Post Job Free

Resume

Sign in

Project Manager Civil Engineer

Location:
VasanthaNagar, Karnataka, 560001, India
Posted:
January 22, 2024

Contact this candidate

Resume:

Sign:M.Abdul razak

M.ABDUL RAZAK CURRICULUM VITAE

Chennai

Mobile no: +919*********

E-Mail: ad20pb@r.postjobfree.com

A qualified Civil Engineer Diploma and B.Tech with 19+years experience in civil construction projects Adept in Planning, Execution of construction activities, Monitoring, Projects involving development, contract administration, Involved in various projects such as structural of Hostel buildings, Residential and High rise Building project & infrastructure of Chennai metro project R.C.C works for station building & Dubai Metro Rail Project in Dubai for Road Transport Authority Proficiency in roads

& bridges, channel and infrastructure of pipe laying and Roads Public all utilities, All Cables Service and Protection works. Dedicated in work and trustworthy colleague capable of dealing with constant challenges and leading change. Posses and good communication, interpersonal, technical, organizational skills Sep 2021– Present

Company name : ELITE CONSTRUCTION PVT LTD

Designations : Project Manager – Civil - CHENNAI

July 2019 – August 2021

Company name : TRADE LINK SERVICES & CO L.L.C

Designations : Project Manager – Civil - OMAN

May 2016- May 2019

Company name : GHANTOOT TRANSPORT & GEN. CONT. LLC Designations : Project Engineer – Civil -OMAN

Sep 2012 - March 2016

Company name : SHRIJEE ENGINEERS AND CONTRACTORS

Designations : Project Engineer -Civil -INDIA

June 2007 – Jan 2011

Company name : E.T.A ASCON GROUP L.LC

Designations : Site Engineer – Civil – U.A.E

June 2004 – June 2006

Company name : EAST COAST CONSTRUCTION & INDUSTRIES (E.C.CI) Designations : Site Engineer – Civil – INDIA

EXPERIENCE IN PROJECTS

• Construction on R.C.C Framed Structure

• Execution on structure on site as per Rebar Drawing and Formwork drawing

• Making solution as per site condition

• AUTO CLIMBING SYSTEM FORMWORK for walls and columns and table form for slabs ion high rise building

• Marble, granite and other tile works False ceiling works (Metal, Gypsum Board and GRC finishes)

• Swimming pool waterproofing and other finishing works related to pool and pool deck

• Stainless steel finishes and staircase handrails

• Supervision of Glazed works for external curtain walls and aluminum cladding works

• Well knowledge for all type scaffolding erection and dismantling

• Construction on R.C.C Structure for Pier, Pier cap. Deck slab, Retaining walls

• Earth works & rock fill, Barrier casting, Stone Pitching works

• Electrical cables and public all utilities protections,

• Pipe culverts, Asphalt roads for light & heavy vehicles,

• Blasting the hills and making a asphalt roads

• Break water in sea(5km), Car parking and Sheik kalifa port

• Kerb laying, Intermedian and Round about Making

• Block works, plastering and finishing works & Coordinate with MEP works

• Construction on R.C.C Structure for Pier, Pier cap. Deck slab, Retaining walls

• Construction on R.C.C Framed Structure Asphaltic Roads making

• Execution on structure on site as per Rebar Drawing and Formwork drawing Career Overview

Sign:M.Abdul razak

ELITE CONTRACTORS CHENNAI PVT LTD

Period : Sep 2021-Current

Project : CONSTRUCTION OF RESIDENTIAL FLATS – BLOCK A,B,C- G+18 Designation : Project Manager

Project value : 120 CR

Consultant : CBRE

Client : RWD

Location : Vanagaran -Chennai

Project Description

The Construction Of Proposed Grand Corridor - Residential Multi Storied Building Consisting 356 Unit 3 BHK - 224 No’s & 2 BHK - 132 No’s, A & B - Basement + Silt + 14 Floors C - Basement + Silt + 12 Floors Club House - Basement + Silt + 2 Floor, 370 No’s parking (Basement - 148 / Stilt - 125 / Open Parking - 97) Parallel Car Park - 42nos Club House, Basements Double Levels Parking And 2bhk, 3bhk Flats, Including Podium And Swimming Pool The Blocks A,B,C of G+18 floors Land Area 3.82 Acres, at 60000 sq.m Built up Area each block have 14500 sq.m & podium also including

Duties

As a Project Manager I looking all Blocks structural and fit out vertical structure like column core wall, and Roof slab and retaining wall has to coordinate with Quality technical team consultant and QAQC for getting approval of rebar. Formwork and concrete up to hand over stage to finishing for Tiling and water proofing. Period : July 2019 to Aug 2021

Project : CONSTRUCTION OF 2X20 MVA PRIMARY SUB STATION FOR AL DAKHIKLIYA GOVERNORATE Designation : Project Manager / Coordinator

Project value : 8.75 Million Omr

Consultant : Tebodin & Partner LLC

Client : MAZOON ELECRTICITY COMPANY S.A.O.C

Country : Nizwa – Oman

Project Description

The Construction Of 2x20 MVA Primary Sub Station -1 For Phase -1 At Al Afiya – Wadi Maharam In Muscat Client MZEC S.A.O.C By The Consultant M/S Tebodin & Partner LLC Plot Area 5000 SQM Including Transform Building And Cellular Building, Roads, Sewerage Connection, Cable Pulling Pit And Cable Ducting works

Period : FEB 2018 to JUNE 2019

• Project : CONSTRUCTION OF 3X20 MVA PRIMARY SUB STATION FOR MALL OF OMAN

• Designation : Project Engineer

• Project value : 2.98 Million Omr

• Consultant : Atlas International Engineering Consultant

• Client : Muscat Electricity Distribution Company (S.A.C.O)

• Country : Muscat – Oman

Project Description The Construction Of 3x20 MVA Primary Sub Station -1,Cable laying And jointing For Mall Of Oman On Plot 447 Phase -2 At Ghubrah South Bausher In Muscat Client MEDC S.A.O.C By The Consultant M/S Atlas International Engineering Plot Area 2250 SQM Including Transform Building And Cellular Building, Roads, Sewerage Connection, Cable Pulling Pit And Cable Ducting works Period : May2016 to Jan 2018

Project : SBJ Staff Accommoodation

Designation : Project Engineer

Project value : 5.98 Milloin Omr

Consultant : Keo International Consultant

Client : Saraya Bandar Jissah

Country : Muscat – Oman

Projects Description :

The construction of SBJ Staff Accommodation (The Project) forms a part of the Saraya Bandar Jissah development which is located on the north east coast of Oman. Bandar Jissah is located 25.0km South East of Muscat, 2.0km south of Qantab Village and 4.0km North West of Shangrila's Barr Al Jissah Resort, Oman. The topography of the site is GHANTOOT TRANSPORT & GEN. CONT. LLC – OMAN - May2016 TO JUNE 2019 TRADE LINKS & SERVICES L.L.C - OMAN

Sign:M.Abdul razak

irregular and follows broadly a hill side valley, arranged around an existing Wadi,approximately 150m wide, leading towards the shoreline. The site is located within a sheltered bay where the mountains of Bandar Jissah meet the Gulf of Oman and covers an area of approximately 220 hectares. Saraya Bandar Jissah is a planned gated integrated community comprising of five residential zones, subdivided into 356 individual units, offering a range of residential typologies, two luxury hotels, a Recreation Club, a park and a lagoon within themain valley, Staff Accommodation for the Hotels and a Technical Zone that includes a Sewage Treatment Plant, a Main Irrigation Reservoir and a Primary Substation.

Duties As a PROJECT ENGINEER looking all vertical structure like column core wall, and Roof slab and retaining wall has to coordinate with technical team consultant and QAQC for getting approval of rebar. Formwork and concrete up to hand over stage to finishing for Tiling and water proofing. Designation : Project Engineer

Project -5 : Honey Dew Residential & Commercial Flats Project value : 16 Cores Indian Rupees 1B+G+4 (64 Flats) Consultant & Client : United Consultants (Mr.Alexjacob) & GMB Housing Pvt Ltd Project -4 : Rani Atrs & Teak Wood Factory

Project value : 5.4 Cores Indian Rupees

Consultant & Client : P.S.D – Consultancy, Architects & M/S Rani Arts & Teak Ltd Project -3 : Residential housings Flat 1B+G+5

Project value : 4.85 Cores Indian Rupees

Consultant & Client : MOAD –The madras office for Architects and design & Vishranthi homes and P.V.T LTD Project -2 : S.O.T Commercial Office Building 2B +G+6 Project value : 11.2 Cores Indian Rupees

Consultant & Client : K.S.M Consultant - Architects and design & M.s Shekar & Co – 132 kv Transforms Supplier Work Description : Pilling, Excavation and R.C.C Structure of Raft, walls,column and roof slab, solid block works and plastering, Coordinate with MEP Works and all kind of finishing works. Project – 1 : Chennai Metro Railways

Designation : Project Engineer / Stations

Structure Consultant : CMRL

Client : CCCL

Work Description Supervising and build Beauty World Station, 22 meter deep, and twin bored tunnels about 2000mtrs in length with Herrenknecht Mix shield machine with a finished Dia of 5.8 Meters supported with segmental lining. The complete tunneling process along the 16.6km stretch of the DTL2 isexpected to take about 18 months with 19 TBMs being used concurrently at different locations along the alignment. DTL2 is on track to be completed in 2015. DTL2, which will be fully underground, comprisesstations and one depot to be completed in 2015,at N.E & S.E Sections. Internal, External service roads making around & Diversion portions. Period : Feb 2011 to July 2012

Project : 1B+M+G+2 American School Building

Designation : Site Engineer

Project value : 110 million UAE Dirham’s

Client : M/S King Abdul Aziz

Country : Dubai - UAE

Projects Description : The project comprises construction completion and maintenance of a campus and school premises for the American school Dubai with total construction area of 45105m2, covered walks,stair terrace, area5,869m2 Roof top play areas of 4033m2, consisting class rooms blocks gymnasium block, auditorium block SHRIJEE ENGINEERS AND CONTRACTORS - SEPTEMBER 2012 To May 2016 Projects with AL AHMADIAH AKTOR L.L.C June 2011 to July 2012 Sign:M.Abdul razak

Period : June 2009 to Jan 2011

Designation : Site Engineer

Project : improvement and development of Al Ghayathi and Al Sila of Ruwais Project value : 220 Million UAE Dirham’s

Consultant : M/S Tangram

Client : Western And Regions Municipality

Country : Abudhabi –UAE

Projects Description : The project construction completion of a Asphalt ring roads and internal roads 120km

& asphalt parking for heavy trucks and cars, Break water in between sea around 4km, Car parking and helipad for Sheik kalifa, Break water for port building construction Period : July 2007 to June 2009

Designation : Site Engineer

Project : Development Of Infrastructure Pipes And Roads For Jumeriah Golf Estates Project value : 300 Million UAE Dirham’s

Consultant : M/S Matt Macdonald

Client : M/S Isthimar

Country : Dubai-UAE

Projects Description : The project construction completion of a Asphalt Road work for ring road at jumeriah golf estates,Portable water network (GRE pipe, chambers, Butter fly Valve, wash out, Air Release valve….etc), Irrigation water network (GRP pipe, chambers, Butter fly Valve, wash out, Air Release valve….etc), Foul water system – Vacuum system & gravity lines (HDPE pipes, UPVC pipes regular manhole and vacuum pit…etc) Duties As a SITE ENGINEER looking Site activities of Organizing machines, material and labour arrangements Exaction formation, subbase laying coordinate with technical team consultant and getting approval QA/QC and Site Inspector up to hand over stage to finishing

Period : Feb 2006 to June 2007

Designation : junior Engineer

Project : Road over bridge in ENNORE – KATHHIVAKKAM IN CHENNAI Project value : 12 Cores Indian Rupees

Consultant : NATIONAL HIGHWAYS OF INDIA

Client : M/S PWD- PUBLIC WORKS DEPARMENT

Country : Chennai – india

Period : Apr 2004 to June 2006

Designation : Junior Engineer

Project : 1B+G+M+8 Governments New General Hospital Project value : 54 Cores Indian Rupees

Consultant : M/S NARAYANA RAO

Client : M/S PWD- PUBLIC WORKS DEPARMENT

Country : Chennai - India

Course : D.C.E - Diploma in Civil Engineering - 2004 College : ST. Xavier polytechnic of college

University : DIRECTORATE OF TECHNICAL EDUCATION

Course : B.Tech - Bachelor of Technology in Civil Engineering - 2012 University : Janardan Rai Nagar Rajasthan VidyaPeeth University Udaipur – India Name : Abdul Razak Marital Status : Married

Date of birth : 31 May 1985 Nationality : Indian

Father name : Mohammed Ibrahim Mother Tongue : Tamil Languages know : English, Tamil, Arabic, Malayalam and Hindi Computer skills. Auto cad(subject:2d drawing, 3d modeling), Photoshop: versions., Ms office and all component.& Windows operating system. Like xp,vista,w7and w8. Declaration: I hereby declare that the information furnished above is true to the best of my knowledge. Yours sincerely

Projects with ETA STAR GROUP ASCON ROADS CONSTRUCTION L.L.C July 2007 TO Jan 2011 Projects with EAST COAST CONSTRUCTION & INDUSTRIES (E.C.C.I) Apr 2004 TO June 2007 Education Qualification

Personal Details



Contact this candidate