Robert Webb
Contact: 1+386-***-**** (USA) Email: **********@*****.***
Home : 1+386–292-5155 (USA)
Qualifications:
30+ years of heavy industrial experience in STRUCTURAL STEEL ERECTION, CRANE AND RIGGING,PIPING,MECHANICAL and CIVIL with 20 years in Management Positions
*Strengths include: LEADERSHIP, TRAINING, PLANNING, KNOWLEDGE of the day to day operations in industrial construction, Read and understand BLUEPRINTS. Proven track record with total commitment to SAFETY, QUALITY and SCHEDULES.
Skilled in Management of multiple crews, material requisitioning, and all equipment needed.
Skilled in the operation, set up and knowledge of all types of cranes, rigging procedures and other construction equipment.
Expertise in GRASS ROOTS petrochemical plants, refineries, compressor stations, power plants (coal and gas fired) and installation of other facilities.
Education:
NCCCO certification-hydraulic and friction cranes
NCCCER certification Rigging,
OSHA- 10 hour course 2009
Emergency Medical Technician- North Florida Community College
Relevant Experience
Mobile Rock Crusher, ThyssenKrupp, Hondo, Tx. June 2015 – Present
Site Manager
Manage and track shipping and receiving of structural and mechanical components from Germany and Turkey. Manage assembly by subcontractors. Assume all managerial duties such as shipping, receiving, scheduling and budgeting.
Vertical Lime Kiln, ThyssenKrupp, Pleasant Gap, Pa. February 2015 – May 2015
General Superintendent
Grass roots installation of state-of-the-art Vertical Lime Kiln in Pennsylvania. Supervising and directing 70+ employees in all facets of construction on $100,000,000 job.
Eco petrol Oil Refinery, CB&I Cartagena, Colombia August 2013 – July 2014
Construction Manager
Managing self- performed and sub-contractor employees to build the alkylation unit in an existing refinery. Directing manpower and equipment to meet tight schedules, milestones and completion dates.
Managing 700 employees and all sub-contractors from construction to completion on this 700 Million +
Project.
JVP Project, SNC Lavalin Penonome, Panama January 2012- August 2013
General Superintendent
Duties are to oversee all infrastructures, roads, camp facilities and shipping port for Joint Venture Panamanian/SNC gold and copper mine.
Ambatovy Project, SNC Lavalin Madagascar, Africa July 2010- September 2011
Refinery Construction Manager
Duties are to oversee all steel erection, all tanks, all vessels and all mechanical and piping installation for a cobalt and nickel refinery. Managing crews of 200 TCN supervisors and 2800 skilled craft workers. Managing the barriers of communication and leading the safety initiatives and team direction required for success on a project of this size, involving 78 nationalities. Focused on the hydro metallurgical refinery section of a 5+ Billion dollar facility.
APS Four Corners Power, Erwin IND. Jan, 2010-May 2010
Senior Site Superintendent
Overseeing complete boiler rebuild for a 750 megawatt coal burner. In charge of all crafts and equipment on this 250 Million dollar project, which was brought in early and under budget.
Dominion Power Plant Wise, VA Shaw Group July 2009-October 2009
Area Construction Manager
Grass roots state of the art coal, wood and steam fired power plant. Managing the fabrication and erection of the turbine exhaust system and all crafts affiliated with erection and piping for the acc unit. This was a 1.5 Billion dollar project that was brought in 3 mths. early.
Morgantown Station, Newburg, MD Shaw Group December 2008-July 2009
*Millwright /Boilermaker Superintendent
Duties included- overseeing the erection of the limestone conveyor systems. Consisting of, anchoring tail sections, setting head chutes, setting drag feeders, welding and fabricating dump chutes and erection of all supports and conveyor sections. Also fabrication and installation of exhaust duct for 3 coal fired units.
.
Relevant Experience Continued:
John Amos Plant, Winfield, WV Shaw Group August 2007-November 2007
*Site Superintendent
Duties included the overseeing all steel installation, crane and rigging procedures, lift plans, structural beef up and duct work fabrication and installation for the dismantling and rebuild of a 1350 megawatt precipitator. Directing 2000 employees to complete this 250,000,000 million
Project on schedule’
Hobbs, NM Colorado Energy Management July 2007-May 2008
*Mechanical Superintendent and Crane Coordinator
Duties include the overseeing of the dismantle, transport and erection of two 80% complete power plants from Mississippi and Tennessee to be re-erected and expanded into a 650MG Gas and Steam Fired power plant. Daily responsibilities include work schedules, maintenance of the cranes, forklifts and all other heavy equipment. Prepared lift plans and plans for miscellaneous platforms and responsible for all steel erections. Managed a crew of 700
employees from all crafts to complete this 700 million dollar venture in a record time of 16 months.
Cortez, CO Saulcon February 2007-June 2007
Construction Manager
Grass roots construction of two CO2 plants. Overseeing the erection of iron, tanks, vessels and piping for both of these facilities, though 40 miles apart .Work force consists of 500 craft people on this 400 million dollar effort.
Career Overview:
From 1978 to 2006 was spent acquiring the skills and extensive knowledge of the construction industry, including, Laborer, Rodbuster, and Carpenter; to a focus on Steel Erection, Heavy Rigging, Piping and mechanical, and Crane Operations and Procedures. This well rounded experience coupled with the commitment to excel in a management career has developed to the point that I can succeed in all my assignments. I thrive especially when challenged and am able to create a team for success.
I am able to travel and strive to meet my employers expectations in not only production but more important, in working safe.
US Passport: Current
References Available Upon Request