Post Job Free

Resume

Sign in

Power Plant Project

Location:
Visakhapatnam, Andhra Pradesh, India
Posted:
September 06, 2020

Contact this candidate

Resume:

CURRICULUM VITTAE

P.KIRAN KUMAR

S/O P.SIMHACHALAM,

D.NO UD/LD-604,

NEW B COLONY

KONDAPALLI, IBRAHIMPATHANAM,

VIJAYAWADA, 521456

Email:adfu99@r.postjobfree.com

Cell: +919*********

CAREER OBJECTIVE:

To work in a challenging career in an esteemed organization where I can utilize my education and technical skills to attain organizational goals.

ACADEMIC QULIFICATION:

STUDY

PLACE

ACADAMIC YEAR

AGGREGATE

PG Diploma in Health Safety & Environment

IISS – Hyderabad (thru Annamalai University)

2012-13

70%

Diploma in Electrical Engg

Govt. Polytechnic, Vijayawada

2009 – 12

67%

S.S.C

VSV High School

2008 – 09

89.6%

PROJECT EXPERIENCE:

Six months Industrial Training in T.V.L Electricals, Vijayawada (nov 2011 to april 2012)

MECHANICAL TECHNICIAN EXPERIENCE IN 6 YEARS:

WORKING ACTIVITIES:

Work Experience in .Turbine rotarys and pumps and valves.

Knowledge and experience on mechanical job and tools

Casing bolt removal and installation

Hands on experience on assembling and disassembling

GULF EXPERIENCE:

Project Name: QATAR CHEMICAL COMPANY (QATAR)

Project Site : Compressors and pumps

Work : overhauling the compressors

Period : 60 Days (FEB 2020-APRIL 2020)

Site Attend as shutdowns jobs, overhauling and errection plants

1 . Project Name: DR.NTTPS IBRAHIMPATNAM (VIJAYAWADA)

Project Site : 500MW

Work : Overhauling works for STG

Period : 45 DAYS

2 . Project Name: TNEB THERMALPOWER STATION,TUTICORAN (CHENNAI)

Project Site : 2*80MW

Work : Erection work for STG

Period : 6 months

3 . Project Name: K.T.P.S

Project Site : 500MW

Work : overhauling (STG)

Period : 45 Days

4 . Project Name: ULTRA TECH CEMENT PLANT TADIPATRI

Project Site : 2*25MW

Work : full steam turbine overhauling

Period : 30Days

5. Project Name: RTPP (KADAPA)

Project Site : Boiler valves

Work : overhauling the boiler valves

Period : 20Days

6. Project Name: DR.NTTPS VIJAYAWADA

Project Site : 210 MW

Work : Major overhauling STG

Period : 20 Days

7. Project Name: JINDAL STEEL PLANT (RAYAGADA)

Project Site : 35 MW

Work : overhauling the STG

Period : 30 Days

8 . Project Name: INDORAMA SYNTHATIC PVT LTD (NAGPUR)

Project Site : 25 MW

Work : Major overhauling

Period : 28 Days

9 . Project Name: CSTPS (CHANDRAPUR)

Project Site : 2*500 MW

Work : Erection works for STG

Period : 1 year

10. Project Name: AMBUJA CEMENTS LIMITED (BATAPARA) C.G

Project Site : 25 MW

Work : Overhauling the STG

Period : 30 Days

11. Project Name: NCC Power Plant (Nellore)

Project Site : 2*660 MW

Work : Erection work for STG

Period : 6 Months

12. Project Name: SRI DAMODHARAM SANJEEVAIAH THERMAL PLANT(NELLORE)

Project Site : 800 MW

Work : Overhauling the STG

Period : 30 Days

13. Project Name: KORBA SUPER THERMAL POWERPLANT (C.G)

Project Site : 200MW

Work : major overhauling

Period : 35 Days

14. Project Name: RAJARAM SUGAR POWER PLANT (KOHLAPUR)

Project Site : 26 MW

Work : Generator overhauling

Period : 15 Days

NATURE OF WORKS:

Steam Turbines,Generator, Gearbox, boiler valves

PERSONAL PROFILE:

NAME :PARUPALLI KIRAN KUMAR

FATHER’S NAME : P.SIMHACHAAM

DATE OF BIRTH : 03-02-1994

NATIONALITY : INDIAN

RELIGION : HINDU

LANGUGES KNOWN : TELUGU, HINDI, AND ENGLISH

PASSPORT NUMBER : N1227991

PASSPORT EXPIRY DATE : 12-07-2025

DECLARATION:

I hereby declare that all the above furnished details are true & correct to the best of my knowledge.

Date:

Place:

(P.Kiran kumar)



Contact this candidate