CURRICULUM VITAE
MOHAMMED ILIYAS ATIQ
MOBILE NO : - 0091-988-***-**** (India)
E-MAIL : - **********@*****.**.**
******@*****.***
ADDRESS : - H.NO.12-2-790/129
MEHDIPATNAM, HYDERABAD. INDIA
Civil Engineer / Supervisor having THIRTEEN years of expertise experience
in Civil Construction specialized for Electrical Power & Distribution
Substations in Oil / Gas and Petrochemical projects.
As Follows,
Construction of Electrical Substations, Polymer Plants [PP, LLDPE, HDPE,
EPPE, Butane] and Oil and Gas Refineries [Gas Treatment Plant, Sulphur
Recovery Unit Export Gas Unit, Gas Turbines, Sulphur Solidification Unit].
Expertise Experienced in Piling / Foundations, Interconnecting Pipe racks,
Heavy Equipment Foundations, Silo Foundations, Underground Piping's,
Underground Trenches (Electrical and Instrument), Blast proof Designed
Buildings, Electrical Substations, Process Interface Buildings, Extrusion
Buildings, Product Warehouse, Bagging Units, Paving and Fireproofing for
Steel Structure and Equipments. Asphalt/ Concrete Roads and Infrastructure.
Worked with Civil Department as Coordinator and focal point for all Civil
works. Worked with Field Engineering for modifications and change works if
required. Worked with QA/QC Department and Worked with Mechanical
Completion Group (MCG) for Handover Systems and Subsystems. Worked with Pre
commissioning Group for UG /AG Pipelines Inspections of Test packs Flushing
Blowing and handover to Client.
EXPERIENCE PATH :
Period
APR- 2013 TILL DATE
OCT-2010
APR-2013
DEC-2008
AUG-2010
JAN-2007
NOV-2008
JULY-2006
DEC-2006
JAN-2004
JUNE-2006
JAN-2003
DEC-2003
JAN-2001
DEC-2002
Company
PPPI CONSTRUCTION
MANAGEMENT & TECHNICAL
SERVICE
TECNIMONT SPA ITALY
TECNIMONT ICB
TECNIMONT ARABIA LTD
RAMKY INFRASTRUCTURES
LTD
JOG ENGINEERING LTD
SGA (JV) BUDHRANI
BUILDERS
SADIQ & CO
Position
CIVIL ENGINEER /
SUPERVISOR
CIVIL SUPERVISOR
CIVIL ENGINEER
CIVIL SUPERVISOR
PROJECT ENGINEER
SITE CIVIL ENGINEER INC
SITE ENGINEER
SITE ENGINEER
Country
IRAN
IRAN
INDIA
SAUDI
ARABIA
INDIA
INDIA
INDIA
INDIA
NATURE OF EXPERIENCE IN BRIEF :
CURRENT EMPLOYER
LOCATION
PERIOD OF EMPLOYMENT
DESIGNATION
NAME OF PROJECT
COST OF PROJECT
CLIENT
JOB RESPONSIBILITIES :
: PPP International : TOMBAK, IRAN
: 15th APRIL 2013 TO TILL DATE
: CIVIL ENGINEER / CIVIL SUPERVISOR
: SOUTH PARS GAS FIELD DEVELOPMENT
PHASE-12 EPC3
: 2 BILLION US $
: PETROPARS LTD.
I worked for this project as Civil Engineer / Supervisor for the
Construction of Gas Processing Facilities with PPPI as leader of consortium
of five companies. I was responsible for the Construction & Execution
activity of all civil woks consists of 05 Electrical
Substations, Heavy Equipment / Structure Foundations, Pipe racks,
Underground
Networks etc. as per AFC Drawings & Contract Specification. Inspection of
civil works as
per ITP Coordinating with clients & partners time to time, day to day
monitoring Making micro planning of the project with considering scheduled
date, attends inspections as per ITP checking all the works suggesting
innovative methods in the interest of completion of project within
stipulated time using all materials as per approval and project standards
from start till finish. Responsible for related communications,
Participates in the development of quality control reports and procedures.
Participates in development of job safety practices. Performs other
responsibilities associated with this position as determined by the Site
Manager.
RECENT EMPLOYER
LOCATION
PERIOD OF EMPLOYMENT
DESIGNATION
NAME OF PROJECT
COST OF PROJECT
CLIENT
JOB RESPONSIBILITIES :
: TECNIMONT SPA ITALY
: TOMBAK, IRAN
: OCTOBER 2010 TO 15th APRIL 2013
: CIVIL ENGINEER
: SOUTH PARS GAS FIELD DEVELOPMENT
PHASE-12 EPC3
: 2 BILLION US $
: PETROPARS LTD.
I worked for this project as Civil Engineer for the Construction of Gas
Processing Facilities with TECNIMONT as leader of consortium of five
companies. I was responsible for the Construction & Execution activity of
all civil woks consists of 05 Electrical Substations, Equipment
Foundations, Pipe racks, Underground Networks etc. as per AFC Drawings &
Contract Specification. Inspection of civil works as per ITP Coordinating
with clients & partners time to time, day to day monitoring Making micro
planning of the project with considering scheduled date, attends
inspections as per ITP checking all the works suggesting innovative methods
in the interest of completion of project within stipulated time using all
materials as per approval and project standards from start till finish.
Responsible for related communications Participates in the development of
quality control reports and procedures. Participates in development of job
safety practices. Performs other responsibilities associated with this
position as determined by the Site Manager.
EMPLOYER LOCATION
PERIOD OF EMPLOYMENT
DESIGNATION
NAME OF PROJECT
: TECNIMONT ICB
: PANIPAT INDIA
: DECEMBER 2008 TO AUGUST 2010
: CIVIL ENGINEER
: CONSTRUCTION OF POLYMER
PLANTS (PP1 & PP2) PACKAGE EPCC-2A
PANIPAT NAPHTA CRACKER PROJECT
HARYANA INDIA
COST OF PROJECT : 350 MILLION US $
CLIENT : INDIAN OIL CORPORATION LIMITED
JOB RESPONSIBILITIES :
I worked for this project as Civil Engineer for the Construction of Polymer
Plants for TECNIMONT. The Polymer Plants are PP1, PP2 03 Electrical
Substations & PRODUCT WAREHOUSE. I was responsible for the Construction &
Execution activity of all civil woks as per AFC Drawings & Contract
Specification. Attends civil and structural witness tests, such as soil
compaction,
moisture content, concrete slumps, concrete compression, lines and grades
survey and concrete coring. Attends destructive and non-destructive tests
Performs surveillance of underground piping to ensure tightness, bedding,
and grade. Responsible for Site Inspection of civil works as per ITP
Coordinating with clients & subcontractors time to time, day to day
monitoring Making micro planning of the project with considering scheduled
date conducting weekly progress meetings & for mechanical completion,
maintaining the work
completion schedule preparing all necessary documents. Attends inspections
as per ITP
checking all the works suggesting innovative methods in the interest of
completion of project within stipulated time using all materials as per
approval and project standards from start till finish. Responsible for
total related correspondence. Participates in the development of quality
control reports and procedures. Participates in development of job safety
practices. Performs other responsibilities associated with this position as
determined by the Site Manager.
EMPLOYER : TECNIMONT (ARABIA LTD.)
LOCATION : RABIGH SAUDI ARABIA
PERIOD OF EMPLOYMENT : JANUARY 2007 TO NOVEMBER 2008
DESIGNATION : CIVIL ENGINEER
NAME OF PROJECT : CONSTRUCTION OF POLYMER PLANTS
COST OF PROJECT
CLIENT
JOB RESPONSIBILITIES
PACKAGE PC1 & PC3 PETRORABIGH
SAUDIARABIA
: 770 MILLION US $
: SAUDI ARAMCO PETRORABIGH
:
I worked for this project as Civil Engineer for the construction of polymer
plants for TECNIMONT ARABIA LIMITED. The polymer plants were 03 Electrical
Substations LLDPE, EPPE, HDPE & BUTENE.I was responsible for the
Construction & Execution activity of all civil woks as per AFC Drawings &
designs. Coordinating with clients & subcontractors time to time, Involved
in inspections as per ITP checking all the works suggesting innovative
methods in the interest of completion of project within stipulated time
using all materials as per approval and project
standards from start till finish. The details of works done are as follows,
UNDERGROUND
. Piling activity, pile caps.
. Heavy structural & equipment foundations, Transformer Foundations. .
Underground pipeline for oily sewer water line, pits, Basins.
. Excavation for laying Electrical & Instrumentation cables directly
buried Duct banks,
Electrical & Instrument pits, backfilling after completion.
. Sanitary sewer line, pits. . Potable water line, pits.
. Fire water line risers, valves.
ABOVEGROUND
. Electrical Sub Stations, Process Buildings, Control Buildings,
Extrusion Buildings
having R.C.C. Deck Slab.
. R.C.C. Blast proof Design Buildings & block work, Finishing including
plaster &
painting complete.
. Waterproofing on Slabs of Substations & buildings.
. Fireproofing on Structural members, Equipment supports, pipe support
which are
under Fire Hazard Zone.
. Drain Trenches, Concrete paving.
. Road Sub base, Base course, Bituminous course.
. Gravel Spreading in unpaved area.
. Firewalls (Fire protection walls) for Equipments as per requirements
by safety.
. Road Side Kerb Stones provided for protection for Firewater Valves &
risers of fire
water line.
. Finishing all the works including painting and all finishes and
handover.
EMPLOYER : RAMKY INFRASTRUCTURES LTD.
LOCATION : HYDERABAD INDIA
PERIOD OF EMPLOYMENT : JULY 2006 TO DECEMBER 2006 DESIGNATION :
PROJECT ENGINEER INCHARGE
NAME OF PROJECT : CONSTRUCTION OF RAMKY REPOSE
HI-TECH CITY HYDERABAD INDIA
COST OF PROJECT : 250 MILLION INR
CLIENT : RAMKY ESTATES & FARMS PVT.LTD.
JOB RESPONSIBILITIES :
I worked for this project as Project Engineer in charge for the
construction of Ramky Repose situated in Hi-Tech City Hyderabad. I was the
total site in charge of this site and responsible for the Planning,
Construction, Execution, material procurement, fixation of subcontractors &
PRW allocation of day to day work to them, achieving progress as per
planning. I was responsible for Quality tests of material like sand,
cement, concrete, steel etc,Testing on site & cube testing after curing
periods in approved laboratory .I was overall in charge of all activities
performed at site including civil woks managing funds from concerned
department, managing all the job activities for smooth completion of
project as per given schedule.
Coordinating with clients & subcontractors time to time. Involved in
inspections as per plan, checking all the works suggesting innovative
methods in the interest of completion of project within stipulated time
using all materials & manpower as per requirement from start till
finish. The details of works are as follows,
. Planning of work as per given schedule
. Manpower & material management
. Fixation of subcontractors & PRW
. Allocation of works and maintaining daily progress report
. Maintaining all the testing records and conducting the tests for all
construction
materials
. Preparing company RA bill and subcontractors bills
. Conducting progress meetings with my team, Clients & consultants
EMPLOYER LOCATION
PERIOD OF EMPLOYMENT
DESIGNATION
NAME OF PROJECT
COST OF PROJECT
CLIENT
JOB RESPONSIBILITIES
: JOG ENGINEERING LTD.
: MUMBAI INDIA
: FROM 2004 TO JUNE 2006
: SITE CIVIL ENGINEER INCHARGE
: CONSTRUCTION OF SLUM REHABILATION
PROJECT S.P.P.L. MUMBAI INDIA
: 880 MILLION INR
: MAHIMTURA CONSULTANTS P. LTD.
:
I was involved in all civil engineering activities related to construction
& execution of
buildings & infrastructure work from start to finish .All the jobs has been
carried out as per
approved drawings and designs. The project consists of 33 buildings of
G+ 7 structures 03 Electrical Substations . The type of building
construction was precast type. I was responsible for planning, allocation
of work, supervision handling precast activities at precast yard and
erection of members with proper planning and schedule, and time bound
completion of project. I was responsible for preparation of monthly company
bills & piece rate workers ( PRW) and coordinating with clients and
consultants time to time and completion of project
as per given schedule of project. The details of construction works are as
follows
. In charge of a section and responsible for each and every construction
activity
. Have done piling works and pile caps for building foundations
. Precast concrete yard for buildings and casting all members like piles
for building
foundations, slabs, wall panels concrete blocks etc.
. Proper planning for erection of various members as per day to day plan
. Casting columns and columns caps in situ
. Construction of 03 Electrical substations including transformer
foundations.
. Construction of shops,Roads,Drains, sewer line & landscaping area .
Preparation of Monthly Company bills & P.R.W. bills.
. Progress meetings & meetings with clients
. Maintaining Daily progress of work & Schedule as per plan
EMPLOYER LOCATION
PERIOD OF EMPLOYMENT
DESIGNATION
NAME OF PROJECT
CONSULTANTS
JOB RESPONSIBILITIES
: SGA (J.V.) BUDHRANI BUILDERS
: THANE MUMBAI INDIA
: FROM 2003 TO 2004
: SITE ENGINEER
: IMPROVEMENT TO ROAD FROM OLD COTTON MARKET TO SHEGAON UNDER I. R.D.P.
M.S.R.D.C. MUMBAI INDIA
: CONSULTING ENGINEERING
SERVICES
:
The work was a road project. I was responsible for total site activities
such as allocation of work supervision and time bound completion of
project. Have taken levels drawn cross sections and l - sections with level
data, was responsible for total billing activities such as preparation
submission, approval from department.
EMPLOYER
PERIOD OF EMPLOYMENT
DESIGNATION
NAME OF PROJECT
CONSULTANTS
JOB RESPONSIBILITIES
: SADIQ & COMPANY NAGPUR
: FROM 2001 TO 2003
: SITE ENGINEER
: 100 BEDDED SUBDISTRICT HOSPITALS.
INDIA
: DESHMUKH MANAGEMENT
CONSULTANCY
:
Execution of work as per Construction and Architectural drawings and R.C.C.
Consultants, layout marking,site planning supervision with quality control
also responsible for all related activities and billing procedures.
PERSONAL DETAILS :
RESIDENTIAL ADDRESS
DATE OF BIRTH
MARITIAL STATUS
EDUCATIONAL
QUALIFICATION
COMPUTER SKILLS
PASSPORT NUMBER
NATIONALITY
DRIVING LISCENCE
Yours sincerely
Mohammed. I. Atiq
: H.NO.12-2-790/128, Ayodhya Nagar Colony
Mehdipatnam HYDERABAD - 28
: 01 / 11 / 1979
(First of November nineteen seventy nine)
: Married
: Diploma In Civil Engineering
: MS OFFICE, BASIC AUTOCAD
: Z-1927856 (Valid up to 26/02/2022)
: INDIAN
: Having Valid Indian Driving License of L.M.V.