Project Power Plant

Location:
MP, India
Posted:
April 17, 2017

Contact this candidate

Resume:

ABHISHEK SINGH THAKUR

**************@**********.***

Subject: Resume for perusal.

Dear Sir/Madam,

I am interested in joining and serving your esteemed organization, and submit my resume with professional and personal details (attached herewith), for your kind assessment and consideration.

I shall be too happy to furnish any other details/clarifications that may be required and look forward to hear from you.

Yours Sincerely,

(Abhishek Singh Thakur)

Place: India

Encl: 5 Pages as above.

Abhishek Singh Thakur

Email: **************@**********.*** +91-887*******(India)

981-***-****

Passport No. L3231593

Managerial Assignments in Electrical Projects in Power, Cement and Process Industry

EXECUTIVE SUMMARY

Close to +7 years widespread cross-cultural experience in Project Development, Team Management and Construction.

Demonstrated excellence in planning, execution, management and spearheading of various engineering and technical activities.

An enterprising leader with proven abilities in leading teams towards the achievement of organizational goals and industry best practices.

AREAS OF EXPOSURE

PROJECTS PLANNING & MANAGEMENT

Execution of projects for expansion, modernization, installation & commissioning of plant, machinery and equipments.

Ascertaining the requirement of upgrading machinery and in accordance developing new machines for enhancing productivity.

Ensuring execution of activities / projects within time & budgetary parameters.

Actively involved in planning for materials, developing vendors to obtain timely procurement of materials and equipments to facilitate smooth production process.

Monitoring projects with respect to Cost, Resource Deployment, Time over-runs, Quality Compliance and Manpower planning to ensure timely execution of projects.

Spearheading production activities involving working out requirements and monitoring of overall project for ensuring timely completion.

Coordinating projects, setting up of standards and accountability for strategic utilization, deployment of available resources to achieve the targets etc.

Monitoring the production at sites and review of project schedule, ensuring cost control within targeted budget limits, and cash flow planning etc.

EMPLOYMENT RECITAL

2007 -2008

Ellcon project.Pvt.Ltd

11KV & 33KV R.G.V.V.Y.Project JBP (M.P.) & Railway project (Ujjain-Indore)

Over head line 11KV & 33KV Erection and commissioning work.

Involved in Erection of various sizes of Pole.

laying of HT and LT Conductor & Cable of various sizes

Installation and commissioning of AVB Switch of 11KV & 33KV Grade.

Installation and commissioning of 11KV/.433 KV Transformer

Modification of overhead lines, LT Lines, HT Lines & platform Modification work.

AMBUJA CEMENT, BHATAPARA (May- 2008 to Nov- 2010)

(Electrical Site Engineer) Under Vishal Electrical’s M.P.

Working as project Site in Thermal Power Project & Cement Plant.

looking after job responsibilities like;

Thermal power project of 2 x 15 MW and 1 x33 MW

Installation, Erection & Commissioning of Thermal power plant project (78 MW) & 135 TPH Boiler also works in Coal side scraper & Reclaimed &CHP

Actively involved in erection of all the equipment related to 11KV/6.6KV Switchyard etc.

Facilitated Testing & Commissioning of 2 MVAx06Nos Distribution Transformer (EMCO make).

Actively involved in the following:

Installation, Erection & Commissioning of Thermal power plant project (78 MW) & 135 TPH Boiler also works in Coal side scraper & Reclaimer &CHP

PMCC/MCC (Power & Motor Control Centres), Battery Chargers, Air Conditioning System and others Electrical Equipments as used in Power Plant

Erection, testing & commissioning of NGR

Facilitated Testing & Commissioning of 2 MVAx06Nos Distribution Transformer

Cable is laying & termination from field to panel end & loop checking from field to panel. Erection of cable trays & cable routing

Handled Erection, Testing & Commissioning of HT/LT PCC & MCC.

Completed motor overhauling till 850KW motor, overhauling and checking of HT & LT circuit breakers, coordinated activities in annual maintenance shutdown, trained and supervised 40 technicians in effective maintenance practices.

Prepared Plant Energy Consumption Report and coordinated energy audits for efficient energy consumption by different systems/process.

Earthling of Boiler, ESP, TG Building, Transformer yard

Erection & commissioning of coal handling plant of various Motors such as Dust collector Fan, vibro feeder, flips flop screen Crusher impact or type motor

K.J.S. CEMENT, MAIHER. SATNA (M.P.) (Nov- 2010 to Nov-2011)

(Electrical Site In-Charge)

Working as project Site in Thermal Power Project & Cement Plant (Under Gautam Eng.Co. Satna M.P.)

looking after job responsibilities same like upon;

Arvee Electricals & Engineers Pvt. Ltd. Nov’11 to till date (Construction Field)

INDIA

I.E.P.L., Nagpur, Maharashtra (NOVMBER-2011 TO APRIL-2013)

-Responsibly executed overall Erection activities for Clint McNally Bharat Engineering Limited.

-Working as project Site in Thermal Power Project 1X270 MW Ideal Energy Project Ltd. Bela Nagpur Maharashtra.

-Erection, Testing & Commissioning of Electrical Equipment.

-Overall co-ordination and control as SITE In charge.

-Hindustan Zink Ltd. Pantnagar, Uttarakhand..(April-2013 to Feb-2014 date)

Working as project Site in Double Circuit Transmission Line & Substation Package Projects 132 kv Under Hindustan Zink Ltd. Pantnagar, Uttarakhand..

Erection, Testing & Commissioning of 132 Kv Transmission Line.

ACC Gagal Cement Works Barmana, Himachal Pradesh (Feb-2014 to Till Date)

Erection, Testing & Commissioning of 20 TPH NEW PET COKE MILL project Electrical packages.

SALARY:

C.T.C: 5.5 Lacks.

Expected Salary: 6.5 Lacks.

Minimum Time required joining: One month after appointment latter.

Software Skills:

Operating System :

Windows 98 / 2000 / XP / XP-Professional/Windows 7.

Microsoft Office :

MS-Excel, MS-Word, etc.

Educational qualifications:

Diploma in Electrical Engineering from, Government polytechnic college Mandla (M.P.) in 2003 with 63.14 % Inveracity –R.G.P.V.V.BHOPAL (M.P.)

Personal Profile:

Name

Abhishek singh thakur

Father's Name

Mr. Santosh singh thakur

Date of Birth

15-06-1984.

Nationality

Indian.

Permanent Address

H.No.316, PO-Garha, Dist-Jabalpur, Madhya pradesh (Pin-482003)

Phone

+91-889*******/887-***-****

e-mail

**************@**************.***

Languages Known

English, Hindi.

Hobbies

Watching Movies, Listening to Music.

Personal Strengths:

Comprehensive problem solving abilities, excellent verbal and written communication skills,

Ability to lead and work with people from multi-cultural backgrounds, and openness to learn.

Quick learner and excellent team player having ability to meet deadlines and work under pressure

Easy and Quick adaptability to new work environments.

Declaration:

I here by declare that the above written particulars are true to the best of my knowledge and belief.

Place: India

Date: 6.04.2015 (ABHISHEK SINGH THAKUR)



Contact this candidate