OBJECTIVE

Seeking the position for Rigging Supervisor

SUMMARY

Creative and motivated rigging supervisor with several experiences in supervision, coordination, monitoring for the activities of the workers engage on rigging, hoisting and lifting and inspection of lifting gears. Review, evaluate and demonstrate heavy lift plan. Involved on inspection of mobile equipment and non-moving equipment.

PERSONAL DATA

AGE : 41 Yrs. Old

BIRTHDATE : 19 NOVEMBER 1974

STATUS : MARRIED

LANGUAGE : ENGLISH, FILIPINO

SKILL : AUTOCAD, MS WORD, MS EXCEL, MS PPT

WORK EXPERIENCE

RIGGING SUPERVISOR

COMPANY : TECHNIP SAUDI ARABIA LTD.

CLIENT : KEMYA / EXXON MOBIL

PROJECT : SAUDI ELASTOMERS PROJECT [HALOBUTYL UNIT]

LOCATION : JUBAIL 1, KINGDOM OF SAUDI ARABIA

DURATION : 19 NOVEMBER 2013 - 30 NOVEMBER 2015

ROLES & RESPONSIBILITIES

1.Preparation of all Lifting and Rigging Plans on the project.

2.Ensure Lifting and Rigging plans are completed within the agreed timeframe and in line with the project schedule.

3.Identify materials and equipment required in order to execute safe lifts on the project.

4.Provide lifting constructability input into all new designs as requested by the Project Management team.

5.Identify any special construction equipment or tooling.

6.Approve contractors lifting equipment and materials.

7.Audit of Construction contractors Lifting and Rigging capabilities.

8.Responsible for the implementation of safety measures in all aspects of rigging works.

9.Participate in site and unit plot plan development.

10.Conduct preliminary crane locations.

11.Review & evaluate transport routes.

12.Check Fabrication areas Vessel / Equipment dress-out areas.

13.Identify utility interferences.

14.Proposed lifting solutions (alternative lifting method).

15.Support development of construction execution strategy.

16.Participate in site and unit plot plan development in addition to crane location determination.

17.Provide rigging input into structural design and mechanical equipment.

RIGGING SUPERVISOR

COMPANY : TECHNIP SAUDI ARABIA LTD.

CLIENT : SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL CO.

PROJECT : JUBAIL EXPORT REFINERY [PACKAGE 2A]

LOCATION : JUBAIL 2, KINGDOM OF SAUDI ARABIA

DURATION : 01 NOVEMBER 2010 - 30 AUGUST 2013

ROLES & RESPONSIBILITIES

1.Preparation of all Lifting and Rigging Plans on the project.

2.Ensure Lifting and Rigging plans are completed within the agreed timeframe and in line with the project schedule.

3.Identify materials and equipment required in order to execute safe lifts on the project.

4.Provide lifting constructability input into all new designs as requested by the Project Management team.

5.Identify any special construction equipment or tooling.

6.Approve contractors lifting equipment and materials.

7.Audit of Construction contractors Lifting and Rigging capabilities.

8.Responsible for the implementation of safety measures in all aspects of rigging works.

9.Participate in site and unit plot plan development.

10.Conduct preliminary crane locations.

11.Review & evaluate transport routes.

12.Check Fabrication areas Vessel / Equipment dress-out areas.

13.Identify utility interferences.

14.Proposed lifting solutions (alternative lifting method).

15.Support development of construction execution strategy.

16.Participate in site and unit plot plan development in addition to crane location determination.

17.Provide rigging input into structural design and mechanical equipment.

RIGGING SUPERVISOR

COMPANY : TECHNIP ITALY S.P.A.

CLIENT : NESTE OIL

PROJECT : NExBTL RENEWABLE DIESEL

LOCATION : TUAS, SINGAPORE

DURATION : 05 OCTOBER 2009 - 31 JULY 2010

ROLES & RESPONSIBILITIES

1.Preparation of all Lifting and Rigging Plans on the project.

2.Ensure Lifting and Rigging plans are completed within the agreed timeframe and in line with the project schedule.

3.Identify materials and equipment required in order to execute safe lifts on the project.

4.Provide lifting constructability input into all new designs as requested by the Project Management team.

5.Identify any special construction equipment or tooling.

6.Approve contractors lifting equipment and materials.

7.Audit of Construction contractors Lifting and Rigging capabilities.

8.Responsible for the implementation of safety measures in all aspects of rigging works.

9.Participate in site and unit plot plan development.

10.Conduct preliminary crane locations.

11.Review & evaluate transport routes.

12.Check Fabrication areas Vessel / Equipment dress-out areas.

13.Identify utility interferences.

14.Proposed lifting solutions (alternative lifting method).

15.Support development of construction execution strategy.

16.Participate in site and unit plot plan development in addition to crane location determination.

17.Provide rigging input into structural design and mechanical equipment.

RIGGING SUPERVISOR

COMPANY : TECHNIP ITALY S.P.A.

CLIENT : THE KUWAIT OLEFINS COMPANY [TKOC]

PROJECT : OLEFINS 2 KUWAIT [EU2]

LOCATION : SHOAIBA, KUWAIT

DURATION : 26 NOVEMBER 2006 - 30 SEPTEMBER 2008

ROLES & RESPONSIBILITIES

1.Preparation of all Lifting and Rigging Plans on the project.

2.Ensure Lifting and Rigging plans are completed within the agreed timeframe and in line with the project schedule.

3.Identify materials and equipment required in order to execute safe lifts on the project.

4.Provide lifting constructability input into all new designs as requested by the Project Management team.

5.Identify any special construction equipment or tooling.

6.Approve contractors lifting equipment and materials.

7.Audit of Construction contractors Lifting and Rigging capabilities.

8.Responsible for the implementation of safety measures in all aspects of rigging works.

9.Participate in site and unit plot plan development.

10.Conduct preliminary crane locations.

11.Review & evaluate transport routes.

12.Check Fabrication areas Vessel / Equipment dress-out areas.

13.Identify utility interferences.

14.Proposed lifting solutions (alternative lifting method).

15.Support development of construction execution strategy.

16.Participate in site and unit plot plan development in addition to crane location determination.

17.Provide rigging input into structural design and mechanical equipment.

RIGGER 1

COMPANY : GAMA AL-MOUSHEGA ARABIA LTD.

CLIENT : SAUDI ARAMCO / SNAMPROGETTI S.P.A.

PROJECT : HAWIYAH NGL RECOVERY PLANT [HNRP]

LOCATION : HAWIYAH, KINGDOM OF SAUDI ARABIA

DURATION : 21 JULY 2006 - 25 NOVEMBER 2006

ROLES & RESPONSIBILITIES

1.Provide and approve heavy lift plan or engineered lifts and critical lift plan.

2.Responsible for execution of heavy lifts, tandem lift, tailing lift.

3.Supervision and monitoring of all critical lifts.

4.Ensures all documents involved to the lift is documented and certified.

5.Ensure all lifts in safe manner and follows as per standard.

RIGGING SUPERVISOR

COMPANY : AMEC SPIE CAPAG S.P.A.

CLIENT : BRITISH PETROLEUM [BP]

PROJECT : SOUTH CAUCASUS PIPELINE [BTC& SCP]

LOCATION : TBILISI, GEORGIA

DURATION : 26 JUNE 2005 - 15 NOVEMBER 2005

ROLES & RESPONSIBILITIES

1.Responsible for the implementation of safety measures in all aspects of rigging works.

2.Recommends for action by job supervision, suspend of work in unsafe areas, imminent danger to life and health situation may stop work on own violation.

3.Maintains up to date and vital information of all applicable safety standards and regulations in rigging works.

4.Conducts inspection for cranes and rigging tackles and ensure that all rigging gears on site are inspected and color coded.

5.Check/monitor and recommend the proper use of rigging gears especially if the nature of the job requires such equipment.

RIGGER 1

COMPANY : GAMA AL-MOUSHEGA ARABIA LTD.

CLIENT : SAUDI ARAMCO / TECHNIP SAUDI ARABIA LTD.

PROJECT : BERRI GAS PLANT @ QATIF FACILITIES

LOCATION : JUBAIL, KINGDOM OF SAUDI ARABIA

DURATION : 02 NOVEMBER 2003 - 03 MARCH 2005

ROLES & RESPONSIBILITIES

1.Provide and approve heavy lift plan or engineered lifts and critical lift plan.

2.Responsible for execution of heavy lifts, tandem lift, tailing lift.

3.Supervision and monitoring of all critical lifts.

4.Ensures all documents involved to the lift is documented and certified.

5.Ensure all lifts in safe manner and follows as per standard.

RIGGER 3

COMPANY : MOHAMMAD AL-MOJIL GROUP

CLIENT : KEMYA / LUMMUZ ALIREZA

PROJECT : OLEFINS 3 [KEMYA 3]

LOCATION : JUBAIL 1, KINGDOM OF SAUDI ARABIA

DURATION : 28 AUGUST 1999 - 26 JULY 2000

VARIUS PROJECTS IN PHILIPPINES EXPERIENCED IN RIGGING

CERTIFICATES

SAUDI ARAMCO CERTIFIED RIGGER LEVEL I & II

TUV RIGGER LEVEL I

KEMYA APPROVED RIGGING SPECIALIST

KEMYA APPROVED EQUIPMENT INSPECTOR

EDUCATION

TERTIARY : SOUTH II CENTRAL SCHOOL [1981 – 1987]

SECONDARY : SUAREZ NATIONAL HIGH SCHOOL [1987 – 1991]

COLLEGE : ST. PETER’S COLLEGE [4TH YR. B.S. MEHANICAL ENGINEERING]

REFERENCES

Salvatore Cassese Ramiro Garcia

Site Manager HSE Manager

SEP Halobutyl SEP Halobutyl

Technip Technip

Alessandro Savi Colin Alexis

Site Manager HSE Manager

JER Project JER Project

Technip Technip

Roberto Pistigliucci Frank Jacobs

Site Manager HSE Manager

NExBTL Project NExBTL Project

Technip Technip

Donald R. Pace Marco Volpe

HSE Manager Site Manager

OL2K Project OL2K Project

Technip Technip

Rui Nunez Peter Horsley

Project HSE Manager Rigging Superintendent

SCP Project OL2K Project

Amec Spie Capag S.p.A TKOC - Fluor Daniel B.V.



Contact this candidate