Anil Ghorpade

Phone, 042*-***-***

E-Mail: acq921@r.postjobfree.com

QUALIFICATIONS

Bachelor of Engineering (Civil) – 1992

Master's In Construction Management -1993

Certified Internal company auditor for the implementation of ISO 9001: 2000 & 14000 WORK HISTORY

Worley Parsons - Transfield Services (TW), Snr Implementation / Shutdown Planner: Apr - 14 to date Responsibilities:

• Construct asset maintenance schedules including detailed shutdown plans for Woodside assets.

• Providing detailed logical activity based plans determined by defined shutdown sequences and provide manpower resourcing (crew mix) analysis for all disciplines.

• Identify required materials/ BOM as per the scope of work and ensure it is manifested on the boat schedule prior to execution. Reprioritize and rejig the work schedule if discrepancy is found to safeguard critical path.

• Producing schedule compliance and productivity reports against set KPIs for analysis alongwith the project engineer for continuous improvement.

• Reviewing potential changes to avoid conflicts and provide input to the change control procedure and incorporate approved changes into the look-ahead programme

• Provide the asset team with a daily work schedule (by workpacks per shift) to prioritise activities as per the lookahead plan.

Gorgon Project – Various Packages : June-13 to Dec-13

• MEIC scope (CKJV) – Barrow Island.

• Domgas Commissioning (Sapura Clough):

Responsibilities:

• Daily updating and monitoring of level 5 commissioning schedule of the Domgas line (T6 to ITZ)

• Establish the re-baseline for the MEIC project to forecast completion milestones.

• Align existing project controls practices in Scheduling, progress measurement and Risk Management to industry best practices.

• Development of rundown curves for tangibles by KPIs (within systems by priority) for early commissioning. GHD, Project Services Lead: May-12 to May-13

• Ore Car repair workshop, BHP Billiton.

Responsibilities:

• Establish cost control and planning function for integrated project control approach in EPCM projects.

• Provide project management support in the development of the work breakdown structure, activities, logic, resources and progress of the integrated project baseline.

• Developing consolidated engineering deliverable list, assigning appropriate weightings to calculate earned value and producing ‘S’ Curves to forecast completions based on AS 4817.

• Provide the Project Manager with monthly progress updates; forecast completions, together with the critical path and trend analyses.

• Developing the contracts and procurement strategy for the preparation of Project Execution Plan (PEP) and the master schedule to ensure key delivery milestones are met.

• Conducting risk workshops and applying probabilistic techniques to determine and communicate the possible range of cost and schedule outcomes using @Risk and Pertmaster. Anil Ghorpade

Phone, 042*-***-***

E-Mail: acq921@r.postjobfree.com

• Change management, claims / arbitrations and dispute handling support to contract administrators.

• Coordinating with finance for the monthly reporting of VoWD, accruals and updating cash flows projections.

• Leading a team of estimators during DPS to generate a Class-II capital estimate. Fluor Australia,

• Project Controls Lead: (Mar-10 to Apr-12) Argyle Diamond Underground Project For Rio Tinto:

• Planning Lead: (May-08 to Feb-10), RGP 5 (Yandi) for BHP Billiton, Surface Iron- Ore Mine. Responsibilities:

• Overall Project Controls functions of Schedule, Risk, Cost and Change Management.

• Analyzing variances in commercial and schedule performance w.r.t the PEP (Project Execution Plan) and provide corrective action plans, recovery measures for its mitigation.

• Manage change control processes (trends / change orders or budget shifts as required), advising project manager of significant variations & supervise its reconciliation for reforecasting.

• Produce timely and accurate project cash flow - commitments and expenditure.

• Develop contract pricing and administration instructions for alignment with the cost breakdown structure, bid evaluations against Company’s internal budget-estimates to support contract award recommendations.

• Develop the contract key dates, milestones and Company plan dates for alignment with the overall integrated plan, in evaluating bid schedules and in reviewing contractor plans to support contract award recommendations.

• Valuation of construction progress, review & approve Contractor's application for payments. Settle contractual claims, EOTs and final accounts ensuring compliance with the contract administration requirements.

• Develop earned value measurement system for E-P-C progress measurement in D&C work packages to assist with analysis of schedule and cost KPIs.

• Ensure all cost reports for work packages are prepared to the required accuracy, risk is understood, and appropriate contingency applied.

Clough Projects, Planning Lead: June-05 to May-08

• Panna Field Development - 3 Offshore WHPs, Interconnecting subsea pipelines & Tie-ins for British Gas Responsibilities @ Fabrication Yard:

• Coordinating all aspects of the planning and scheduling functions across all work locations and ensuring the schedules are integrated into one integrated EPC schedule.

• Maintain overall progress measurement systems covering engineering, procurement, fabrication and commissioning progress and productivity reporting across all work locations.

• Internal and external liaison to facilitate planning, scheduling and progress measurement.

• Prepare project controls section of weekly and monthly study and project reports.

• Maintaining Basis of Schedule Document to provide full visibility on the current schedule assumptions, risks and opportunities.

• Additional responsibility of interfacing with the QA-QC department for the documentation of MDRs and carry-over works to complete balance commissioning offshore. Responsibilities @ Home Office: (Tendering & Business Development for SURF projects)

• Prepare & assess alternative schedules to arrive at the most suitable/economical schedule in line with the constraints and client specified milestones.

• Perform risk analysis (using Pertmaster) on tender schedule and report on any problems/risks likely to impact tender schedule.

• Support the Proposal Coordinator with the Project Control requirements of the tender.

• Understanding the tender scope and planning requirements to issue the project controls section of tender submittal for inclusion with the bid.

Anil Ghorpade

Phone, 042*-***-***

E-Mail: acq921@r.postjobfree.com

Dodsal Pte. Ltd., Dubai, Lead Planner / Project Coordinator: Aug 01 to May 05

• Khuff Condensate Fractionation Project, Saudi Aramco: Brownfield Construction & Hook-up of fractionation plant in Saudi Aramco’s Ras Tanura Refinery Complex.

• Melut Basin Upstream Development, Sudan: EPC for crude oil FPF (Field Processing Facility)

• Sohar Refinery, Oman: “Construction only” project for the total Offsites package.

• Al Shuweihat Power Plant Piping, Abu Dhabi: EPC project for power plant piping. Responsibilities:

• Preparing control baseline containing Project Budget, Planning Dossier & Project execution manual on project award.

• Establishing progress measurement procedures in order to establish an accurate planning and reporting system.

• To monitor/analyze the weekly and monthly reports (physical & financials) in order to review progress, analyze trends & highlight discrepancies & variances.

• To monitor and analyze activities of vendors / subcontractors, interface with Contracts Engineer on subcontract cost, schedule issues and resource requirements for calculating Cost-To-Completion.

• Coordinate and establish level 4 budgets by phase per department and monitor earned progress to the detailed level of individual deliverable in engineering, POs in procurement or physical progress in construction.

• Development of detailed schedules for all Commissioning work including Work Packs, FTC’s and ITR’s.

• Prepare and present Monthly Progress Reports in monthly meetings with client, highlighting the milestones and progress achieved during the month. Also the variances with planned progress if any and the reasons thereof.

• Establish productivity requirements in accordance with master schedule & budget requirements.

• Provide assistance to the tendering team during Estimation stage. Al Habtoor, Murray Roberts JV, Dubai, Snr. Planning Engineer: Aug' 98 to July 01.

• Dubai International Airport (Terminal I & Concourse II) Responsibilities:

• Updating baseline programmes highlighting areas of backlog & rescheduling critical path activities to achieve milestone dates.

• Preparing short term, superintendent-wise construction schedules for target setting

• Using Primavera to prepare monthly progress invoices and to reforecast budgets.

• Preparing weekly & monthly reports to highlight variances/short fall in targets.

• Evaluating subcontractor resource loading and preparing total project manpower requirement loading charts.

• Preparing estimates for variations, claims & change work orders. TSKJ Nigeria Ltd., Bonny Island, Nigeria, Project Controls Engineer: Nov' 97 to Aug' 98.

(JV of Technip, Snamprogetti, M. W. Kellogg & JGC)

• Nigeria LNG – Train 1 and 2

Responsibilities:

• Developing area wise detailed construction schedules for the LNG trains to prioritize systems within area & use that to generate the required rates of piping spools fabrication and erection.

• Measuring and monitoring the Offsites, Tanks & Trains progress and consolidating it to produce overall plan v/s actual S curve.

Anil Ghorpade

Phone, 042*-***-***

E-Mail: acq921@r.postjobfree.com

• Keeping track of expended man-hours with respect to the rate of physical progress achieved.

• Producing reports to highlight variances for productivity factor analysis and cost control.

• Liaising with area construction superintendents to updating level 5 construction schedules. Larsen And Toubro Limited, Oil And Gas division, Mumbai, Project Engineer: June'96 to Nov'97

• B-173A Platform: A fast track 8-month EPC project for a wellhead platform producing 10,000 BOPD.

• HRC Process Platform: A conventional platform (topside weighing 1200 tons) to produce 30,000 BOPD oil, 20,000 BWPD water 1.50 MMSCMD gas

• Sagar Laxmi Rig Modification Project: Remodeling & repair of drilling rig during shutdown. Responsibilities:

• Handling all planning aspects for on-going multiple projects.

• Preparing planning requirements for new tenders & baseline schedule submissions on award of LOI.

• Making Revised Baseline submissions/monthly updates for client. Internal departmental reports for backlog on critical procurement items and catch-up plans.

• Working out peak manpower estimates for yard fabrication and rescheduling construction sequence to level resources.

• Liaise with engineering for maintaining and updating engineering deliverable list; procurement & fabrication centers for progress measurement and producing monthly report with reforecasted “balance-to-go” data.

• Interacting with individual planners of sub-contract packages like building module & compressor module to develop an integrated master plan achieving milestone dates for load out and off-shore hook-up. M/s Hindustan Construction Company, Project Engineer: Aug'93 to May'96

• Metro Rail Project Calcutta

• Bandra Influent and Effluent Works Mumbai.

Summary of Industries / Companies worked in

Industry Client Company Projects Type

Oil and Gas:

Upstream - Offshore

Platforms & SURF

British Gas,

ONGC, Woodside

Clough Projects, L&T,

Worley Parsons

O&G Greenfield,

Brownfield

EPCI, EPCM

LNG Plant Shell, Chevron TSKJ (Technip,

Snamprogetti, KBR, JGC)

CBI

O&G Greenfield EPCM, PCC

Downstream -

Onshore Refineries

Aramco, PDOC,

Siemens, SRC

Dodsal Pte. Ltd. Dubai O&G Brownfield &

Greenfield

EPC, PC, D&C

Mining:

Iron Ore BHP Billiton Fluor Australia (RGP5), Surface Mine Greenfield - EPCM

Diamonds Rio Tinto Fluor Australia

(Argyle Diamonds)

UG Mine Brownfield -

EPCM

Infrastructure Civil Projects:

Int’l Airport Dubai Civil

Aviation / Bechtel

Habtoor–Murray Roberts Greenfield EPCC

Metro Railway (MRT) Indian Railways Hindustan Construction Brownfield PCI



Contact this candidate