CURRICULUM VITAE

Last Name : SALEEM

First name : ADNAN

Telephone No. : +974-******** / 44815286 (Home)

E-mail : ada75i@r.postjobfree.com

Nationality : Pakistani

Qatar ID No : 283********

UPDA Reg. No : 23523

Passport No : CF5752883

Visa Status : Transferable & NOC available

NOC Available : Yes

Date of Birth : 23rd January 1983

Marital status : Married

Children : 02

Languages : English & Urdu

Total no of years Exp: 15 Years

Education :

S. No

Qualification

Year of Passing

1

Bachelors of Civil Engineering

2003

2

Higher Secondary Certificate (H.S.C)

1999

3

Secondary School Certificate (S.S.C)

1997

Trainings Attended: Many technical and Project Managers training (SIEMENS W.L.L).

Attended Various Technical Seminars arranged for the project.

Last Position : Civil Site Manager

Professional Career:

December 2011 –Till 07 January 2019

Position : Civil Site Manager

Company: SIEMENS WLL

Country: Qatar

Project Worked: (Project Cost – 500 Mn $)

GTC/735C/2015 – Qatar Power Transmission System Expansion Substations – Phase 13 (66/11kV Murrah South & 66/11kV- New Assiri Substations)

GTC/488C/2012 – Qatar Power Transmission System Expansion Substations – Phase 11 (66/11kV Doha Industrial-G, 66/11kV Murrah North, 132/11kV Al Wukair-1, 220/66/11kV New Doha A, 220/132/11 Al Thumama Substations)

GTC/679/2014 – Phase 11 – Establishment of New 132/11kV Substations (Al-Bahya Substation)

GTC/371B&D/2010 – Qatar Power Transmission System Expansion Substations – Phase 10 (66/11kV Bin Mahmood,66/11kV Umm Al Ghahab and 132/66/11kV Al Kheesa West Substations)

Role and Responsibilities:

Responsible for construction and execution of 220/132/66/11 kV sub-stations (including foundations for heavy equipment like IDT transformers, 66 KV Gas Insulated Switchgears, Underground Oil/Water Tank using shoring, dewatering system using latest Techniques) and other Civil Activities.

Co-ordination with sub-contractors, in order to make sure that all activities are in compliance with SIEMENS and Client (KAHRAMAA).

Co-ordination and follow up with Design team to ensure all design and drawings are timely approved from Client/Consultant and are issued to Sub-contractor well in time.

Responsible for acquiring excavation, foundation and full building permit from Municipality and their inspections to site whenever necessary.

Responsible for all civil co-ordination required for Firefighting, MEP, Small Lightning and power, Transformer erection, testing and commissioning and other Electrical requirements.

Responsible for Red marked (As Built) drawings.

Responsible for Completion of all Civil snags list.

Aug 2010– November 2011

Position: Construction Engineer Civil

Company: ZEL (Zishan Engineers Limited)

Country: Pakistan

Project Worked: (Project Cost – 20 Mn $)

Substations in QICT (Qasim International Container Terminal) Port Qasim Karachi.

Role and Responsibilities:

Supervision of All civil Works including Raft/Isolated foundations, Generator foundations, Transformer rooms, Cable rooms, Electrical pits, trenches and other constructional activities.

Coordination with Client to incorporate contract specifications on site.

Weekly meeting with client over progress pace and quality issues.

Preparation of Bidding Documents/BOQ.

Preparation of Bid Comparison for different contractors on basis of Cost, Professional experience and resources.

Preparation of Bid Evaluation for Short listed contractors.

Ensurance of civil works execution with safety, quality, and up to planned progress pace as per Client Requirement.

Responsible for checking/Arranging the required resources for construction.

Responsible for completion of all works as per contract including finishing items.

Provide guidance/technical support to field staff, follow up schedule and ensure availability of drawings, manpower and equipment.

Coordinating all construction activities on site with different disciplines and parties.

Coordination with Design office for any changes if required on site and preparation of As-Built drawings.

Ensure availability of AFC drawings and approval of civil work construction materials.

Coordination in preparation of Redline drawings and development of AS-BUILT drawings through it.

July 2009 - July 2010

Position: Civil Engineer

Company: ABIS (Abdullah Al Barak Industrial Services Limited)

Country: Saudia Arabia

Project Worked: (Project Cost – 150 Mn $)

Construction of Utility Building in SAUDI KAYAN, Al Jubail City.

Role and Responsibilities:

Supervision of All civil Works including piling, Pile cap, Blast proof wall and other constructional activities.

Ensurance of civil works execution with safety, quality, and up to planned progress pace as per FLUOR Arabia /SAUDI KAYAN requirement.

Responsible for checking the resources required for construction.

Responsible for completion of all works as per contract including finishing items.

Provide guidance/technical support to field staff, follow up schedule and ensure availability of drawings, manpower and equipment.

Coordinating all construction activities on site with different disciplines and parties.

Ensure availability of IFC drawings and approval of civil work construction materials.

Prepare weekly construction activity schedule.

Initiate RFI and coordinate with inspectors.

Follow up concrete delivery and other material. Ensure preparation of As Built drawings.

Coordinate with third party inspection agency.

Assure and control quality.

Ensure availability of sufficient manpower and construction equipment.

Prepare periodical report and immediate reporting about critical issues.

Oct 2007 - June 2009

Position: Project Civil Engineer

Company: EVTL (Engro Vopak Terminals Limited)

Country: Pakistan

Project Worked: (Project Cost – 35 Mn $)

Construction of Ethylene Storage tank and Handling facility Project, Port Qasim, Karachi.

Role and Responsibilities:

Supervision of All civil Works including piling, Pile cap, Process area foundations, Roads, Dyke wall, pipe sleepers,Culverts,backfilling,Switch gear room, Generator and transformer Room work.

Ensurance of civil works execution with safety, quality, and up to planned progress pace.

Documentation related to all civil activities of project as well as of base plant.

Correspondence with main contractor (CNCEC-China) and subcons regarding progress and to implement checks to catch-up desired quality and progress pace.

Setting out technical terms and conditions with contractor as well as supervision, monitoring of construction quality/progress regarding base plant maintenance and new civil works.

June 2005 - October 2007

Position: Site Engineer

Company: Mobilink (A Telecommunication Company)

Country: Pakistan

Role and Responsibilities:

Supervision of Macro, Micro, MBTS and BSC Sites Activities i.e. Concreting, Checking of Steel, Tower Erection, Power Connections and Supervision of other activities till RFI (Ready for Installation).

Doing the Acquisition Visits for Macro, Micro and BSC Sites, Selection of locations considering favorable conditions for Build out and Preparation of Annexure for Build out activities (approximately 500 sites visited).

Build out and Acquisition of sites for VI-MAX project.

August 2004 - June 2005

Position: Site Engineer

Company: A.A Associates (Consultant)

Country: Pakistan

Role and Responsibilities:

Checking of reinforcement, formwork, water cement Ratio, concreting, material quality, finishing items and makes it possible to meet drawings and specified standards.

Observe work standards as well as progress pace so that project can be complete in client’s specified time period.

Supervision of Pile work (Drift Pile / Rotary Pile).

Resolve any uncertain problematic condition on site.

February 2004 - July 2004

Position: Site Engineer

Company: Consultec International (Consultant)

Country: Pakistan

Project Worked:

Village Restaurant, Rehabilitation Project, Karachi.

Role and Responsibilities:

Checking of reinforcement, formwork, water cement Ratio, concreting, material quality, finishing items and makes it possible to meet drawings and specified standards.

Observe work standards as well as progress pace so that project can be complete in client’s specified time period.

Supervision of Pile work (Drift Pile / Rotary Pile).

Resolve any uncertain problematic condition on site.



Contact this candidate