WORK EXPERIENCE:
PAST EMPLOYER: (Total duration: Sept'07 to jan'11)
Organization Duration Designations Scope of Work
September'07 to Supervisor IMPLEMENTATION OF APDRP- RE
March'10 PROJECT (RGGVY) IN KISHANGANJ
KALPATARU POWER DISTRICT OF BIHAR UNDER
TRANSMISSION LTD. POWERGRID.
March'10 to Supervisor 400 KV D/C NABINAGAR - SASARAM
November'10 T/L LINE IN DEHRI-ON-SONE OF
BIHAR UNDER POWERGRID.
November'10 to Supervisor 400 KV D/C MARWA - RAIPUR T/L
Jan'11 LINE IN CHATTISGARH UNDER
C.S.E.B.
JOB SKILL:
**ALL ACTIVITY OF SITE WORK i.e HT & LT POLE ERECTION, D/T ERECTION(16 &
25kva),STRINGING, BPL CONNECTION etc FOR RURAL ELECTRIFICATION WORKS.
**FOUNDATION WORKS FOR TL LINE .
**Site Management & Contractor mobilization.
**Preparation of Project Planning, scheduling and Monthly Progress Reports.
**Every day Site Execution work progress Monitoring & Preparation of next day
site program for client.
**Supervision for the concrete area size is perfect or not, supervision for the
Steel binding is ok as per drawings or not and supervision for the every
foundation is going on as per TS and drawings or not.
**Job monitoring for all types of tower foundation work.
**Material Handling & Reconciliation.
**Co-Ordination with Client, Head office & Regional office.
PRESENT EMPLOYER: (Total duration: Feb'11 to Till Date)
Organization Duration Designations Scope of Work
February'11 Field 220 KV M/C SUBHASGRAM -
K.E.C to Engineer SAITALA T/L IN 24 PARGANAH(S)
INTERNATIONAL August'12 UNDER C.E.S.C.
LTD.
August'12 to Field 220 KV D/C BELUR - NEW
June'14 Engineer COSSIPORE T/L IN KOLKATA
(GANGA RIVER CROSSING TOWER)
UNDER C.E.S.C.
July'14 to Field 400 KV D/C RAJARHAT - PURNEA
Till Now Engineer TRANSMISSION LINE UNDER
POWERGRID.
JOB SKILL:-
**Site Management & Contractor mobilization.
**Preparation of Project Planning, scheduling and Monthly Progress Reports.
**Every day Site Execution work progress Monitoring & Preparation of next day
site program for client.
**Supervision for the Pile and Pile Cape foundation as per TS and drawings.
**Completed RC 1 & RC 2 Tower of 114 mtr. height.
**Completed Ganga river crossing stringing of ACSR Zebra. Maintain the quality
of all type of work.
**Supervision for the concrete area size is perfect or not, supervision for the
Steel binding is ok as per drawings or not and supervision for the every
foundation is going on as per TS and drawings or not.
**Job monitoring for all types of tower foundation work.
**Material Handling & Reconciliation.
**Co-Ordination with Client, Head office & Regional office.
ACADEMIC QUALIFICATION :
EXAM. PASSED BOARD YEAR OF PASSING % OF MARKS DIVISION
SECONDARY W.B.B.S.E. 2002 76.25 Ist
Higher Secondary W.B.C.H.S.E. 2004 63.3 Ist
TECHNICAL QUALIFICATION : DIPLOMA IN ELECTRICAL ENGINEERING
EXAM. PASSED BOARD YEAR OF % OF DIVISION
PASSING MARKS
D.E.E W.B.S.C.T.E 2007 75.7 1st
CASTE : General
SEX : Male
RELIGION : Hinduism
NATIONALITY : Indian
MARITAL STATUS : Married
PASSPORT NUMBER : M2848993 (Valid up to-
15.10.2024)
OBJECTIVE: A position in technical field, I would like to contribute with
my technical & professional approach towards betterment & continuous
improvement within the organization.
PLACE : SERAMPORE
DATE: 15.04.15
[pic]
(SUBHANKAR KAR)