Jeffery J. Boudreaux Jr.
*** ******* **., ***** ******, LA, 70037
Home phone: 504-***-**** / Cell phone:504-***-**** Objective:
To find a challenging position suited to my 35 years of Manufacturing and Scheduling knowledge in the Manufacturing \ Test fields. SUMMARY:
Experienced in Scheduling, Manufacturing processes and Build to Test strategies. First hand working knowledge of Craft manufacturing, Program Management, Cost management and Schedule development. Education:
1979 Belle Chasse High School
1982 Delgado Community College - Welding
Experience:
CPM Scheduler 3; 2014 to 2015
Avondale Engineering & Construction Division
• Estimates RFQ’s by drawing, establishing linear footages, weld sizes, man hour rates, and material take offs.
• Issues project work orders using Microsoft Dynamics ERP system.
• Handles all facets of shipping and receiving.
• Developed Job Safety Analysis sheets for all equipment within the facility.
• Developed Operations Quality procedures.
• Develop and maintain weekly schedule metrics Machine Shop/Oil and Gas projects.
• Perform critical path analysis on schedules.
• Interface with a multi-disciple team, program managers and external customers.
• Developed production schedules.
• Develop and Maintain the site facility Master Schedule CPM Scheduler 3. 2006 to 2014
Huntington Ingalls Industries, Avondale Operations
• Update and maintain Integrated Master Schedule for LPD Class, Amphibious Ship Program.
• Develop and maintain weekly schedule metrics for Program office
• Perform critical path analysis on schedules.
• Build and maintain weekly Pipe Craft install to test metric reports
• Interface with a multi-disciple team, program managers and external customers.
• Developed production schedules.
• Assisted development of the LHA 7 IMS.
1 of 2
Lead Pipe Superintendent (Delivery Area) 2002 to 2006 Northrop Grumman Ship Systems, Avondale Operations
• Worked Polar Tanker and LPD contracts. Overall responsibility for all Pipe Department onboard all ships on the waterfront.
• Lead Pipe Superintendent in the Delivery area. My responsibilities included: all aspects of Budgets, Manpower projections, Scheduling, Training/ Certification adherence and Day to Day Pipe planning. Pipe General Foreman (Integrate Area) 2001 to 2002 Northrop Grumman Ship Systems, Avondale Operations
• Gen. Foreman Pipe Dept. Unit Construction LPD-17 at erection site.
• Controlled all aspects of piping installation for 6 Supervisors under my direction.
General Ship Superintendent (Delivery Area) 2000 to 2001 Litton Industries/Northrop Grumman Ship Systems, Avondale Operations
• Gen. Ship Superintendent with Ships Management on Polar contracts.
• Responsible for all Production (all crafts) onboard vessel.
• My responsibilities included: all aspects of Budgets, Manpower projections, Scheduling adherence for all craft disciplines onboard the vessel. Pipe Supervisor 1985 to 2000
Avondale Shipyard/Avondale Industries
• Pipe Dept. Supervisor gaining valuable experience in all phases of piping process from unit construction thru unit erection to final outfitting and Sea Trials.
• As a Pipe Supervisor, my areas of responsibilities have been system completion, instrumentation, multi-tubing, tank / compartment completion, diagram verification, manning level load planning and titanium piping. Test Operator\Pipe Fitter 1979 to 1985
Avondale Shipyard / Avondale Industries
• Worked 11 months with Ship Operators during 1983 and 1984. Worked the SL7 contract. Main area of responsibility was Main Propulsion (Steam plant).
• Worked as a Pipe Fitter/Helper throughout the Main Yard on various contracts until being promoted to Line Supervisor. Qualified as a P-1 pipe fitter for all High pressure and Steam systems.
COMPUTER SKILLS:
MS Project 2003 & 07; MS Office Applications-Outlook, Excel, Access, Powerpoint, Primavera (P6), Microsoft Dynamics
2 of 2