Post Job Free

Resume

Sign in

Engineer Piping

Location:
Vasant Nagar, Karnataka, India
Salary:
5.5 lack per annum
Posted:
August 04, 2020

Contact this candidate

Resume:

PRATAP KUMAR BISWAL

E-Mail: ade2ky@r.postjobfree.com Phone: 701-***-****

E-Mail: ade2ky@r.postjobfree.com what app :897*******

Industry preference: refinery and Power Plant

Piping Engineer – piping and equipment,fabrication

Erection & Hydrotesting

14Years of Experience

PROFILE SUMMARY

Gained overall experience in refinery and power with hands-on experience in:

oFuel Oil System Piping: HFO & LDO Tank, coal Handling System-Piping, Compressor Piping & DG Piping; erection of piping work as per GA drawing and P& ID relative equipment

Knowledge in: p& ID,GA, Isomatric drawing and ASTM, ASME code B31.3

Pipeline Fabrication,Erection and hydro testing : UG Piping, AG Piping &Unit Piping

oWelding Inspection: weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment

otank: fabrication, erection and commissioning.

o

oBelt convyore:erection and commissioning.

oWelding Inspection: weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment

Skilled in bag house, Esp, bucket elevator, belt conveyors, bag filter, hag equipment, blowers, vibrating screen &vibro feeders, belt conveyors, raw mill fan, bucket elevator, chain conveyors, belt conveyors, raw mill ducting erection and so on

Expertise in project coordination, planning & execution including the project SOW preparation, manpower management, contractor coordination including generation of monthly progress reports

CORE COMPETENCIES

Project Planning & Execution Erection, Fabrication& Commissioning Shutdown Planning

Site & Risk Management Management Reporting /Meetings Resource Management

Quality & Safety Management Client Interaction & Coordination Team Training & Development

PROJECT DETAILS

Organization:Puzzlona machinery ltd,Hyderabad.

Designation: senior engineer.

Duration: april ‘19 to may’20

Nature of work

Successfully executed the

fabricatin erection, alignment & commissioning of:

oJaw crusher and sander 100

oCone, vsi

oVibrating screen, belt conveyor

oEOT Crane with Tekfrens Pvt. Ltd.

Project: Reliance refinery, jamnager

Organization: Gannon dunkerely co ltd.

Designation: senior engineer.

Duration: Feb’15 to ’nov ‘18

Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts

Drove the welding inspection, weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment

Job and resource planning as well as material and manpower handling at site.

Analyzing the piping support design as per approved drawing and fabricating same.

Played a key role in planning & scheduling of project execution, meeting client requirements, necessary documentations for any modification & rectification jobs during erection & commissioning work including inspection

Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts

Recommending mdifactions in the piping installations as per the field conditions and modifying the same in field in accordance with revised drawing.

Identifying and continuous monitoring of the critical paths and bottlenecks in the projects so as to achive set monthly targets.

Recommending mdifactions in the piping installations as per the field conditions and modifying the same in field in accordance with revised drawing.

Project: GUJARAT REFINEREY,IOCL

Organization: Gannon dunkerely co ltd.

Designation : Assistant Engineer

Duration:AUG’13 to FAB’15

Highlights:

Planned and executed project activities such as SOW preparation, manpower management, contractor coordination including generation of monthly progress reports

Played a key role in executing key projects such aserection, installation & commissioning of:

oSuccessfully executed the fabrication and erection of UG piping, AG piping all job as per planned schedule& availability of material & erection fronts

oJob and resource planning as well as material and manpower handling at site.

Project: 660x5 MW, Adani Power Ltd., Mundra, Gujarat (Client: Sepco III)

Organization: Gannon dunkerely co. ltd

Designation:Assistant Engineer

Duration:Aug’12 to AUG’13

Highlights:

Successfully executed:

oFuel oil system piping including HFO & LDO Tank, Ash Handling System Piping, Fly Ash Handling System, Compressor Piping & DG Piping as per erection

oFabrication of HFO & LDO tank and erection of piping work as per GA drawing and P& ID relative equipment sequence by taking the material requisitions from the client Sepco III

oTest such as vacuum, hydro and pneumatic test as per design parameter of drawing

oSubmission of test report to the client

oTotal coal handling system such as erection of stacker reclaimer, belt conveyor, crusher house, driver house, relative all equipment & water pipeline

Project: Reliance refinery Ltd., Moti Khavdi, Jamnagar

Organization: Gannon dunkerely co .ltd

Designation: jr. Engineer

Duration: may’07 to aug’12

Highlights:

Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts

Drove the welding inspection, weld visual inspection, electrode, filler wire and pre-heat & post-heat treatment

Job and resource planning as well as material and manpower handling at site.

Analyzing the piping support design as per approved drawing and fabricating same.

Played a key role in planning & scheduling of project execution, meeting client requirements, necessary documentations for any modification & rectification jobs during erection & commissioning work including inspection

Successfully executed the fabrication and erection of UG piping, AG piping & unit piping all job as per planned schedule& availability of material & erection fronts

Recommending mdifactions in the piping installations as per the field conditions and modifying the same in field in accordance with revised drawing.

Identifying and continuous monitoring of the critical paths and bottlenecks in the projects so as to achive set monthly targets.

Prject: Vedanta aluminium ltd,kalahandi,Orissa

Organization : S R BROTHER

Designation : Engineer

Duration:Dec’05 to March’07

Successfully executed the fabrication and erection of UG piping, AG piping all job as per planned schedule& availability of material & erection fronts

Job and resource planning as well as material and manpower handling at site.

ACADEMIC DETAILS

2002 Diploma in Mechanical Engineering from Nilachal Polytechnic Bhubaneswar

CERTIFICATION

AutoCAD from Debta Infotech

PERSONAL DETAILS

Date of Birth: 2nd June 1984

Languages: English, Hindi & Oriya

Address: Ballari, Toranagllu



Contact this candidate