPER THERMAL POWERPLANT (C.G)
Project Site : 200MW
Work : major overhauling
Period : 35 Days
14. Project Name: RAJARAM SUGAR POWER PLANT (KOHLAPUR)
Project Site : 26 MW
Work : Generator overhauling
Period : 15 Days
NATURE OF WORKS:
Steam Turbines,Generator, Gearbox, boiler valves
PERSONAL PROFILE:
NAME :PARUPALLI KIRAN KUMAR
FATHER’S NAME : P.SIMHACHAAM
DATE OF BIRTH : 03-02-1994
NATIONALITY : INDIAN
RELIGION : HINDU
LANGUGES KNOWN : TELUGU, HINDI, AND ENGLISH
PASSPORT NUMBER : N1227991