PRATAP KUMAR BISWAL
E-Mail: *******************@*****.*** Phone: 701-***-****
E-Mail: ********************@*****.*** what app :897*******
Industry preference: refinery and Power Plant
Piping Engineer – piping and equipment,fabrication
Erection & Hydrotesting
14Years of Experience
PROFILE SUMMARY
Gained overall experience in refinery and power with hands-on experience in:
oFuel Oil System Piping: HFO & LDO Tank, coal Handling System-Piping, Compressor Piping & DG Piping; erection of piping work as per GA drawing and P& ID relative equipment
Knowledge in: p& ID,GA, Isomatric drawing and ASTM, ASME code B31.3
Pipeline Fabrication,Erection and hydro testing : UG Piping, AG Piping &Unit Piping
oWelding Inspection: weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment
otank: fabrication, erection and commissioning.
o
oBelt convyore:erection and commissioning.
oWelding Inspection: weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment
Skilled in bag house, Esp, bucket elevator, belt conveyors, bag filter, hag equipment, blowers, vibrating screen &vibro feeders, belt conveyors, raw mill fan, bucket elevator, chain conveyors, belt conveyors, raw mill ducting erection and so on
Expertise in project coordination, planning & execution including the project SOW preparation, manpower management, contractor coordination including generation of monthly progress reports
CORE COMPETENCIES
Project Planning & Execution Erection, Fabrication& Commissioning Shutdown Planning
Site & Risk Management Management Reporting /Meetings Resource Management
Quality & Safety Management Client Interaction & Coordination Team Training & Development
PROJECT DETAILS
Organization:Puzzlona machinery ltd,Hyderabad.
Designation: senior engineer.
Duration: april ‘19 to may’20
Nature of work
Successfully executed the
fabricatin erection, alignment & commissioning of:
oJaw crusher and sander 100
oCone, vsi
oVibrating screen, belt conveyor
oEOT Crane with Tekfrens Pvt. Ltd.
Project: Reliance refinery, jamnager
Organization: Gannon dunkerely co ltd.
Designation: senior engineer.
Duration: Feb’15 to ’nov ‘18
Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts
Drove the welding inspection, weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment
Job and resource planning as well as material and manpower handling at site.
Analyzing the piping support design as per approved drawing and fabricating same.
Played a key role in planning & scheduling of project execution, meeting client requirements, necessary documentations for any modification & rectification jobs during erection & commissioning work including inspection
Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts
Recommending mdifactions in the piping installations as per the field conditions and modifying the same in field in accordance with revised drawing.
Identifying and continuous monitoring of the critical paths and bottlenecks in the projects so as to achive set monthly targets.
Recommending mdifactions in the piping installations as per the field conditions and modifying the same in field in accordance with revised drawing.
Project: GUJARAT REFINEREY,IOCL
Organization: Gannon dunkerely co ltd.
Designation : Assistant Engineer
Duration:AUG’13 to FAB’15
Highlights:
Planned and executed project activities such as SOW preparation, manpower management, contractor coordination including generation of monthly progress reports
Played a key role in executing key projects such aserection, installation & commissioning of:
oSuccessfully executed the fabrication and erection of UG piping, AG piping all job as per planned schedule& availability of material & erection fronts
oJob and resource planning as well as material and manpower handling at site.
Project: 660x5 MW, Adani Power Ltd., Mundra, Gujarat (Client: Sepco III)
Organization: Gannon dunkerely co. ltd
Designation:Assistant Engineer
Duration:Aug’12 to AUG’13
Highlights:
Successfully executed:
oFuel oil system piping including HFO & LDO Tank, Ash Handling System Piping, Fly Ash Handling System, Compressor Piping & DG Piping as per erection
oFabrication of HFO & LDO tank and erection of piping work as per GA drawing and P& ID relative equipment sequence by taking the material requisitions from the client Sepco III
oTest such as vacuum, hydro and pneumatic test as per design parameter of drawing
oSubmission of test report to the client
oTotal coal handling system such as erection of stacker reclaimer, belt conveyor, crusher house, driver house, relative all equipment & water pipeline
Project: Reliance refinery Ltd., Moti Khavdi, Jamnagar
Organization: Gannon dunkerely co .ltd
Designation: jr. Engineer
Duration: may’07 to aug’12
Highlights:
Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts
Drove the welding inspection, weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment
Job and resource planning as well as material and manpower handling at site.
Analyzing the piping support design as per approved drawing and fabricating same.
Played a key role in planning & scheduling of project execution, meeting client requirements, necessary documentations for any modification & rectification jobs during erection & commissioning work including inspection
Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts
Recommending mdifactions in the piping installations as per the field conditions and modifying the same in field in accordance with revised drawing.
Identifying and continuous monitoring of the critical paths and bottlenecks in the projects so as to achive set monthly targets.
Prject: Vedanta aluminium ltd,kalahandi,Orissa
Organization : S R BROTHER
Designation : Engineer
Duration:Dec’05 to March’07
Successfully executed the fabrication and erection of UG piping, AG piping all job as per planned schedule& availability of material & erection fronts
Job and resource planning as well as material and manpower handling at site.
ACADEMIC DETAILS
2002 Diploma in Mechanical Engineering from Nilachal Polytechnic Bhubaneswar
CERTIFICATION
AutoCAD from Debta Infotech
PERSONAL DETAILS
Date of Birth: 2nd June 1984
Languages: English, Hindi & Oriya
Address: Ballari, Toranagllu