Anish Vettath Thankachan
Address: Abu Hamour near Salwa Road, Building No. 35, Street No. 449, Zone 56, Doha, Qatar. Mobile: +974******** (Qatar); Email: ************@*****.***; ************@*****.*** Electrical Engineer - Project Management/Consultant & Construction A highly capable, result-driven, & achievement resource works as an Electrical Engineer & offers 13+ years of experience, and international exposure in Qatar, in the construction field, with a proven track record to leverage domain knowledge & technical expertise in project engineering through all stages of the project lifecycle, drive project planning, scheduling, & commission MEP engineering, apply industry best practices to accomplish operational excellence for project delivery within timelines, while operating in complex & challenging multi-cultural global environment. Professional Experience
ERGA Qatar LLC, Doha, Qatar.
Electrical Engineer (Consultant) (Nov 2020 – Till Date) Responsibilities:
• Reported to the Sr. Electrical Engineer, Carried out material/work inspections & ensured all electrical installations complied with project specifications, approved drawings & applicable international standards.
• Review of Shop drawings, Pre-qualification/Material submittals, Method statements/ ITPS, As-built drawings & operation & maintenance (O & M) manuals.
• Coordinated with the contractor to control work activities in accordance with approved drawing, method of statement, inspection & project specification requirements.
• Supervised work as per project specifications & complied with Kahramaa, MOI, NFPA, QCS & BS regulations during the installation, testing & commissioning phases.
• Followed up on corrective & preventive action for NCRs/SORs issued & verified the effectiveness of the same.
• Studied & analyzed design/ sketch plan which included materials breakdown given by the client to execute the project.
• Prepared & updated daily reports, inspection logs, & journals to document construction activities.
• Participated in weekly meetings with the project management team & monthly with the project planning team in reference to the baseline program.
Achievements:
• Qatar's Umm Al Seneem Park has officially been awarded the Guinness World Records title for the longest air- conditioned pedestrian and jogging path in an open park, as the Ministry of Municipality inaugurated on November 1, 2022. The 1,143-metre path is the fifth project of the Public Works Authority (Ashghal) to obtain a Guinness World Record.
• Solar Grid System Installation in Al Gharafa (234 KWp), Umm Al Seneem (410 KWp) & Rawdat Al Hamama (251 KWp) Public Parks.
ECG Engineering Consultants Group WLL, Doha, Qatar. Electrical Engineer (Consultant) (Nov 2017 – Oct 2020) 2 Page
Achievements:
• Essayed a success story to carry out & submit 1515 nos. inspections, testing, & commissioning reports within 1 year in accordance with the gradual progress of the project.
QD-SBG (Qatar Diar – Saudi Binladen Group Co LTD) Construction, Doha, Qatar.
Electrical Engineer (Construction) (Jul 2015 to Oct 2017) Responsibilities:
• Reports directly to the MEP Manager, leads a team of 7, to drive project construction within the company to increase department production and profitability as per corporate goals & set key performance indicators.
• Perform testing and commissioning protocols, and hand over the system to end users.
• Carried out the second fix, final fix, testing and commissioning with consultant (KEO) inspections.
• Prepare Redline drawings as per site installation and with reference to the submitted As-built Drawings.
• Study & improve operation & maintenance (O & M) manuals, and provide training for operators.
• Discuss with managers to resolve critical & time-sensitive electrical issues relating to project construction.
• Mentor & motivate staff, appraise performance, & provide training to maximize work productivity. Achievements:
• For Project: ISF (Internal Security Force) Camp Duhail, Package: CPC 07B; effectively done testing & commissioning for electrical systems, Lighting, Power, Emergency lighting, UPS & Fire-Alarm.
• All Handing-over procedures for the 12 Barrack building have been done in 150 days without any fail as per the planning schedule.
Hamton International Group WLL, Doha, Qatar.
Site Electrical Engineer (Jan 2011- Jun 2015)
Responsibilities as Site Electrical Engineer:
• Reported to the MEP Manager, led a team of 13, in the MEP Projects Department, in ISO 9001:2008 QMS, ISO 14001:2004 EMS, and ISO 18001:2007 certified company, to steer project designs as per specified key performance matrices.
• Provided support to the Engineering & Purchase Department during the preparation of purchase orders, material procurement for construction, & commissioning activities as per project requirements.
• Prepared and submitted Shop drawings, Pre-qualification/Material submittals, Method statements/ ITPS, As-built drawings & operation & maintenance (O & M) manuals for consultant approval.
• Overseen inspection & commissioning programmes & ensured compliance with project specifications, Kahramaa, MOI, NFPA, QCS & BS regulations during the drafting, installation, testing & commissioning phase for electrical systems.
• Submitted Request for Information (RFI) in case of clarifications during engineering and installation proceeds.
• Made presentations & submitted reports to the Project Manager/ Project QA/QC Manager to highlight performance.
• As in charge, evaluated the performance of production work & kept the senior management updated on progress. Achievements:
3 Page
• Created history by setting new performance benchmarks in my entire career to complete & hand over to client Aster Hospital (B+G+2F+P) project, in Doha, Qatar within 475 days.
V-Tech Electro-Mechanical Group, Kerala, India.
Site Electrical Engineer (Oct 2009 - Nov 2010)
Responsibilities:
• Reported to the Resident Engineer, handled site management & interfaced with various divisions such as quantity survey & estimation to complete the project within timelines as per the set key result areas.
• Supervised & assisted in overall site management to properly execute work according to the approved bar chart.
• Assigned tasks to prepare the bill of quantities & issue purchase orders.
• Provided technical assistance to the supervisors and crew.
• Coordinated with the project controls & submitted reports on daily work progress. Key Project Details
1 Consultant Organization
(Qatar)
ERGA Qatar LLC, Doha, Qatar.
Client ASHGHAL - Public Works Authority, Qatar.
Associated Projects • CONSTRUCTION OF THREE (3) PUBLIC PARKS OF AL GHARAFA (51,857.60 SQM), UMM AL SENEEN (129,598.88 SQM) & AL MUNTAZAH (139,501.21 SQM). Main Contractor: Boom Qatar
• Project Value- QAR 245 Million
• CONSTRUCTION OF PUBLIC PARK AT RAWDAT AL HAMAMA (134,216.21 SQM). Main Contractor: Nakheel Qatar
• Project Value- QAR 170 Million
2 Consultant Organization
(Qatar)
Engineering Consultants Group (ECG) WLL, Doha, Qatar. Client ASHGHAL - Public Works Authority, Qatar.
Associated Projects • Design & Built for Modification and additional works of 27 Schools – Package – 1, Main Contractor: Amana Qatar.
• Construction of Health centres at Al Shamal & Al Sadd – Package – 9, Main Contractor: Al Matar Qatar.
• JW Marriott Hotel (3B+G+M+51F) West Bay in Doha, Qatar; Main Contractor: Harinsa Qatar ECISA International Group
• Project Value- QAR 684 Million
• Mixed-used development project (twin towers: 3B+G+M+10F commercial complex & 5-star hotel), Airport Road, Doha, Qatar (Operator- Steigenberger Hotel Group) Main Contractor: Al Jabar Trading & Contracting Doha, Qatar.
• Project Value- QAR 242 Million; Electrical BOQ Value QAR 27 Million 3 Contracting Organization QD-SBG (Qatar Diar–Saudi Binladen Group Co LTD) Construction, Doha, Qatar. 4 Page
(Qatar)
Associated Project • ISF (Internal Security Force) Camp Duhail-Qatar, Package: CPC 07B
• Project Value – QAR 2.5 Billion.
4 Contracting Organization
(Qatar)
Hamton International WLL, Doha-Qatar.
Associated Projects • Bin Samikh Tower/ Melia Doha Hotel (3B+G+UG+M+42 floor); West Bay, Doha, Qatar. Main Contractor: Harinsa Qatar ECISA International Group. Consultant: Arab Consulting Engineers
• Project Value QAR 185 Million; Electrical BOQ Value- QAR 22 Million
• Aster DM Healthcare (Aster Hospital Group) is a 50-bed private hospital along with 3 fully equipped operating theatres (B+G+2F+P) in the old airport area, Doha, Qatar. Main Contractor: Hamton International. Consultant: Dimensions Engineering, Qatar.
• Project Value- QAR 56 Million; Electrical BOQ Value QAR 6 Million
• Reconstruction of EZDAN Hotel; 2B+G+4 floor, Al Gharafa, Qatar. Main Contractor: SEF Construction Pte Ltd. Consultant: MZP Consultancy, Qatar. 5 Organization (India) V-Tech Electro-Mechanical Group, Manadiar Line, Thrissur, Kerala. Associated Projects • Skyline Apartments with 1B+G+M+18 storey tower, East Fort, Thrissur, Kerala
• MIR Realtors Apartments with 2B+G+M+27 storey tower, Kakanad, Cochin, Kerala Profile Highlights
Technical Calibre: Solution-oriented problem solver & analytical thinker with proficiency in LV systems: Installation & Testing of Transformers, Gensets, Low Voltage (LV) Panels, Motor Control Panels (MCC), Sub-Main Distribution Board (SMDB) & Distribution Board (DB); Lighting - Small Power Systems and Solar Systems.
Technological Knowhow: Verifiable track record to installation, testing
& commissioning of ELV systems: Structural Cabling System (Data- Tele/WIFI/IPTV); CCTV system; Audio-Visual System (AV); Building Management System (BMS); Fire Alarm & Voice evacuation system (FA- VA); Nurse-call system; Queue management system & Master clock system. Also, basic knowledge of mechanical systems: Fire-Fighting, Drainage & Plumbing systems & HVAC.
Team Leadership: Visionary, conscientious, with a positive approach to liaising with clients, contractors & vendors for flawless project delivery. Strong work ethic, quickly learns & adopts new trends, tasks, & technology. Dedicated & committed with the skill set to motivate & build a successful team of engineers.
Organizational Exposure: Organisational capability with well-honed relationship-building qualities to engage in stakeholder management; champions people & organization development; communication & interpersonal skills to work in a multi-team environment, plan & control project work, & deliver results within timelines to meet corporate goals. Project Planning & Monitoring: Exceptional conceptual knowledge of LV & ELV engineering principles, deft in preparing & managing projects to deliver turnkey engineering projects. Enforce standards relating to quality, cost efficiency & client specifications. Coordinate project engineering & adhere to quality & safety specifications. Core Competencies
Profit Centre Management
Complete Project Lifecycle
Construction codes & regulation
Cost Reduction & Budgeting
Change Management
Quality Assurance & Control
Regulatory Compliance
Project Conceptualisation
Resource Management
Projects Technical Coordination
Team / People Management
5 Page
Educational Credentials
• Bachelor’s Degree in Technology- Electrical & Electronics Engineering (2005- 2009) from Mahatma Gandhi University (Viswajyothi College of Engineering and Technology) Kottayam, Kerala, India. Certifications/Accreditations/Training
• Certified Electrical Engineer, accredited by UPDA/ MMUP- Ministry of Municipality & Urban Planning, Qatar, Registration No. 16430 (2017).
• Attended a 12-day industrial training programme on transformers & completed a project on an on-load tap changer & control circuit at KEL Ernakulum, Kerala (2009).
Personal Details
Date of Birth
• Permanent Address
• Language
• Computer Literacy
• Nationality
• Passport Details
• Visa Status
• Driving License
: 26th Sep 1987
: Vettath (H), Kannara P.O, Marakkal, Thrissur, Kerala, India - 680652.
: Fluency in English, Hindi, Tamil, Malayalam, & basic skills in Arabic.
: MS Office (Excel, Word, PowerPoint), Aconex, C, C++ & AutoCAD (3D) 2014.
: Indian
: M 6182933; (valid up to 12/07/2025).
: Qatar Resident Visa; Transferable.
: Holding Qatar Driving License.