Talented professional with 3 years leading planning teams and project initiatives for General Dynamics NASSCO planning and scheduling departments. A strong strategic planner, problem solver and leader. Well versed NAVSEA standard items and ale to incorporate those standards into day to day operations to satisfy external customer needs. Have the ability to train staff using existing or creating work instructions as a guideline for repetitive processes. An effective multi-tasker, and the willingness to take on collateral duties.

Possess the organization & leadership skills to follow through & drive closure. Able to convey complex subject matter clearly and engagingly.

Ability to identify and quickly resolve complex issues. Is able to assess risk/challenges/impact and recommend solutions and options. This includes solid root cause analysis, driving corrective action plans to closure, effective engagement, communicating & influencing at all levels. Ability to deal with change, delays & unexpected events.

Planner/Scheduler, 08/2020 to Current

General Dynamics Nassco - San Diego, CA

· · Generated resource loaded Integrated Master Schedules to track Baseline and revised forecasted execution plans to meet government outlined milestones.

· Knowledge of: Government provided Specifications (statement of work), Trade specific blueprint reading and diagrams.

· Stage of Construction (SOC) Manufacturing planning and philosophy

· Planning Software Utilization: Open Plan Professional, Microsoft Project, Excel, Power Point, MacPac Material Management System & LMS (Labor Management System), GD Proprietary Software, Microsoft Office

· Development of detailed plans and schedule to track forecasted risk impacts and integration for

“what if scenarios” (GFE, Supplier Material, GFI)

· Build strategy application during planning process stage by logically linking in 3 Phases (Level 1, Level 2, and Level 3)

· Correction of technical conflicts between Engineering, Materials & Production as a liaison to outline disconnects In communication for hand offs in scope of work

· EVMS Knowledge – Earned Value Management System

· Provide cost and schedule performance reports to the analyst

· Execution / Sustainment Planning

· Lead Planner and trainer

· Revision to Baseline Dates, Progress Updates Integration (Data integration, Weekly meeting), Plan vs. Actual Reports and analysis for mischarging

· Creates production schedules as a means of planning, tracking and coordinating the accomplishment of work to key events and milestones

· Labor Resourcing at the task level rather than a code field

· Work Breakdown Structure detailed by work item then logically linked to associated key events and milestones

· Critical Path analysis, Validation of driving paths and Critical Paths, and Total Float impact reports

· Submission of weekly required reports and Cost Analysis Reports

· Work package maintenance: Validation of actuals, budget disconnects between planning and finance, re-allocation of budget

· Analyzing and reporting performance measurement against the baseline

· Manpower plans and projection: identifying manning over allocation, and mitigation plans to provide a realistic manpower spread.

· Contract Status Report (CSR)

· Creating Proposal Schedules for RFP Submittal

· Work in a dynamic environment planning/maintaining multiple schedules and programs simultaneously

· Perform variance analysis against the program baseline (cost & schedule impact) and participate with the program management team in root cause/corrective action analysis Warehouseman/Transportation Driver, 03/2019 to 08/2020 General Dynamics Nassco - San Diego, CA

· Receiving and processing all GFM, Non Coded, Timsa Material

· Conduct daily inspections for any missing, damaged material before releasing to production

· Palletized and Transported all released material to new construction and Repair

· Coordinated with the load out team onboard and confirmed all material was received and assigned to the proper compartments.

· Transported cables, pipes, and equipment for Soc 5 management; cleared all pallets, crates and reels in all lanes and supported production throughout with any requests.

• Able to manage multiple priorities • Team player • Excellent time management skills • Public Speaking • Data analytics •Strong communication skills to work with multiple organizations onboard • knowledge of Tag out requirements

· English/ Full professional

· Spanish/ Full professional