CURRICULUM VITAE

Name : Munif Hari Budi

Place/Date of Birth : Jember,Desember 18th,1970

Marital Status : Married

Nationality : Indonesian

Permanent Address : Jl.ImamBonjol, no. 35 Tanggul,Jember

Mobile Phone : +62-822********

+628**********

E-mail Address : *********@*****.***

*********@*****.***

Passport Number : A6558038 Exp. Date:16-10-2018

Qualifications : - Coating Inspector IndocorLevel-2

-Coating Inspector IndocorLevel-1

-T-BOSIET

- Implementation and Application of Painting, Coating and Corrosion

Senior High School

Having more than 15 (fifteens) years in inspection & quality in cluding charge hand (Coordinator),inspection,prepare quality countrol procedure and responsible for general quality,countrol activity to confirm that they comply with specified procedure or client requirement,has served as QC Inspector,Coating and Painting Inspector for Oil and Gas Project,Oil Refinery Project,Petrochemical and Pipeline Project ( Onshore and Offshore Project )

1.“CoatingInspectorIndocorLevel-2”Conducted by an INDOCOR’S Authorized Training Body for research and development of corrosionand material product.

2.“CoatingInspectorIndocorLevel-1”Conducted by an INDOCOR’S Authorized Training Body for research and development of corrosion and material product.

3.“In HouseTraining for Implementation and Application of Painting and Corrosion” conducted by Bredero Shaw. Batam-Indonesia

4.“Incident andInjuryFree”Training Conducted by Bredero Shaw.Batam-Indonesia

5.Seminar and Workshop National 2013 “Corrosion for Industry and Environmental Integrity” held in JW Marriot Hotel Surabaya.”

1.Know ledge of Coating and Painting Inspector and QualityControl

2.Excellen tof Concrete coating

3.Know ledge of lab test for concrete coating

4.Know ledge of Rock jacket coating (Grooving&un grooving)

5.Know ledge of windows Application, MSoffice, Adobe,and Internet research

6.Know ledge in English both oral and written

7.Know ledge of Code SSPC,ASTM,NACE,ISO, etc

1.PT. WIJAYA KARYA – WIKA (PERSERO) CONSURTIUM

Position : Sr Coating Inspector

Period : April 21, 2015 – 15 februari 2016

Location : PT WaruTeknikatama

Sidoarjo, Province of East Java – Indonesia.

Client : PT. Chevron Pacific Indonesia

Project : NORT DURI DEVELOPMENT ( NDD ) - AREA 13

Job Description

-Monitored & Witnessed ITP & Quality Plant Approved by All parties.

-Monitor Loading and unloading for painting damages and internal side of structure

-Monitoring and Inspection surface preparation Blasting and Painting to ensure and check abrasive, surface profile, coating,DFT check,Salt test, environmental and Perform test such as Holiday test, Adhesion test (after the coating process will quantify the strength of the bond between substrate & coating),hydrotastic,MDR.IRN

-Final inspection

Inspection Item : - CVC Condensate cooler

- AWT Heater

2. PT UNICO UTAMA ( OFFSHORE)

Position : Coating inspector

Period : 20 January 2015- 15 April 2015

Location : Offshore Southeast Sumatera

Client : CNOOC SES LTD – NORTH AREA

( REFURBISHMENT )

Job description :

-Monitoring and Inspection blasting and surface preparation Painting for sure and checkabrasive, surface profiles, coatings, environment,DFT check,Monitoring the Implementation When applications.

Inspection the item :

a.WIDURI PROCES

The Main item structure :

-Vessel and pipeline

-Hydro cyclone

-Cellar deck

-Main deck- underneat

-Leg jacket

3. PT.WIJAYA KARYA – WIKA (PERSERO) CONSURTIUM

Position : Coating Inspector

Period : June 16, 2014– December 24, 2014

Location : PT WaruTeknikatama

Sidoarjo,Province of East Java – Indonesia.

Client : PT. Chevron Pacific Indonesia

Project : NORT DURI DEVELOPMENT (NDD) AREA 13

Inspection the item:

- CVC Condensate cooler

- AWT Heater

Job Description

-Monitored & Witnessed ITP & Quality Plant Approved by All parties.

-Monitor Loading and unloading for painting damages and internal side of structure

-Monitoring and Inspection surface preparation Blasting and Painting to ensure and check abrasive, surface profile, coating,DFT check,Salt test, environmental and Perform test such as Holiday test, Adhesion test (after the coating process will quantify the strength of the bond between substrate & coating).

2.PT. HANJUNG INDONESIA

Position : Coating Inspector

Period : March 2012 – May 2014 (Job Complete)

Location : Srengsem – Panjang, Bandar Lampung City

Province of Lampung – Indonesia.

Project : Gorgon Project Barrow Island LNG Plant (Job Complete)

Job Description :

-Responsibility the inspection to client ;Keylog Joint Venture (KJV) and SaipemLeigthon Consortium (SLC).

-Full support inspection for PT. Hanjung Indonesia

-With SLC and Jotun (Paint Manufacture) coordination to ensure the result of inspection.

-Inspection the item of baltoflake system (painting system 1)/ atmospheric zone, splash zone & immersion zone.

The main item structure :

a.Marine Operation Platform (MOP) and

b.Breasting Dolphin (BD).

-Inspection the item of three coat system (painting system 2)/ atmospheric zone.

The roadway structure :

a.Catwalk (CT)

b.Bracket and support structure

-The inspection scope :

a.Conductivity test

b.Sharp edges, visual of welding and assessment blackspot(pitting corrosion)

c.Visual inspection after blasting (Cleanliness ISO 8501 Sa 2,5).

d.Salt test (the rate not exceed = 30 mg/ m )

e.Chloride SulfatNitrit Test (CSN test), if required.

f.Measurement profile (tape press O method)

g.Dry film thickness check (DFT)

h.Holiday Test (High Voltage)

i.Final inspection

-Responsibility and the one of authorize for coating/ painting report.

-

Project : Ketapang II. Ltd, Bukit Tua Development Project (Job Complete)

Job Description :

-Responsibility the inspection to client; PT. Technip Indonesia and PCK2L – PetronasCarigali.

-Inspection of Ketapang II. Ltd, Bukit Tua Development Project. Thepaint specification :

a.System 1A

The coating type for atmospheric zone (Three Coat System)

The item structure : vent boom, handrail and support.

b.System 3B

The coating type for atmospheric zone (Epoxy Glass Flake)

The item structure : Deck, angle and support.

c.System 5A(1)

The coating type for heat resistance (Inorganic Zinc Silicate & Modified Acrylic)

The item : vessel and pipe (carbon steel) with surface temperature 110 – 250 C.

d.System 5A(2)

The coating type for heat resistance (Inorganic Zinc Silicate & Silicone Alumunium)

The item : vessel and pipe (carbon steel) with surface temperature 250 – 450 C

e.System 16B

The coating type for internal lining (Epoxy – Amine Adduct)

The item : internal lining (inside) pipe of diesel.

-The inspection scope:

a.Conductivity test

b.Visual inspection after blasting (Cleanliness ISO 8501 Sa 2,5).

c.Salt test (the rate not exceed = 30 mg/ m )

d.Chloride SulfatNitrit Test (CSN test), if required.

e.Measurement profile (tape press O method)

f.Dry film thickness check (DFT)

g.Holiday Test (Low Voltage)

h.Final inspection

-Check and advice the blasting/ painting work.

Project : PETRONAS LNG Train 9 Project / PETRONAS

Job Description

-Responsibility the inspection to client; JGC & Furnace Engineering Inc.

-Inspection of Petronas LNG Train 9 Project.Thepaint specification :

a.System 1A

The coating type for atmospheric zone (Three Coat System)

The item structure :, handrail and support.

b.System 5A(1)

The coating type for heat resistance (Inorganic Zinc Silicate & Modified Acrylic)

The item : Radiant Casing, Convection module and the material item with surface temperature 110 – 250 C.

-The inspection scope:

a.Visual inspection after blasting (Cleanliness ISO 8501 Sa 2,5).

b.Salt test (the rate not exceed = 50 mg/ m )

c.Measurement profile (tape press O method)

d.Dry film thickness check (DFT)

e.Cross Cut, X – Cut & Pull off

f.Final inspection

-Check and advice the blasting/ painting work.

Project : TAIF – NK VCC LLE2 Project

Job Description

-Responsibility the inspection to client; Furnace Engineering Inc.

-Inspection of TAIF – NK VCC LLE2 Project. The paints specification :

Primer Coat – Inorganic Zinc Silicate = 75 µm.

-Check and advice the blasting/ painting work.

3.CP7 MUARA KARANG Project, PGN Indonesia

Position : Coating Inspector

Period : February 2011 – March 2012

Project : Tanjung Karang Pipeline Project

Location : Indal Steel Pipe - Indonesia

4.PT. S P I N D O

Position : Coating Inspector

Period : July 2009 - January 2011

Location : Beji- Pasuruan

Project :

-RGP 6 (Porth Hedland Project)

-RGP 5 (Harriet Point Berth Extension Project)

-Townsville Marine Precinct Project.

Job Description

-Monitoring, Inspecting, witnessing, coating pipe process to ensure meet the specification requirement.

-Reviewing and signing the complete coating MDR to be submitted to client.

5. PT KARYA ADHI NUGRAHA ( contruction )

Position : Quality Countrol

Period : juny 2006 – April 2009

Location : East java

6.PT BAJA DJAYA

Position : Quality Countrol

Period : March 2000 – may 2006

Location : East java

Note.

Certify that all statements in this data are true and correct to the best of my know ledge and

belief.

Best Regard

MUNIF HARIBUDI

QA/QC Inspector

MobilePhone :+62-822********

+62-823********



Contact this candidate