OBJECTIVE
Control Combined Cycle Power Plant-generating equipment which may use any one type of fuel such as Natural Gas a. Read charts, meters, and gauges to monitor voltage and electricity flows, Check equipment and indicators to detect evidence of operating problems, Adjust controls to regulate the flow of power Start or stop generators, turbines, and other equipment as necessary.
Experience Profile : (From OCTOBER 2006 to Present)
CONTROL ROOM (DCS) OPERATOR: 20 OCT 2015 to till date
SAUDI ARAMCO COGEN IPP 890 MW (ASHOMCO)
CONTROL ROOM OPERATOR: 07 DEC 2011 to 13 OCT 2015
K- ELECTRIC 560 MW CCPP BIN QASIM POWER STATION 2.
SENOIR FIELD OPERATOR: 01 FEB 2011 to DEC 2011
ENGRO FERTILIZER LIMITED KARACHI
FIELD OPERATOR: 27 OCT 2006 to 26 OCT 2010
FAUJI FERTILIZER COMPANY (MIR PUR MATHELO)
Academic and Technical Qualification
D.A.E (Electrical) from NIAMS Karachi with A grade.
F.S.C from Govt. Degree College Ghotki in 2007 with first Division.
Metric from Govt.High school Mathelo in 2005 with first Division.
Two years apprenticeship training from FAUJI Fertilizer Company.
JOB RESPONSIBILITIES:
Supervised and coordinates plant personnel in start-up, shut-down and other major operational changes and follow PTW system.
Diagnosed and/or troubleshoots particular operating problems. Take necessary courses of action to rectify or improve situations.
Identify situation where engineering or maintenance assistance may be required.
Oversee complete plant operation to ensure safe and efficient operating procedures are followed.
Coordinate plant operations as necessary with other connected plants upstream or downstream.
Ensure accurate operating logs are maintained.
Respond to emergency or plant upset situations by shutting down plant or taking necessary action to restore normal running.
Oversee maintenance work in progress or completed within the unit. Ensures that safe procedures are adhered to and that completed work is satisfactory.
Control and maintain auxiliary equipment, such as pumps, fans, compressors, condensers, feed water heaters, filters, and chlorinators, to supply water, fuel, lubricants, air, and auxiliary power.
Monitor and inspect power plant equipment and indicators to detect evidence of operating problems.
Open and close valves and switches in sequence upon signals from other workers, in order to start or shut down auxiliary units.
Start or stop generators, auxiliary pumping equipment, turbines, and other power plant equipment, and connect or disconnect equipment from circuits.
Communicate with systems operators to regulate and coordinate transmission loads and frequencies, and line voltages.
Confirm and carry out safe isolation (electrically and mechanically) and normalizing of equipments.
Implement scheduled and emergency equipment changeovers / testing in order to ensure healthy condition of the equipment.
Description of experience
Gas Turbine (General Electric 128 MW) frame 9E
Gas turbine units, single shaft, heavy duty gas turbines is model of PG9171E supplied by GE (General Electric) Company along with three generators provided by GE as well 128 MW each.
Duel Fuel with DLN 1.0 and Water injection system.
Mark VI e control system.
GAS TURBINE GE FRAME F7A 182 MW WITH DLN 2.6 TECHNOLOGY
Heat Recovery Steam Generator (Harbin Boiler Company China)
Dual and single pressure, horizontal duct and natural circulation.
Steam Turbine (Harbin Power Engineering, China 185 MW)
Steam turbine 185 MW is tandem compound, single shaft, double pressure, double casing, double flow, two exhausts, Impulse and condensing steam turbine and crossover pipe between HP and LP cylinders.
Ball cleaning system to clean tubes of condenser cooler with rubber balls
Hydrogen cooled and stator water cooled generator of 250 MVA driven by steam turbine.
Hydrogen, oil sealing and stator cooling water systems for steam turbine generator.
Natural Gas Compressor
Three Natural gas compressor/Dry gas seal compressor to boost up gas pressure up to 28 bar, centrifugal double stage HP and LP compressor with dry gas seal N2 system 50% capacity of each compressor with inter stage cooler and cyclone separators.
BOP (Balance of Plant) System
Hydrogen (H2) generation Plant AND Sodium hypo chlorite (NAOCL) plant.
Nitrogen (N2) generation plant, air compressor fire fighting pumps
Water treatment plant Includes CLARIFIER, RO AND DEMIN WATER SYSTEM.
Cooling tower, fin fan cooler AND Furnace Operation. (F-01)
Bucket Elevators, conveyers, Rotary Drums & Blowers
Auxiliary boiler 10 ton per hour capacity.
EDG 1200Watt and BSDG 1800 Watt for blackout.
Gas InsUlated Switch Yard.
220KV gas insulated switch yard DOUBLE BUD BAR SCHEME.
230 KV gas insulated switch yard with double bus bar.
Authorize for HV MV and Low voltage system.
COMMISIONING
Involved in erection and commissioning of gas turbines like GE frame 9E, 7 FA AND 7EA with HRSG and BOPs.
Safety ENVIRONMENT and Health
Safety Achievement OSHSAS Management system (OHSAS 18001-2007).
Quality Management System (QMS9001-2008).
Environmental Management System (ISO14001:2004).
PSRM, NEQS limits and SAFETY critical equipments knowledge.
First aid and CPR techniques.