INSTRUMENT AND ELECTRICAL SUPERVISOR

Graduate Diploma: in June 2009- Electronic Applied University Degree Educational Qualification: Communication in June 1993. Education/Qualifications:

June 2003: Baccalaureate Electronic

June 2009: Electronic Applied University Degree (DEUA).

( Very good grade)

Training:

permit work course and Safety Inductions.

Career Summary:

Over 12 years’ experience in Instrumentation and Control in Oil filed projects, LNG (Gas plant), maintenance, plant construction, Commissioning & Start-up assistance. Calibration & repairs of various pneumatic and electronic field Instruments, Loop checks & Function test. Able to read all applicable drawings including P&ID, Loop Sheets, Cable schedule, JB wiring Instrument Location & Instrument Hookup drawings, Instrument data sheets. And electrical construction.

Responsibilities:

- Maintaining all safety aspects both at site and offices as per company HSE policy

- Knowledge for safe use of all tools and test equipment commonly used for industrial electrical installations.

- follow and fill up the daily inspection, according with quality team

- Coordinate with clients and carrying timely inspection of construction activities with Client

- Preparation of documents from project data base, daily job planning, coordinate with sub-contractors, client representative and equipment vendor.

- Pre-inspection, Installation inspection, Final inspection

- responsible for witnessing combined instrument loop check, commissioning at all instrument

- Commissioning of Fire gas detectors and smoke detector Full Name: AMARI Rabah

Family Status: Married, 2 child

Address: Cedex 03 bp159 Taregregt Ait Smail -

Bejaia

Mobile : +213-***-***-*** & 077*-***-***

E-mail : *************@*****.** /

*************@*****.***

Passport: to 12/09/2027

- Assist of calibration of instruments PG TT LT PT...

- Insulation Resistance test, continuity of power, control & Instrument cables before pulling and after installation (Mugger/ hi put)

- Supervising and testing the installation

- Cable tray supervision

- Dielectric test (hi put)

- Inspection of the carcass paint condition

- inspection Auxiliary transformers

- Inspection auxiliaries’ cabinets

- Inspection auxiliaries

- Hit tracing inspections

- Main transformer inspection

- Electrical connection test, and processes connection test

- Fire and gas detectors inspections

- Good use for P&ID plan and instrument HOOK UP details and isometric plan

- Finally, because I believe that improvement is better than perfection. PROFESSIONAL EXPERIENCE:

1)-Employer : Cevielec spa

Client : Tecnimont (TCM)/ project ZCINA-Hassi messaoud Designation : electrical and instrument supervisor From : 13/06/2021 to this day

JOB RESPONSIBILITIES:

Installation cable tray junction box instrument, pulling main cable and branch cable. Insulation Resistance test, continuity of power, control & Instrument cables before pulling Installation panels in LTI room and sub-station

Installation tubing for instrument, valves

2)-Employer : JGC

Client : JGC Corporation project south satellite (Revamping project) Designation : instrument supervisor (Construction & pré commissioning) From : 06/10/2020 to 05/04/2021

JOB RESPONSIBILITIES:

-Prepare work permit, vehicle entry permit as per requirement., daily reports manager

- Involve in the tri-party walk down with the client.

-Coordinate with clients and carrying timely inspection of construction activities with Client

-inspection & Control on site,. Doing inspection of Equipment & materials, with the present of Client as per the specification & Standards also require all certificates

- Loop check & commissioning of field Instruments. Involved in continuity checking, simulation & pre commissioning Trouble shooting of new loop and Modification of internal panel activity. wiring.

3)- Employer : Entrepose

Client : JGC CORPORATION Project Upside North

Designation : Instrument and Electrical supervisor From : 23 /01/2019 at 25 /09/2020

JOB RESPONSIBILITIES:

- Prepare permit to work, vehicle entry permit as per requirement.

- Maintaining all safety aspects both at site and offices as per company HSE policy

- Knowledge for safe use of all tools and test equipment commonly used for industrial electrical installations.

- Supervises all construction work

- Responsibilities included construction activities like cable & gladding, Cable tray work, Impulse tubing, Marshalling rack & JB termination. 4) Employer : ABB / SARPI

Client : SONATRACH Project (time system counting)

Designation : Electrical and instrument supervisor construction & commissioning

From : 17/02/2016 at 31/02/2018

JOB RESPONSIBLITIES:

- Supervises all construction work in project time system counting at the National Gas Distribution Center (CNDG).

- Safety preparation (job Distribution, Safety talk, Tool box Talk, Permit Authorization etc.).

-inspection & Control on site. Doing inspection of Equipment & materials, with the present of Client as per the specification & Standards also require all certificates

- Testing, calibration and maintenance during pre-start-up of the system on the temperature, pressure, flow & level transmitter instrument/device using hart communicator.

-Co- operation with operation, preparing equipment for maintenance. Lab calibration of Various electronic & Pneumatic field and panel instruments 5) Employer : SARPI

Client : SONATRACH / BP Project renovation train 03 (In Amenas) Designation : Instrument supervisor

From : 20/09/2014 to 31/01/2016

JOB RESPONSIBLITIES:

- Supervises all construction work instrument.

- Responsibilities included construction activities like cable & gladding, Cable tray work, Impulse tubing, Marshalling rack & JB termination. 6) Employer : SARPI /ABB

Client : ANADARCO Project collection desaire El Merk Designation : Instrument technician

From : 05/01/2013 to 01/08/2014

JOB RESPONSIBLITIES:

-Co- operation with operation, preparing equipment for maintenance.

-Hot and cold loop checks and functional test of field instruments

- Loop check & commissioning of field Instruments. Involved in continuity checking, simulation & pre commissioning Trouble shooting of new loop and Modification of internal panel activity. wiring.

7) Employer : SARPI /ABB

Client : Saipem MLE project

Designation : Instrument Forman

From : 26/11/2011 to 20/12/2012

JOB RESPONSIBLITIES:

-Installation cable tray junction box instrument, pulling main cable and branch cable.

-Insulation Resistance test, continuity of power, control & Instrument cables before pulling

-Installation panels in LTI room and sub-station

-Installation tubing for instrument, valves

8) Employer : SARL MGCP

Client : Saipem MLE project

Designation : technician

From : 10/2010 to 10/ 2011.

JOB RESPONSIBLITIES:

Termination of JB, panels and instrument

Installation of instruments, cable termination

Other:

● Good at doing MS-Office programs Microsoft Excel, Word, Outlook, Power Point, Windows., Internet,

● Enjoy all kinds of sports such as soccer, basketball, swimming, running, etc. References

Available on request

Drive license

Travel

hard worker

Mobility international

various troubles shooting to Pressure transmitter, D.P.T Flow transmitters, Temperature transmitter, Level transmitter, Control valve, Switches and etc.

Repair and overhauling of Control valves and positioner calibration and stock check.

Loop check & commissioning of field Instruments. Involved in continuity checking, simulation & pre commissioning Trouble shooting of new loop and Modification of internal panel activity. wiring.