RODNEY H PATCH
***********@***.***
281-***-**** Cell Houston, TX
May, 2015
SUMMARY OF EXPERIENCE
Over Forty five (45+) years of petroleum related construction experience including Pipeline projects, below and above water, onshore and offshore, on platforms and barges. Have worked in various roles such as Project, Construction and Start-up Manager, Chief Pipeline Inspector, Project, Mechanical, Piping, Start-up, Area and General Superintendent. Work experience also extends to Pipeline Consultant, General and Multiple Crafts Foreman for Construction, Pipeline, Shop and Field Inspector QA/QC, Construction and Inspection Coordinator.
JOB TITLES
Welding, Utility/ all phases of Pipeline Inspection
Mechanical & Piping Superintendent
Assistant & Chief Inspector Pipelines Onshore and Offshore
Pipeline Superintendent
Area Superintendent
Onshore/Offshore Construction Manager
SR Construction Manager pump stations
Site Construction Manager
Start-up Coordinator
PERSONAL DATA
Residence:
Houston, Texas
**SCHOOLS:
As of 4-16-2015, I have become an online student of ASHWORTH COLLEGE to get my Construction Manager Certification
(Brushing up on what might be new.)
EQUIPMENT/COMMODITIES/SPECIALTIES
Pipeline Installation 36+” Pipeline
Pipeline Maintenance Pipeline Fabrication
Offshore Pipeline Lays Hook-Ups
DOT Pipeline Upgrades Pipe Spools
Setting of Hull & Topside 6500 Tons
Deep Water (4000+’) Offshore Pipeline Lays, Phlem, Plet and Umbilical Fabrication & Installation
20" X-70 Pipeline
Offshore Single Module Gas Compressor
Packages
Installation Of Cross-Country Fiber Optic
Cables
Well Head to Flow Line Tie-In Piping
Riser Installations
Cat Stripper, Reactors, Platformers
Refinery New Construction & Turn-a-Rounds
Shop Inspection: Heater Treaters, Injection Skids, Amine & Glycol Reboiler Packages and Contactors, fab & retraying, High Pressure Inlet Separators & Scrubbers, Filters, Inst. Air Compressor Packages, Complete Gas Compressor Packages, Heat Recovery Ducting Units.
Side Tap Assemblies
1400 Ton Deck Sections
300 To 400 Ton Generators
72’ Pentane Spheres (CB&I)
Deep Water Well Tie-Backs (200' to 450’)
Crude Columns
Gas Compressors and Pump Station
Installations
CERTIFICATIONS/TRAINING
HOT WORK.
LOCK0UT/TAGOUT-CONTROL OF HAZARDOUS ENERGY.
CONSTRUCTION LOCKOUT TAGING OF CIRCUITS.
TRENCHING & EXCAVATION SAFETY.
PERMIT AND NON-PERMIT CONFINED SPACES.
CONFINED SPACE ENTRY COMPETENT PERSON/SUPERVISOR.
DOT Pipeline Certified (Veriforce) VF-100,
102, 202, 203, 208, 304, 408, 501, 607, 427-I, PE-911, ELP-002PIP
DOT Pipeline Certified NCCER – AOC- Gas/Liquid. PMT Pipeline Maintenance
OQ’d to all Kinder Morgan (California) pipeline inspection jobs.(liquids)
USAFI 2 years collage equivalent - Engineering
U.S. Navy-Submarine, 2nd Class Diver's Training
Machinist - Tool and Die Training
Certified Welder ( Have Been ) API 1104 - SMAW B.31.3 - GMAW, D2.2- SMAW & GMAW
Construction Diver and Supervisor - 8 years,
+ U.S.N. 3 Yrs.
U.S. Passport I have a new one, good for 10 yrs.
Tank Construction, Erection & Repair to API-650
API 14C, T- 2, Certified, Offshore Control Systems
TWIC card, expires 18 April 2017
LANGUAGES
English (Comprehension, Writing, Reading)
Spanish (Comprehension, Writing, Reading)
PROFESSIONAL WORK HISTORY
Sept. 2014 to Oct. 2014
QIS Chief inspector
Doing a 2 week turn-a-round for Williams Markham, TX. The replaced and installation of a new compressor/expander. This was completed ontime.
Aug. 2014 to Sept. 2014
TIR ---Construction Supervisor 1
Installing a condensate loading terminal for DCP. The job was finished within the time scope allowed by DCP.
Oct. 2013 to July 2014
CSD Engineering
SR Construction Manager for 20 Pump Stations
Started as a Construction Manager for 51 miles of pipeline. I was personnel Construction Manager for 2 spreads. Once they started the pump stations, I was made SR Construction Manager in charge of 20 pump stations, which 6 or 7 stations were being worked at, at the same time. I had 2 construction managers working for me. one having the West stations and the other having the East stations. There was a total of 16 inspectors working for me. These stations went from Washington, PA to Philly, PA
Aug. 2013 to Oct, 2013
Gulf Interstate
Assistant Chief Inspector for 80 Miles of 10” pipeline running from Tioga, ND to the
Canadian Border. Doing different inspections as needed, taking all the daily reports
from the other inspectors and making a daily report for the Chief Inspector.
Sept. 2012 to Aug. 2013
Mustang Engineering ( Pipelines ) Houston, TX
Pipeline inspector for Kinder Morgan ( California )
Responsible to Kinder Morgan for pipeline safety during construction close to KM Lines.
Jan 2009 to Sept. 2012 (Intermittent)
Intertek
QA/QC Inspector Field and Shop
Performing various inspections and expediting activities on site and at vendor facilities during manufacture, fabrication, installation and operational testing (FAT’s). Verification of vendor compliance to purchase orders and specifications.
March 2012 to July 2012
Tulsa Inspection Resources 918-***-****
Chief Inspector for Enbridge in Venice, LA
VCSE Project ---3 Contractors
Dec. 2011 ---3 days
Steel Pipe and Tubing 337-***-****
Welding Inspector -3rd party inspection for qualifying 6 welders to API 1104 in SMAW & FCAW
For an offshore pipelay.
August 2011 to October 2011
QIS ---Markwest in PA 580-***-****
Chief Inspector on a Compressor Station.
This was a temporary job, until another Markwest chief finished up another station and became available.
July 2010 to Aug. 2011
Universal Pegasus 713-***-****
Welding Inspector / Chief Inspector Florida Gas Transmission Phase VIII, Expansion Project
Preformed all the different inspections for a tie-in crew. Did welding audits on the welders for each tie-in, each day. Made sure that all trenches met OSHA safety standards. Made sure that everything done on my spreed, was done to Florida Gas Transmission, OSHA< & Sheehan ( contractor ) standards. Verification that every act of work, was done by a person that had an OQ for that job, or had a person with that OQ, watching over the person doing the job. Chief Inspector over Meter and Regulator Stations.
Jan. 2009 to July 2010
Intertek-WISco 281-***-****
QA/QC Inspector
Performed various inspections and expediting activities on site and at a vendors facilities during the fabrication and operational testing of a PLET and a PLEM. Verification of welding procedures spec’s
(WPS) for each weld made.
OCEANEERING
REX East Pipeline – Kinder Morgan – Pipeline
Oct 2008 to Dec 2008
Mustang Engineering, Houston, TX
Utility Inspector
Road bore inspector for a PMI (PEMEX) Pipeline being installed in El Paso, TX.
Most bores were done by directional drilling, Main highways were cased.
Sep 2008 to Oct 2008
TransMontaigue in Port Everglades, FL
Chief Inspector
Overseeing a pipeline Contractor that was installing 4 pipelines alongside their existing pipelines, making sure they didn’t get close or hit the lines.
May 2008 to Aug 2008
Mustang Engineering, Houston, TX.
Inspector
Road and RR bore inspector on the MinnCan 24” pipeline (Henkles & McCoy) in Minnesota, to the refinery in Farmington, MN.
Aug 2007 to Mar 2008
SPT Energy Group, Abbyville, LA.
Senior Inspector
Fabrication of pipeline, riser clamps and riser and installation of the above in 455’ of water in the Gulf of Mexico. His included the Sub Sea Tie-in
Mar 2007 to July 2007
Williams E&C Midstream, Houston, TX.
Inspector Coordinator-Chief Offshore
Overseeing the installation of a Hot Tap, installation of a side tap assembly, Pipeline installation, connecting to the side tap assy. testing, and commissioning of the line (Sub Sea). Deep water Xings and mat placements.
Mar 2006 to Mar 2007
The Clement Companies – Dade, La. –
Offshore Construction Manager
Overseeing well conductor and platform/piping repairs for APACHE Corp. All the inspections & QA for acceptance of work done, for the repair of damage done by the hurricanes in 2005. Rework and rebuild of tankage to API – 650.
Sep 2005 to Mar 2006
Fluor – Greenville, S.C. YAMBU, Saudi Arabia
Construction Superintendent
Installation of a new section and upgrade of a polymer shipping chips plant.
Overseeing the installation of Mobil Homes, Park Trailers, and they had to be installed to FEMA and local regulations. Travel Trailers in the Lake Charles area ( District 4 ). QA/QC of all installed units.
Mar 2005 to Sep 2005
Mustang Eng. Houston, TX. For Hunt Petroleum – Houston
Construction
Manager for deep water (385’) offshore pipeline lays, tie-ins to side taps, Tie-ins to risers, Riser installation, hydro testing & dewatering of various lines. QA inspection and acceptance of fabrication of tie-in pieces & risers to API 1104.
Mar 2004 to Mar 2005
Fluor Daniels & Williams Bros. Sugarland, TX
Chief Pipeline Inspector
Fed DOT pipeline upgrade, Wood River 12” hydro’s from Ponca City, OK. to Glen Pool, OK. Monitored and approved different hydro tests to up-grade the pipeline.
Nov 2003 to Feb 2004
Fluor Arabia Ltd.
Area Superintendent
In a petrochemical plant in Yambu, Saudi Arabia. In charge of the Polymer area to make sure the all the upgrades and new systems were installed correctly and on time during a plant shutdown. Fabrication of Storage tanks to API – 650.
Oct 2003 to Nov 2003
OCI Houston TX. For Gulfterra (El Paso)
Construction Manager
Offshore admin for the installation of Marco Polo (TLP) pile and tendons F 4300, hull & topside 6500 tons. Inspection for pipeline installation.
May 2002 to Oct 2003
Construction Management Group, Mustang Engineering Co.
Construction Manager
Caracas, Venezuela, Curacao, N.A., Trinidad /Tobago, W.I.
Made 4 constructability studies for PDVSA. These were: The setting of an Amine contactor, 85’-6” X 12’-0”dia. & an Amine K.O. Drum (Vert.) 38”-0’ X 10’-0”. The complete retraying (33) trays, of a Naptha Splitter. The building of a 72’ pentane sphere and the building of a complete ISAL Unit, including the setting of a debutenizer 150’ X 16’, 2 – reactors that weigh over 180 ton each. Made 3 constructability studies for Isla Refinery in Curacao, of an addition of a new ISAL Unit and an addition of a new reactor for Platformers. Construction Manager for Deep Water Well Tie-Back and platform up-grade. Acceptance of all QC works to various codes, for vessels, piping, electrical and instrumentation. This work included a 24’’ pipeline to the beach of 83 kilometers. The multiple tie-ins and setting of an new HP Separator, Hipps Skid and tie-back to the new wells (600ft. water depth). Spent a short time in EG Africa.
Nov 2001 to Apr 2002
Fluor Maintenance Group – Houston,
Mechanical & Piping Superintendent
Superintendent on night shift for a refinery rebuild (Crude Unit) in Lemont, IL.
I was responsible of each of the 3 Mech./piping contractors to get started on the fire rebuild, including the start of installation of the 28 down comers on the crude column, 24’ X 153’. After getting these contractors started, I was in charge of 2 of these contractors for most of the time. This was a major fire rebuild with over 5000 spools that were installed. This was done in less than 6 months. My contractors had the best safety audit averages, because I motivated them to have safety awareness and good housekeeping.
Jun 2001 to Oct 2001
Chief Inspector/ Pipelines and facilities –ONEOK Gas Transmission Line, Tulsa, Ok
Chief of Inspection
Made hot tie-ins to lines. I made daily reports as to actual progress. I accepted facilities and completed pipelines to API 1104 & B31.8. I had the contractor work to an ecological and environmentally safe way of installation.
Apr 2001 to May 2001
Parsons Construction Services, in Maturin (Boqueron) Venezuela
Area Superintendent
E/I and piping. Set 2 – 250 ton compressor and driver units, Mammout did this. The client Company decided that they were over budget.
Aug 1999 to Aug 2000
PIC of Marietta, Ga. for Siemen’s Mexico, in Mexico
I/E Construction and Commissioning Manager
Hired 8 of the 12 pump station supervisors and got them set up. Took care of, on a day-by-day basis, all of the engineering and problems that this job entailed. These 12 PUMPSTATIONS were spread over 1200 Km. distance from one end to the other end. Logistics was terrible. Made sure that all the protocols for turnover and start-up from each station superintendent were correct and complete.
Apr 1998 to Dec 1998
Mustang Engineering, Houston, TX. In Nigeria (MOBIL OIL) and in Argentina for (Gasoducto nor Andino) - (Southern Energy)
Construction & Start-up Coordinator
Revamp and addition to QIT oil storage facility and construction of 2 new 750,000 BBl
Oil storage tanks in Eket, Nigeria
In Argentina - Site Construction Manager - 5 months
Day by day- Owners management of the construction of 115 kilometers of 20" X-70 pipeline, being installed by Techint, from Pichenal (elev. 280 Mts.) to Abra de Zenta (elev. 4250 Mts.).I had 15 inspectors and 5 people in my environmental group. Day by day communications in Spanish, reports done in English.
Feb 1997 to Mar 1998
ABB Randall Corp. Houston, TX. In Pucallpa, Peru
Pipeline Construction Coordinator
Liaison between (client) Aguaytia Energy (Duke Energy) and Bolinter from (Bolivia) (pipeline contractor) for ABB Randall Corp. for the installation, inspection, all documentation for turn over to the client and start-up of app. 300 Km. of 2", 3", 4", 6", 10", 12" pipeline (including the gathering and re-injection lines), from the Amazon jungle into the foothills of the Andes Mountains. All communications were in Spanish.
Nov 1996 to Jan 1997
CBS Engineering - Houston, Texas, Gulf of Mexico, Mexico
Chief Inspector
Walked out and up-dated P&ID'S for 6 platforms. Did an API 14C safety audit of 48 offshore platforms and an 850mmf/da. Gas plant for PEMEX de México. All meetings and communications were in Spanish.
Feb 1996 to Oct 1996
Staatsolie Oil Co. of Suriname
Consultant
Responsible to Staatsoile for the construction and start-up of a 10,000bbl. /da. De-watering/treating facility, app. 10Km. of 10" pipeline and a 6,000bbl. /da. pump station.
May 1995 to Dec 1995
Fluor/Daniels -- Escondida, Chile South America
Pipeline Superintendent
Responsible for the installation, inspection, testing, documentation and the start-up of app. 120Km. of 4", 6", 10", 20", 24", 34" pipeline, hook-up of 26 well sites and a 270,000 Gal./min. pump station. The pipeline contractor was Techint (Argentina).All documentation and meetings were in Spanish.
Jan 1995 to Apr 1995
Fluor/Daniels Taft, La. for Union Carbide
Area Superintendent
Took the P& ID’s, walked out the systems to see if in fact everything was in place as per P&ID, if not, wrote up notification of the discrepancies. After corrections, would allow the testing of each system to take place, walk them down and accepted them for Union Carbide when acceptable. Completed all the paper work for the acceptance of the systems as they were completed.
Sep 1993 to Nov 1994
CBS Engineering
Construction & Start-Up Superintendent
Grass Roots installation of a 10,000 BBL. /day. Treating, Dewatering, Pumping and Storage Facility in Venezuela. In charge of all the construction, I/E, inspection, QA/QC acceptance and start-up of this facility. This included a Westinghouse 501 Simple Cycle, of which I was responsible for hook-up and commissioning. This was a complete Spanish Contract including Contracts, Contractors, Documents, Labor and Direction.
Dec 1992 to Jul 1993
Fluor Arabia Ltd.; Saudi Arabia for Aramco
Area Superintendent-Onshore/Offshore
For the Onshore Part, I coordinated with the Contractor to make sure that over 2,000 Large Bore (8"-36") Heavy Wall (.500-1.875) Pipe Spools were fabbed, X-rayed, Stress relieved, Sand Blasted, painted and then shipped Offshore for a 9 platform turn-a-round and upgrade from ANSI 150# systems to ANSI 300# systems. Offshore I was the turn-a-round and start-up Superintendent for a Platform Complex (3 Platforms). This was a 30-day shut down. The platforms were completed and started up in 21 days.
Oct 1991 to Aug 1992
Staatsolie Oil Co. Of Suriname, South America
Chief Consultant & Superintendent
Responsible to STAATSOLIE to order all the major equipment, review and order all the major materials, make a detailed time schedule as to material & pipe placement, labor and equipment locations and time allotments for the countries first major pipeline - 14" .250 wall X-60 pipe-55 kilometers long. This included 17 road crossings, 2 river & 4 canal crossings, 3 road bores, 1 push/pull area of 8 kilometers and app. 4-5 kilometers of Terrain that was underwater. I was also in charge of building 2 pump stations and one receiver station, (Tie in to existing facilities) 3 areas. My responsibilities included, leveling 4 pumps, and all the piping and hot Tie-ins, setting and piping up the pig launcher and pig receiver, all the instrumentation, monitor the training of 35 welders to API 1104 and 4 welders to B.31.3. Also, testing of the total pipeline to 1800 PSIG and all the pump stations, launcher and receiver to 1800 PSIG. I set-up the QA/QC procedures for his complete project. Taught the people how to operate 571's and 572's side booms. In charge of start up. The job was completed without a loss time accident.
1990 to 1991
Williams Bros.
Senior Inspector / Start-up Superintendent
Shop inspector for the fabrication of two 2600 HP offshore single module gas compressor packages. The installation, hook-up and start-up of one of these units. The installation of four 1000HP gas compressors, the complete compressor station to include the DeHy unit and all associated equipment. Plant start-up. Installation, hook-up and commissioning of a Westinghouse 501 Combined Cycle Unit, for thermo reinjection, in California.
1988 to 1990
Williams Bros.
Chief Inspector/Shop Inspector
Inspect and accept offshore pipe lays riser installations, setting of platforms, the pile-driving, and pipeline mechanical hook up. Inspection and repair acceptance of oils storage tanks of API 650 Code and API 1104 for lines connected to the tanks. Inspection of 95 miles installation of cross-country fiber optic cable, this includes installation of many regen-stations and splices each 15,000 ft.
1987 to 1988
Brown and Root, Houston, Texas
Coordinator/Superintendent
Planning and scheduling of major demolition and reconstruction of the internals a 50,000 bbl/day cat regen, cat stripper, and reactor. Also Alky, HCU, MEK, CCU, Merox, Toppers, Udex, and Platformers units for Marathon Oil Texas City, TX. and Norco, LA.
1987
Citrus Hill - Frost Proof, Fl.
Instructor
Teaching employees the operation and maintenance of citrus processing equipment and machinery; Fl.
1986
Arco Oil & Gas, Houston, Texas
Chief Inspector
Construction inspection of a 60,000 bbl/day NGL pump station: authorized field construction changes and made all as-built drawings.
1985
Williams Bros.
Piping/Mechanical Superintendent
Grass roots project on construction a 160,000 bbl/day, oil dewatering facility. Fabrication and installation of well head to flow line tie-in piping. Responsible for two 16-man crews laying two 12" lines through the Llanos, including two river crossings where the push/pull method was implemented. Fabrication of oil storage tanks to API 650. These jobs were simultaneously in the Llanos area in Columbia, South America, monitoring and trouble shooting fabrication of ASME rated heaters and pressure vessels for our project. Then went to the area of construction, ordered out tools and took charge of the piping, welding and rigging and the tank erection crews. All directions, such as, tool and material orders, were given in Spanish
1985
Piping Foreman
Supervision of pipe fitter, welders, and insulators on construction of a rock refinery facility in VA. Orders most of the tools used by the pipe fitters, welder, and insulators. Instructed and supervised these crews how to do there job safely, orderly and in a professional manner within a completion date and time frame. Plant start up.
1984
Brown and Root
Area Supervisor
Supervision all crafts and turn-a-rounds, petro-chemical, and plant maintenance projects in the Houston Area.
1983
Pyle Const. Edmond, Ok.
Project Superintendent
Construction, additions, and remodeling of fast food restaurants: obtained permits, ordered materials, supervised sub-contractors, etc.
1982
Mcdermott Int.
Piping Superintendent
Installation and hook-up of 10 oil-gas platforms for process, Zakum Field, offshore Abu Dhabi, UAE. Supervised structural and piping installation for start-up of 10 platforms and start-up.
1981
Arco Oil and Gas
Chief Inspector
Installation of compressor station, construction and start-up of Cryogenic plant.
1980 to 1981
Mcdermott Int.
General Crafts Foreman
Supervised all crafts, all testing, installation, and start-up of an Offshore compressor station and LNG plant, Abu Dhabi, UAE.
1980
Pemex De Mexico
Project Superintendent
Supervised all construction and testing of a cyrogenic plant, Vera Cruz, México. Also, involved one 6" and one 8" pipelines; laid approximately five miles to a Hot Tap locations and completed tie-ins.
1975 to 1980
Mcdermott Int.
Superintendent/Foreman
Responsible for supervision of construction and installation of piping and equipment for LNG plant in Jebel Ali, UAE; a chlorine petro-chemplant in the Houston, TX area, Arco Oil and Gas - Fluor Const. and Eng., installation and start-up of an NGL marine refining and loading terminal in Jakarta, Indonesia; also construction of offshore platforms; Ju' Aymah, Saudi Arabia and Dubai, UAE. Responsible for setting of major equipment on offshore platforms, including, 1400 ton deck sections, 300 to 400 ton generators, compression packages and 350 person living quarters.